Endeavour Silver Provides Q4 2023 Construction Progress Update On the Terronera Mine

Mine Development & Operations

Endeavour Silver Provides Q4 2023 Construction Progress Update On the

Terronera Mine

VANCOUVER, British Columbia, Feb. 12, 2024 -- Endeavour Silver Corp. (“Endeavour” or the “Company”) (NYSE:

EXK; TSX: EDR) provides a Q4 2023 construction progress update for its Terronera Project in Jalisco state, Mexico. A photo

gallery presentation accompanies this news release and can be found here or on the Company website at Terronera Project

Progress Photos. All dollar ($) references in this news release are United States dollars.

The Terronera project has made significant construction progress to date. Concrete work is well advanced, and erection of

structural steel for the grinding and flotation areas has started. In early 2024, the Company provided an Updated Initial Capital

Cost (“2024 Updated Scenario”), which increased the project budget by $41 million to $271 million. This increase was primarily

due to a stronger Mexican Peso, ongoing inflation and availability of bulk materials such as steel, piping and electrical

supplies (see news release dated January 24, 2024 ). As of December 31, 2023, approximately $120 1 million had been

invested in direct project expenditures, with project commitments totaling $171 1, 2 million or 63% of the updated budget. With

an experienced and seasoned team leading the project, the Company anticipates the schedule will remain in line with previous

guidance, with initial production anticipated to start in the fourth quarter of 2024.

“Throughout 2023, we’ve achieved several major milestones across multiple fronts,” commented Don Gray, Chief Operating

Officer. “We’ve concentrated our efforts on completing key items including earthworks for our Upper Mill Platform, procurement

of equipment, and advances in plant concrete. Our underground mine development continues to advance rapidly as we look to

start ore development sometime in Q2 2024. We’re extremely satisfied with Terronera’s progress thus far and remain

committed to successfully completing and operating Endeavour’s next core asset.

Q4 2023 Construction and Development Highlights

As of December 31, 2023, site works and activities included:

• Safety – Our strong onsite safety focus continues: The Project finished 2023 with 172 days totaling over 600,000

manhours with no lost-time accidents.

• Progress – Overall project progress reached 43% completion including a 3% reduction due to the adjusted weighting

related to the 2024 Updated Scenario. The project remains on track for commissioning in Q4 2024.

• Engineering – Detail engineering for the mill and infrastructure began transitioning to construction support towards the

end of 2023. Excavation designs for the Lower Platform and detail design for Tailing Storage Facility (“TSF”) have been

advanced using supplemental geotechnical investigation results obtained in Q4 2023.

• Mine Development – Over 2,200 metres of underground development were completed in 2023. The in-house mining

team has been successfully transitioning from using contracted to direct-hire labor with greater development

efficiencies. Development was focused on Portal 1, 2 and 4 declines for accessing ore and setting up the main

ventilation circuit and haulage way; the Portal 4 incline broke through to surface and preparations are underway to

complete the portal structure in Q1 2024.

• Plant Site – Surface mill and infrastructure construction is now almost 50% complete; concrete works were well

advanced to allow the start of vertical construction in early Q1 2024. The electromechanical contract was awarded and

mobilization commenced.

◦ Primary Crusher – Concrete has been completed for the jaw crusher foundation and the perimeter walls,

including backfill and compaction.

◦ Course Ore Stockpile and Reclaim Tunnel – The Coarse Ore Stockpile support walls have been completed along

with the roof including the feeder chute imbeds. For the reclaim tunnel, concrete has been completed for two

major roof sections with two sections remaining.

◦ Grinding – The concrete of the grinding area is nearly complete and being prepared for release to the general

contractor to begin structural steel and mechanical installations.

◦ Flotation – The concrete of the flotation cell pedestals is nearly complete and being prepared for release to the

general contractor to begin structural steel and mechanical installations.

◦ Thickener – The thickener tank support pedestals were completed and was backfill initiated. Concrete work has

been started for the raw water, process water, thickener surge, and concentrate storage tank pedestals and

foundations.

• Lower Facilities Platform and TSF – Access road construction has commenced from the Lower Platform and TSF area

to the Upper Mill Platform.

• Procurement – Focused on procuring bulk materials, including structural steel, piping, and electrical cable following a

comprehensive scheduling for delivery that tracks construction requirements.

• Onsite Personnel – The workforce had increased to 126 employees and 400 contractor workers.

• Community Relations – Supporting the local municipality has continued to be a major focus with sponsoring cultural

and community activities in the area.

• Environmental – Environmental and social assessment initiatives continue according to schedule as outlined under the

Equator Principal requirements for project loan financing.

2024 Outlook and Planning

Endeavour remains focused on advancing the Terronera Project for initial production in Q4 2024, with a comprehensive

schedule and plan under the 2024 Updated Scenario.

For Q1 2024, surface construction will focus on completing concrete work to allow structural steel erection, mechanical

installations and initial electrical work for the crushing, coarse-ore stockpile, grinding, flotation and tailing thickener areas.

Early in Q2, excavation is anticipated to be complete for the Lower Platform, which includes facilities such as the LNG and

power generation areas and the concentrate and tailing filtration areas. For Q2 and Q3, work is planned for all mill and

infrastructure areas with mechanical completion and commissioning activities planned in Q4.

For the mine, development in Portal 1, 2 and 4 declines will continue with first ore development anticipated in Q2. Initial long-

hole mining is planned for Q3 and cut-and-fill mining is planned with ore being stockpiled for mill ramp up. Development

activities at La Luz are expected to begin in Q3 with portal construction and ramp advance to ore access anticipated in Q4.

The critical path remains the TSF construction and advancing underground mine, where development efficiencies have been

steadily increasing.

The Company is well-positioned to satisfy the Terronera project financing requirements and expects the first draw under the

$120 million project loan debt facility in Q1 2024.

Dedicated Project Website

The Company has launched a dedicated project website, accessible at www.terronera.com, serving as a virtual hub for the

local community, key stakeholders, and other interested parties to stay informed and engaged with the ongoing progress of

the Terronera Project. The Company invites all stakeholders to explore the latest updates, learn about our commitment to

environmental stewardship and discover the positive impacts this venture will bring to local communities.

About the Terronera Project

The Terronera project is a high-grade silver-gold project being developed in the San Sebastian mining district in Jalisco state,

Mexico. It is located within the Sierra Madre volcanic belt, which hosts most of Mexico’s gold and silver deposits. It is a low-

sulphidation epithermal vein system that will be mined using a combination of long hole and cut and fill techniques. The

underground mine consists of two deposits, Terronera and La Luz, which will feed a centralized 2,000 tonne per day process

plant. Based on the Feasibility Study, Terronera is expected to produce 4 million ounces of silver and 38,000 ounces of gold

annually over its 10-year life.

For more information about the project and details of the Feasibility Study, the technical report is entitled “NI 43-101 Technical

Report on the Feasibility Study of the Terronera Project, Jalisco State, Mexico” dated October 21, 2021, with an effective date

of September 9, 2021, and it is available on the company website or under the Company’s name on SEDAR at

www.sedar.com.

About Endeavour Silver – Endeavour is a mid-tier precious metals mining company that operates two high-grade

underground silver-gold mines in Mexico. Endeavour is advancing construction of the Terronera Project and exploring its

portfolio of exploration projects in Mexico, Chile and the United States to facilitate its goal to become a premier senior silver

producer.  Our philosophy of corporate social integrity creates value for all stakeholders.

Contact Information

Galina Meleger, VP, Investor Relations

Email: [email protected]

Website: www.edrsilver.com

Follow Endeavour Silver on Facebook, X, Instagram and LinkedIn.

Footnote:

1. Financial figures are based on a preliminary estimate. Final audited figures will be released with the 2023 financial

statements on March 11, 2024.

2. Project commitments are inclusive of total project expenditures.

Cautionary Note Regarding Forward-Looking Statements

This news release contains “forward-looking statements” within the meaning of the United States private securities litigation

reform act of 1995 and “forward-looking information” within the meaning of applicable Canadian securities legislation. Such

forward-looking statements and information herein include but are not limited to statements regarding the development and

financing of the Terronera Project including: capital cost estimates, anticipated timing of the project construction; anticipated

timing of drawdown under the project loan debt facility, Terronera’s forecasted operations, costs and expenditures, and the

timing and results of various related activities. The Company does not intend to and does not assume any obligation to update

such forward-looking statements or information, other than as required by applicable law.

Forward-looking statements or information involve known and unknown risks, uncertainties and other factors that may cause

the actual results, level of activity, production levels, performance or achievements of Endeavour and its operations to be

materially different from those expressed or implied by such statements. Such factors include but are not limited changes in

production and costs guidance; the ongoing effects of inflation and supply chain issues on mine economics; national and local

governments, legislation, taxation, controls, regulations and political or economic developments in Canada, Chile, the U.S.A

and Mexico; financial risks due to precious metals prices; operating or technical difficulties in mineral exploration,

development and mining activities; risks and hazards of mineral exploration, development and mining; the speculative nature

of mineral exploration and development; risks in obtaining necessary licenses and permits; satisfaction of conditions

precedent to drawdown under the project loan debt facility; the ongoing effects of inflation and supply chain issues on the

Terronera Project economics; fluctuations in the prices of silver and gold, fluctuations in the currency markets (particularly the

Mexican peso, Chilean peso, Canadian dollar and U.S. dollar); and challenges to the Company’s title to properties; as well as

those factors described in the section “risk factors” contained in the Company’s most recent form 40F/Annual Information

Form filed with the S.E.C. and Canadian securities regulatory authorities.

Forward-looking statements are based on assumptions management believes to be reasonable, including but not limited to:

the continued operation of the Company’s mining operations, no material adverse change in the market price of commodities,

forecasted Terronera mine economics as of 2024, mining operations will operate and the mining products will be completed in

accordance with management’s expectations and achieve their stated production outcomes, and such other assumptions and

factors as set out herein. Although the Company has attempted to identify important factors that could cause actual results to

differ materially from those contained in forward-looking statements or information, there may be other factors that cause

results to be materially different from those anticipated, described, estimated, assessed or intended. There can be no

assurance that any forward-looking statements or information will prove to be accurate as actual results and future events

could differ materially from those anticipated in such statements or information. Accordingly, readers should not place undue

reliance on forward-looking statements or information.