Endeavour Silver provides a Q3 2024 construction progress update on Terronera; the surface construction progress has reached 77% completion

Mine Development & Operations

Endeavour Silver provides a Q3 2024 construction progress update on

Terronera; the surface construction progress has reached 77% completion

VANCOUVER, British Columbia, Oct. 21, 2024 -- Endeavour Silver Corp. ("Endeavour" or the "Company") (NYSE:

EXK; TSX: EDR) is pleased to provide a Q3 2024 construction progress update for its Terronera Project in Jalisco state,

Mexico. A photo gallery presentation accompanies this news release and can be found here or on the Company website at

Terronera Project Progress Photos . All dollar ($) references in this news release are in United States dollars.

The Terronera project made substantial progress during the third quarter as the Upper Plant Platform nears completion.

Surface mill and infrastructure construction reached 90%, further preparing for advancement into operations. Focus continues

on the Lower Platform, where concrete work is well underway, and the Tailing Storage Facility, with underdrain embankment fill

and pipe installation advancing at a good pace.

“We’re in the final construction phase with the finish line in sight,” commented Don Gray, Chief Operating Officer. “The Upper

Platform is nearly complete, and the primary jaw crusher was commissioned, with rock crushed in August. The major focus is

the Lower Platform and Tailing Storage Facility. Our dedicated Terronera team continues to meet the challenges both for

developing the mine and constructing the mill facilities to keep the project on track to begin commissioning systems near the

end of Q4.”

Q3 2024 Construction and Development Highlights

As of September 30, 2024, site works and activities included:

• Safety – Health and safety for operational readiness is underway. The mine rescue equipment arrived, and team

members are being recruited and trained. Two refuge stations were installed.

• Community Relations – Local community support continues to be a priority. In Q3, the Company supported a series of

local initiatives and investments such as: a municipal cooperative agreement; inauguration of an early-childhood

development center; scholarships for university students in Santiago de Pinos; municipal road maintenance; workshops

for business entrepreneurship for local residents; environmental education program for primary schools; community tree

donation; and summer community workshops for children and youth.

• Progress – Overall project progress (mine development and surface construction) reached 77% completion, with more

than $258 million 1 of the project's budget spent to date. Project commitments total $270 million 1,2, 99% of the $271

million capital budget.

• Mine Development – During the third quarter, 1,051 metres were developed underground for a project total of 5,544

metres. Furthermore:

◦ Underground explosive magazines were completed and the explosive use permit application was submitted for

approval, which is anticipated in Q4 2024.

◦ Terronera main sump and pump station excavation and support were completed.

◦ Development was nearly complete for the test stope that will be used to verify stope design criteria including

opening span widths, length and height as well as establishing longhole drilling, blasting and backfill procedures.

◦ Development ore was stockpiled on surface.

◦ Slashing of an existing portal commenced for access to mine the high-gold grade La Luz vein, which is

anticipated to be reached in H1 2025.

• Upper Plant Platform Site – Mill and surface infrastructure construction was 90% complete and continues to transition

to operations.

◦ Primary Crusher – Primary jaw crusher was commissioned with rock crushed in August, marking a major project

milestone.

◦ Coarse Ore Stockpile and Reclaim ("COS") Tunnel – Reached 100% completion and pre-commissioning tests

commenced.

◦ Grinding and Thickening – Piping, mechanical, electrical, and instrumentation are expected to be completed in

October.

◦ Flotation – Compressor pressure vessel and air dryer systems were installed with piping connections in

progress. Flotation equipment, including blowers, instrument, and valve installations are ongoing and scheduled

for Q4 completion.

◦ Raw and Process Water Tanks – Steel rings are in place and welding was over 90% complete. Inlet, outlet and

access port installations, final weld testing, sand blast/mechanical cleaning, and painting are scheduled for

completion in Q4.

• Lower Facilities Platform and Tailing Storage Facility (TSF) – Lower Platform area was nearly 30% complete. Focus

has been on completing the last section of the tailing filter bearing wall prior to starting the filter support deck; the first

structural steel columns and beams were erected for the Concentration Filter building and equipment mechanical

structures.

◦ Main Embankment TSF – Excavation for the main embankment key trench was 100% complete, the secondary

key was at 40% complete, and underdrain piping placement has been completed.

◦ Tailing Filtration Area – More than 75% of the floor slab and 100% of the filter bearing wall for the tailing filter

building has been poured. The tailing filters, which are stored at the Puerto Vallarta warehouse, are schedule to

be transported to site for Q4 2024 installation.

◦ Concentrate Filter Area – More than 80% of the floor slab and 75% of the pipe rack and equipment foundations

in the concentrate filter area has been poured, and tank foundations and equipment pedestals were nearly

complete.

• Auxiliary Buildings – Laboratory and Plant Maintenance buildings reached 40% of completion.

◦ Laboratory Building – Majority of the sheathing and insulation have been installed and steel studs are in place.

Sheetrock and compressor and dryer installations are in progress.

◦ Plant Maintenance Building – Structural steel installation started in late September.

• Procurement –The project team continues to expedite pending arrivals. Procurement was 99% complete.

• Onsite Personnel – At the end of Q3, the workforce increased to over 250 Endeavour Silver employees and over 800

contract workers, with the total number expected to decrease in Q4 2024 as commissioning begins.

Next Steps and Planning

The Terronera Project is tracking to begin commissioning systems near the end of Q4.

For Q4 2024, the tailing filter area, which was turned over to the mechanical contractor in early October, will allow focus on

installing at least one tailing filter along with the concentrate filter using an extended work schedule to allow initial systems

commissioning anticipated near the end of Q4. Grinding, flotation, and thickening systems will be mechanically completed in

late October, allowing testing and ramp-up of these circuits to begin in November and December.

Mine development in Portals 1, 2, and 4 declines will continue, with longhole stopes being developed and initial production

planned for Q4; ore will continue to be stockpiled for mill ramp-up. At La Luz, the portal is being constructed, and the orebody

ramp access will advance in Q4.

The critical path remains the TSF, tailing concentrate filters construction, and the advancing underground mine.

Visit www.terronera.com, our dedicated project website, to stay informed on the ongoing development at Terronera. Explore

updates, learn about our commitment to environmental stewardship, and discover the positive impacts on local communities.

About Endeavour Silver: Endeavour is a mid-tier precious metals company committed to sustainable and responsible

mining practices. With operations in Mexico and the development of the new cornerstone mine in Jalisco State, the Company

aims to contribute positively to the mining industry and the communities in which it operates. In addition, Endeavour has a

portfolio of exploration projects in Mexico, Chile, and the United States, which has helped it achieve its goal of becoming a

premier senior silver producer. 

Contact Information

Allison Pettit, Director of Investor Relations

Tel: (604) 640 4804

Email: [email protected]

Website: www.edrsilver.com

Follow Endeavour Silver on Facebook, X, Instagram and LinkedIn

Cautionary Note Regarding Forward-Looking Statements

This news release contains "forward-looking statements" within the meaning of the United States Private Securities Litigation

Reform Act of 1995 and "forward-looking information" within applicable Canadian securities legislation. Such forward-looking

statements and information herein include but are not limited to statements regarding the development and financing of the

Terronera Project, including capital cost estimates, the anticipated timing of the project construction and commissioning,

Terronera's forecasted operations, costs and expenditures, and the timing and results of various related activities. The

Company does not intend to and does not assume any obligation to update forward-looking statements or information other

than as required by applicable law.

Forward-looking statements or information involve known and unknown risks, uncertainties, and other factors that may cause

Endeavor's actual results, level of activity, production levels, performance, or achievements, and its operations to be

materially different from those expressed or implied by such statements. Such factors include but are not limited changes in

production and costs guidance; the ongoing effects of inflation and supply chain issues on mine economics; national and local

governments, legislation, taxation, controls, regulations and political or economic developments in Canada, Chile, the USA

and Mexico; financial risks due to precious metals prices; operating or technical difficulties in mineral exploration,

development and mining activities; risks and hazards of mineral exploration, development and mining; the speculative nature

of mineral exploration and development; risks in obtaining necessary licenses and permits; continued compliance with the

project loan debt facility; the ongoing effects of inflation and supply chain issues on the Terronera Project economics;

fluctuations in the prices of silver and gold, fluctuations in the currency markets (particularly the Mexican peso, Chilean peso,

Canadian dollar and US dollar); and challenges to the Company's title to properties; as well as those factors described in the

section "risk factors" contained in the Company's most recent form 40F/Annual Information Form filed with the SEC and

Canadian securities regulatory authorities.

Forward-looking statements are based on assumptions management believes to be reasonable, including but not limited to

the continued operation of the Company's mining operations, no material adverse change in the market price of commodities

forecasted Terronera mine economics as of 2024, mining operations will operate, and the mining products will be completed

under management's expectations and achieve their stated production outcomes, and such other assumptions and factors as

set out herein. Although the Company has attempted to identify important factors that could cause actual results to differ

materially from those contained in forward-looking statements or information, other factors may cause results to be materially

different from those anticipated, described, estimated, assessed, or intended. There can be no assurance that any forward-

looking statements or information will be accurate, as actual results and future events could differ materially from those

anticipated in such statements or information. Accordingly, readers should not place undue reliance on forward-looking

statements or information.

1 Financial figures are based on a preliminary estimate. Final unaudited figures will be released with the Q3 2024 financial

statements on November 5, 2024.

2 Project commitments include total project expenditures.