Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

ELD.TO ·

Eldorado Gold Provides Skouries Project Update; 2025 Detailed Company Production & Cost Guidance; Updated Three-Year Growth Profile; Conference Call Details

Financials

1

NEWS RELEASE

TSX: ELD NYSE: EGO February 5, 2025

Eldorado Gold Provides Skouries Project Update;

2025 Detailed Company Production & Cost Guidance;

Updated Three-Year Growth Profile; Conference Call Details

(All dollar figures are in US dollars, unless otherwise stated)

VANCOUVER, BC - Eldorado Gold Corporation (“Eldorado” or “the Company”) today provides an update on the

construction progress at its copper-gold Skouries Project (“Skouries” or the “Project”), detailed 2025 production and

cost guidance, and three-year production outlook.

As previously disclosed, labour market tightness in Greece, particularly pronounced in construction, has continued to

limit the availability of key construction personnel at Skouries, resulting in a slower ramp -up of the workforce and

delayed progress in certain areas of the Project. To address these constraints, Eldorado recently undertook, and has

now completed, a comprehensive bottom -up analysis to evaluate, and where possible , mitigate their impact on the

Project schedule and costs. This analysis included an optimization of the production plan, which is now expected to

provide earlier access to higher grade ore through early start-up of mining operations and to facilitate efficient process

plant commissioning.

First production at Skouries is now expected in the first quarter of 2026, followed by commercial production expected

in mid-2026. The revised Project capital cost estimate incorporates an increase of approximately $1 43 million or

15.5% over prior capital cost estimates, to a total of approximately $1.06 billion. In addition, the Company expects to

complete additional pre-commercial production mining and has accelerated the purchase of higher capacity mobile

mining equipment (originally expected to be purchased post commercial production), resulting in $1 54 million of

accelerated operational capital prior to commercial production.

The revised schedule and cost estimates remain sensitive to a successful workforce ramp up, with a target of

maintaining approximately 1,300 workers on site through the peak of construction activities. The Company continues

to make progress, achieving a daily on-site total of approximately 1,150 workers at the end of January. The workforce

risk will remain after ramping up to the required personnel, as the Company continues integrating and managing

diverse skill sets (concrete, mechanical, electrical and control systems) needed to support the unfolding work fronts.

As of December 31, 2024, the Company has incurred approximately $512 million of capital expenditures at Skouries,

with approximately $7 05 million of remaining expenditures expected to achieve commercial production, including

accelerated operational capital.

The Company maintains a strong financial position, with approximately $ 857 million of cash and cash equivalents (1)

and total liquidity(2) of approximately $1.1 billion as of December 31, 2024. The project remains fully funded through

a combination of our balance sheet and remaining undrawn amounts under the Company’s Skouries Project finance

facility. Year-end liquidity has been further augmented by the divestment of our G Mining Ventures holding in January

2025 for proceeds of $155 million.

(1) Cash position reflects the Company’s cash balance and cash equivalents. Amounts are unaudited.

(2) Total liquidity includes the cash balance and availability on the senior secured facility. Amounts are unaudited.

2

“While we have revised the start-up and cost estimates, we remain confident in Skouries’ long-term value, highlighted

by an initial 20-year mine life that is expected to have a transformational impact on our production and cost s,” said

George Burns, President and CEO. “ Skouries will increase our operational scale and strengthen our foundation for

sustainable growth and long-term value. We continue to operate responsibly and sustainably and the Skouries Project

will continue to be a significant contributor to the Greek economy and local communities, with hundreds of jobs and

significant social investments for the people of the Aristotle Municipality.

“Our updated 2025 gold production guidance is expected to be between 460,000 and 500,000 ounces. This has been

lowered from our prior outlook provided in 2024 to reflect the change in initial production at Skouries from the third

quarter of 2025 to the first quarter of 2026. In addition, guidance at both Kisladag and Olympias has been lowered

compared to our prior 2025 guidance provided in 2024. At Kisladag, expected production has been impacted by longer

than planned leach cycles and lower grade stacked. At Olympias, production guidance has been impacted by a delay

in mill expansion commissioning to 650 ktpa and unscheduled maintenance of the gold concentrate filters.

“Our costs have increased due to wage pressures in Turkiye and Quebec and increased royalties across the global

portfolio due to the anticipated continuation of high er gold prices. In Turkiye, the increase is primarily the result of

inflation not currently being fully offset by the depreciation of the Lira against the US dollar. At the Lamaque Complex

the increase is primarily the result of wage pressure from a competitive labour market in Quebec and deepening of

the mine and lower grade in the top of Lower Triangle.”

Skouries Cost Variance

The revised cost estimates reflect a mid-2026 commercial production date with variances allocated to either Project

Capital or Accelerated Operational Capital.

Table 1. Skouries Project –Cost Estimates ($Millions)

Category

Previous Revised Incurred Remaining

Estimate Estimate (Dec-31-24) (Dec-31-24)

Project Capital 920 1,063 505 558

Accelerated Operational

Capital 0 154 7 147

Total Capital and Cost 920 1,217 512 705

Project Capital

The Project Capital cost variance relates primarily to:

• Indirect Costs : Certain fixed monthly costs, such as those associated with the owner's team, EPCM,

insurance, and general administration, will be incurred over an extended construction period.

• Quantity of Materials: Higher expected quantities of materials such as concrete, steel, and piping, identified

during completion of detailed engineering in compliance with Greek engineering standards.

• Other: Escalation in the unit rates from the construction contractors and other items.

Table 2. Project Capital – Variance from Previous Estimate ($Millions)

Category Variance

Indirect Costs 86

Materials 36

Other 21

Total Variance 143

3

Accelerated Operational Capital

The Company has reviewed and optimized the open pit and underground mine start -up and production plans. With

commercial production now expected in mid-2026, the Company expects to incur additional mining costs through to

commercial production of approximately $154 million. These accelerated operational capital costs reflect the following:

• Pre-Commercial Mining: The Company continues to progress the operationalization of mining activities and

expects to complete additional pre-commercial production mining in both the open pit and underground mines

ahead of commercial production. This will provide better continuity of our mining teams and faster access to

higher-grade ore, enabling the mill to process higher -quality material during 2026. This plan is expected to

deliver gold and copper production volumes in 2026 in line with prior guidance.

• Open Pit: Trade-off studies for the open pit mine support a faster transition from contract mining to an owner-

operated model. This has accelerated the purchase of higher capacity mobile mining equipment, including

five Cat 777 haul trucks and three additional load ing units. The combination of these larger 100 -tonne haul

trucks versus the 20-tonne haul truck fleet being required for construction of civil works and switching to an

owner-operated model is expected to increase overall efficiency and lower life of mine unit costs. The studies

also support transitioning from a two-phase to a four-phase open pit, accelerating access to higher grade ore

while optimizing waste stripping.

• Underground: Underground development is progressing well with a leading European contractor, which is

also deploying a multi-year training program to develop the local workforce and enhance large-stope mining

capability. The longer period of underground mining prior to commercial production provides additional time

to complete the required development metres, which, combined with the completion of test stoping , derisks

overall production plans. As previously guided, test stoping is expected to be completed within 2025.

Table 3. Accelerated Operational Capital ($Millions)

Category Estimate

Mining Equipment 47

Mining & Mobile Maintenance 67

Other 40

Total Variance 154

Project Status

As of December 31, 2024, phase 2 of the Project was 60% complete. D etailed engineering and procurement were

substantially complete.

4

2025 Production and Cost Guidance

2025 Guidance

Lamaque

Complex Kisladag Efemcukuru(3) Olympias(3,4) Skouries

Project Total

Gold Production

(000’ oz)

170 – 180 160 – 170 70 – 80 60 – 70 460 – 500

Silver Production

(000’ oz)

1,300 – 1,500 1,300 – 1,500

Lead Production

(000’ t)

12 – 15 12 – 15

Zinc Production

(000’ t)

12 – 15 12 – 15

Tonnes Processed

(millions) 0.95 – 1.00 13.20 – 13.60 0.53 – 0.55 0.50 – 0.52

Gold Grade

(g/t) 5.50 – 6.20 0.65 – 0.75 4.80 – 5.30 7.50 – 8.50

Total Cash Costs(1)

($/oz sold)

790 – 890 1,020 – 1,120 1,300 – 1,400 1,020 – 1,120 980 – 1,080(5)

All-in Sustaining Costs(1)

($/oz sold)

1,290 – 1,390 1,200 – 1,300 1,560 – 1,660 1,280 – 1,380 1,370 – 1,470(5)

Capital Expenditures

($ millions)

Sustaining Capital(1) 85 – 95 25 – 30 15 – 20 20 – 25 145 – 170

Operations - Growth

Capital(1,2)

70 – 75 115 – 125 15 – 20 45 – 50 245 - 270

Operations -

Sustaining and Growth

Capital(1,2)

155 – 170 140 – 155 30 – 40 65 – 75 390 – 440

Skouries -

Construction Project

Capital(1)

400 – 450 400 - 450

Skouries - Accelerated

Operational Capital(1) 80 – 100 80 - 100

(1) These financial measures are non-IFRS financial measures. Certain additional disclosures for non-IFRS financial measures and ratios have

been incorporated by reference and additional detail can be found at the end of this press release in the section titled ‘Non-IFRS and Other

Financial Measures and Ratios.’

(2) Includes capitalized exploration at the Lamaque Complex and Efemcukuru.

(3) Payable metal produced.

(4) Olympias by-product grades: Silver: 90 – 120 g/t; Zinc: 4.0 – 4.5%; Lead: 3.5 – 4.0%.

(5) Totals may not add based on the averaging of costs.

Gold production in 2025 is expected to be between 460,000 and 500,000 ounces which reflects the following:

• First production from Skouries in 2026 rather than 2025.

• At Kisladag, expected production has been impacted by longer than planned leach cycles and lower grade

stacked.

• At Olympias, expected production has been impacted by a delay in mill expansion commissioning to 650ktpa,

and unscheduled maintenance of the gold concentrate filters.

Similar to prior years, quarter -to-quarter gold production in 202 5 is expected to fluctuate with higher production

expected in the second half as a result of ore grade variability across the portfolio and the impact of winter conditions

at Kisladag.

Total cash costs(1) in 2025 are expected to be between $9 80 and $1,080 per ounce sold and an average AISC (1) of

$1,370 to $1,470 per ounce sold. The expected increase in 2025 costs is driven by forecasted higher labour costs as

a result of inflation particularly in Turkiye, as well as lower production, increased sustaining capital and higher royalty

expense, partially offset by higher by-product credits.

5

(1) Total cash cost per ounce sold and AISC per ounce sold are non-IFRS financial measures. Certain additional disclosures for non-IFRS financial

measures and ratios have been incorporated by reference, and additional detail can be found at the end of this pre ss release and in the section

‘Non-IFRS and Other Financial Measures and Ratios.’

Exploration and evaluation expenditures are expected to be between $29 and $32 million in 2025, with 88% expensed,

and 12% capitalized. General and administrative expenses are expected to be between $35 and $38 million in 2025,

and depreciation expense is expected to be between $250 and $270 million.

OPERATING MINES:

CANADA

Lamaque Complex

In 202 5, production guidance of 170,000 to 180,000 ounces at the Lamaque Complex is unchanged from the

previously guided range. In 2025, the focus remains on further resource conversion drilling at Triangle and Ormaque

and the completion of a second bulk sample.

Total cash costs and all-in sustaining costs per ounce sold are expected to increase as a result of the deepening of

the mine and lower grade in the top of Lower Triangle , in addition to increased labour costs as a result of wage

pressures due to the tight labour market in Quebec and increased royalties due to the anticipated continuation of

higher gold prices.

Sustaining capital expenditures of between $85 and $95 million for 202 5 are expected to include significant

underground mine development and resource conversion drilling at the Triangle deposit , as we target the C8 zone.

Expected growth capital of between $70 and $75 million for 2025 primarily includes development and infrastructure

to access the Ormaque deposit, construction of the North Basin, a new water basin that is expected to extend the life

of the Sigma tailings storage facility and construction of the paste plant.

TURKIYE

Kisladag

In 2025, production guidance of 160,000 to 170,000 ounces at Kisladag is slightly lower than the previously guided

range of 175,000 to 185,000 ounces, primarily due to lower grade as a result of recent mine plan optimization adjusting

to avoid an area of local cultural significance. Also, as previously disclosed in the third quarter of 2024, the Company

has incorporated the longer leach cycle and coarse ore particle performance in its guidance. The Company continues

to focus on irrigation optimization efforts , which have demonstrated positive results on gold inventory reduction ,

partially offsetting the longer leach cycle. In addition, an engineering study is underway to confirm optimal recovery,

leach kinetics and process throughput and is expected to be completed in mid-2025.

Total cash costs and all-in sustaining costs per ounce sold are expected to be impacted by inflation not currently being

fully offset by the depreciation of the Lira against the US dollar , and increased royalties due to the anticipated

continuation of high gold prices.

Planned 2025 sustaining capital of between $25 and $30 million includes the increased total material that is expected

to be moved (+2.6Mt) as the Company transitions from Phase 4 to Phase 5 and begin pre -stripping of Phase 6,

resulting in h igher demand from the mobile fleet and related equipment overhauls. Planned 2025 growth capital of

between $115 and $125 million includes the continuation of the capitalized waste stripping campaign and the phased

expansion of the North Heap Leach Pad, in addition to capital for the engineering study and long lead items.

Efemcukuru

In 2025, production guidance of 70,000 to 80,000 ounces is unchanged from the previously guided range. Total cash

costs and all -in sustaining costs per ounce sold are expected to be negatively impacted by increased labour costs

and electricity costs. Higher labour costs are expected as a result of inflation not currently being fully offset by the

depreciation of the Lira against the US dollar, and increased royalties due to the anticipated continuation of high gold

prices.

6

Planned sustaining capital expenditures of between $15 and $20 million for 2025 includes underground development

and equipment purchases. The planned growth capital of between $15 and $20 million for 202 5 is expected to be

primarily focused on development and infrastructure for expansion of the Kokarpinar vein system including portal

construction and development of the Bati vein systems , foll owing the additional two-year mine life extension

announced in December 2024.

GREECE

Olympias

In 2025, production guidance of 60,000 to 70,000 ounces at Olympias is expected to be lower than the prior guidance

due a delay in mill expansion commissioning to 650ktpa and unscheduled maintenance of the gold concentrate filters.

Total cash costs and all-in sustaining costs per ounce sold are expected to be positively impacted by increased by -

product metal sales partially offset by increased royalties due to the anticipated continuation of high gold prices .

Continued quarter to quarter variability in AISC and total cash costs is expected due to by-product credits from timing

of by-product concentrate shipments.

Planned 2025 sustaining capital expenditures of between $20 and $25 million include underground mine development

and management of the Kokkinolakas tailings management facility. Planned 2025 growth capital of $45 to $50 million

is primarily focused around the mill expansion to support the ramp-up to 650 ktpa , capitalized development and a

resource conversion drilling program.

Three-Year Outlook Overview:

• Gold production of between 660,000 and 720,000 ounces by 2027, resulting in growth of 33% over the three-

year period compared to 2024 production.

o Delivering consistent safe production from robust long-life assets.

o Unlocking mineral value across the portfolio through expansion and development.

o Skouries commercial production in mid-2026.

o Addition of copper, a critical mineral to the portfolio.

• Continued focus on exploration to unlock the outstanding potential of the Company’s brownfield property

portfolio and to the identification and development of new opportunities in Eldorado’s focus jurisdictions.

2025 2026 (2) 2027 2024 Actual

Gold Production (000’ oz)

Lamaque Complex 170 – 180(1) 180 – 190 175 – 185 197

Kisladag 160 – 170 135 – 145 165 – 175 174

Efemcukuru 70 – 80 75 – 85 70 – 80 80

Olympias 60 – 70 80 – 90 80 – 90 70

Skouries 135 – 155(2) 170 – 190

Total Gold Production 460 – 500 605 – 665 660 – 720 520

Copper Production (Mlbs)

Total Copper Production

Skouries 45 – 60 60 – 80

Silver Production (000’ oz)

Total Silver Production

Olympias 1,300 – 1,500 1,550 – 1,750 1,750 – 1,950

Lead Production (t)

Total Lead Production

Olympias 12,000 – 15,000 15,000 – 18,000 17,000 – 20,000

7

Zinc Production (t)

Total Zinc Production

Olympias 12,000 – 15,000 18,000 – 21,000 19,000 – 22,000

(1) Includes expected production ounces from the second bulk sample process at Ormaque.

(2) Includes expected pre-commercial production from Skouries. Skouries’ commercial production is expected in mid-2026.

2025 Assumptions and Sensitivities

Commodity and Currency Price

Assumptions

Gold ($/oz) 2,300

Silver ($/oz) 28.00

Lead ($/mt) 2,050

Zinc ($/mt) 2,700

USD : CDN 1 : 1.33

EUR : USD 1 : 1.05

USD : TRY (Q1) 1 : 35.00

USD : TRY (Q2) 1 : 37.00

USD : TRY (Q3) 1 : 39.00

USD : TRY (Q4) 1 : 41.00

Sensitivities 2025 Change Operating Sites Local

Currency Exposure AISC ($/oz sold)

Gold Price $2,300 $100 ~8

USD : CDN 1 : 1.33 $0.05 90% ~20

EUR : USD 1 : 1.05 $0.05 95% ~15

Qualified Person

Except as otherwise noted, Simon Hille, FAusIMM , Executive Vice President, Technical Services and Operations, is

the Qualified Person under National Instrument 43-101 responsible for preparing and supervising the preparation of

the scientific or technical information contained in this news release and for verifying the technical data disclosed in

this document relating to our operating mines and development projects.

Jessy Thelland, géo (OGQ No. 758), a member in good standing of the Ordre des Géologues du Québec, is the

Qualified Person as defined in N ational Instrument 43-101 responsible for, and has verified and approved, the

scientific and technical data contained in this news release for the Quebec projects.

Data is verified through the internal reviews of life of mine plans on a site-by-site basis which confirms the expected

production outputs along with the expected revenue and cost distribution.

8

Conference Call

Senior management will host a conference call to discuss the details of the Company’s Skouries Project Update and

Guidance on Thursday, February 6, 2025 at 11:30 AM ET (8:30 AM PT). The call will be webcast and can be accessed

at Eldorado’s website: www.eldoradogold.com or via this link:

https://event.choruscall.com/mediaframe/webcast.html?webcastid=hXu5PtUk

Participants may elect to pre -register for the conference call via this link:

https://dpregister.com/sreg/10196352/fe619f1800. Upon registration, participants will receive a calendar invitation by

email with dial in details and a unique PIN. This will allow participants to bypass the operator queue and connect

directly to the conference. Registration will remain open until the end of the conference call.

Conference Call Details Replay (available until March 20, 2025)

Date: Thursday, February 6, 2025 Vancouver: +1 412 317 0088

Time: 11:30 AM ET (8:30 AM PT) Toll Free: 1 855 669 9658

Dial in: +1 647 484 8814 Access code: 1502892

Toll free: 1 844 763 8274

About Eldorado

Eldorado is a gold and base metals producer with mining, development and exploration operations in Turkiye, Canada

and Greece. The Company has a highly skilled and dedicated workforce, safe and responsible operations, a portfolio

of high-quality assets, and long -term partnerships with local communities. Eldorado's common shares trade on the

Toronto Stock Exchange (TSX: ELD) and the New York Stock Exchange (NYSE: EGO).

Contact

Investor Relations

Lynette Gould, VP, Investor Relations, Communications & External Affairs

647 271 2827 or 1 888 353 8166

[email protected]

Media

Chad Pederson, Director, Communications and Public Affairs

236 885 6251 or 1 888 353 8166

[email protected]

Non-IFRS and Other Financial Measures and Ratios

Certain non-IFRS financial measures and ratios are included in this news release, including total cash costs, all -in

sustaining cost ("AISC"), growth capital costs, and sustaining capital costs. The Company believes that these

measures and ratios, in addition to conventional measures and ratios prepared in accordance with Internation al

Financial Reporting Standards (“IFRS”), provide investors an improved ability to evaluate the underlying performance

of the Company. The non-IFRS and other financial measures and ratios are intended to provide additional information

and should not be co nsidered in isolation or as a substitute for measures or ratios of performance prepared in