ENDEAVOUR ANNOUNCES WET COMMISSIONING IS UNDERWAY AT SABODALA-MASSAWA BIOX® EXPANSION First gold expected in May · Project on schedule and on budget with no LTIs · 91% project completion

Mine Development & Operations

1

NEWS RELEASE – LSE & TSX: EDV

ENDEAVOUR ANNOUNCES WET COMMISSIONING IS

UNDERWAY AT SABODALA-MASSAWA BIOX® EXPANSION

First gold expected in May · Project on schedule and on budget with no LTIs · 91% project completion

HIGHLIGHTS:

• Over 3 million man hours have been completed with zero lost-time injuries

• Wet commissioning is underway with overall construction activities 91% complete

• Expansion project on budget and on schedule with the first gold pour expected in May

• Sabodala-Massawa is expected to produce between 360-400koz at a sector leading AISC of between $750-

850/oz in FY-2024

• Sabodala-Massawa is the largest exploration focus this year with a guided spend of $21 million

Dakar, 27 February 2024 – Endeavour Mining plc (LSE:EDV, TSX:EDV, OTCQX:EDVMF) (“Endeavour”, the “Group”

or the “Company”) is pleased to announce that wet commissioning activities are now underway at the Sabodala-

Massawa Expansion project (“BIOX® Expansion”) in Senegal. The BIOX® Expansion project is on budget , with

construction now 91% complete, and the first gold pour is expected on schedule, in May.

Ian Cockerill, CEO, commented: “We are extremely pleased with our progress as we start wet commissioning at

the BIOX® Expansion project. Importantly, we have achieved this milestone with no lost -time injuries having

worked more than 3 million man hours, which is a testament to the strong safety culture that is a hallmark of our

in-house construction teams.

At completion, Sabodala-Massawa will become a true top tier asset with 2024 production of up to 400koz at an

industry leading AISC of less than $850/oz, with costs expected to improve further in the coming years, embedding

the mine firmly in the lowest cost quartile.

This year, Endeavour is well positioned to transition from a phase of investment in organic growth, to a more cash

flow generative phase in the second half of the year. This inflection point will allow us to focus our efforts on

increasing our shareholder returns programme while de-levering our balance sheet, as we continue to execute on

our strategy.”

Wet commissioning of the BIOX® Expansion was delivered in less than 23 months after construction was launched

in April 2022. During construction activities, up to 1,300 employees and contractors were on site, 82% of whom

were Senegalese nationals, successfully completing over three million man-hours with zero lost time injuries.

The addition of the 1.2Mtpa BIOX® Expansion, with an initial capital cost of $290 million, is expected to add

194koz per annum of incremental production over the first five years, lifting Sabodala-Massawa to top-tier status

with expected production of 360-400koz at an AISC of between $750-850/oz in FY-2024, increasing to above 400koz

from 2025.

2

Figure 1: BIOX® Expansion project overview highlighting construction activities at 91% complete

Figure 2: Crushing circuit construction is complete and wet commissioning of the primary jaw crusher is underway

3

Figure 3: Milling circuit construction is complete and wet commissioning of the ball mill (left) and the SAG mill (right) is underway

Figure 4: Flotation circuit construction is largely complete and sulphide concentrate is expected to be delivered to the BIOX® circuit in

early March

4

Figure 5: BIOX® reactors wet commissioning is underway with BIOX® inoculum active and starting to fill the first reactor

Figure 6: BIOX® inoculum currently active in the back-up reactor

5

Figure 7: CIL tank construction is largely complete

Figure 9: Elution and electrowinning circuit construction is largely complete with wet commissioning planned for early March

6

Figure 10: Gold room construction is largely complete with first gold pour expected in May

Figure 11: Tailings storage facility (“TSF”) 1b comprising two HDPE lined cells has been completed

7

Figure 12: 18MW HFO power plant expansion was completed and successfully energised during Q4-2023,

increasing the capacity of the existing power plant by 50%

8

ABOUT THE SABODALA-MASSAWA MINE

The Sabodala-Massawa mine was acquired by Endeavour in February 2021, as part of its acquisition of Teranga.

Endeavour owns a 90% stake in the Sabodala-Massawa mine, with the remaining 10% owned by the Government of

Senegal.

Located approximately 630 km east-southeast of Dakar, the capital of Senegal, the Sabodala-Massawa mine consists of

several open pit operations on the highly prospective Birimian Greenstone Belt. Non-refractory ore is treated at a

4.0Mtpa CIL plant that achieved commercial production in November 2009. In 2021, Endeavour expedited the

completion of the initial upgrades at the existing CIL plant and simultaneously advanced the definitive feasibility study

for the addition of a refractory ore processing plant to confirm the economic viability of processing the high -grade

refractory ores from the Massawa Central Zone and Massawa North Zone deposits. In 2022, Endeavour launched the

construction of the 1.2Mtpa BIOX® circuity to process the large refractory ore resource with first gold expected in May

2024. As at 31 December 2022, Proven and Probable reserves totalled 62.8Mt at 2.02 g/t containing 4.1Moz of gold

and Measured and Indicated resources (inclusive of reserves) totalled 106.1Mt at 1.86 g/t containing 6.3Moz of gold.

For the full year ended 31 December 2023, Sabodala-Massawa produced 294koz at an AISC of $ 767/oz. For FY-2024,

Sabodala-Massawa is expected to produce between 360-400koz at an AISC of between $750-850/oz.

Sabodala-Massawa is Endeavour’s largest exploration focus this year with a guided spend of $21 million, or 31% of total

Group exploration expenditure for the year. The exploration programme is focussed on expanding non-refractory and

refractory resources for the existing CIL processing plant and the new BIOX® Expansion respectively. The exploration

programme remains on track to achieve its 5-year target of discovering an additional 2.3-2.7Moz of Indicated resources

by the end of 2025.

QUALIFIED PERSONS

Mark Morcombe, COO of Endeavour Mining PLC., a Fellow of the Australasian Institute of Mining and Metallurgy,

is a "Qualified Person" as defined by National Instrument 43 -101 - Standards of Disclosure for Mineral Projects

("NI 43-101") and has reviewed and approved the technical information in this news release.

CONTACT INFORMATION

Jack Garman

Vice President, Investor Relations

+442030112723

[email protected]

Brunswick Group LLP in London

Carole Cable, Partner

+442074045959

[email protected]

ABOUT ENDEAVOUR MINING CORPORATION

Endeavour Mining is one of the world’s senior gold producers and the largest in West Africa, with operating assets

across Senegal, Cote d’Ivoire and Burkina Faso and a strong portfolio of advanced development projects and

exploration assets in the highly prospective Birimian Greenstone Belt across West Africa.

A member of the World Gold Council, Endeavour is committed to the principles of responsible mining and

delivering sustainable value to its employees, stakeholders and the communities where it operates. Endeavour is

listed on the London and Toronto Stock Exchanges, under the symbol EDV.

For more information, please visit www.endeavourmining.com.