VANCOUVER, BC,

May 20, 2021

/CNW/ -

East Africa Metals Inc. (TSXV: EAM) ("East Africa",

"EAM" or the "Company") would like to provide an update on the ongoing exploration of its gold and

gold/copper/zinc projects in the Federal Democratic Republic of Ethiopia ("Ethiopia").

After productive meetings with government officials in

Addis Ababa

last week, the Company is

looking to building on the success achieved over the past ten years through the Company's

investment of approximately

$30,000,000

in exploration with the support of the Ministry of Mines and

Petroleum ("MoMP").

East Africa

is preparing to initiate a fully funded

$2,700,000

exploration program announced in early

2021 (see new release

February 1, 2021

). The six-month state of emergency declared in the Tigray

region was lifted on

May 4

th

, 2021. It is anticipated that commercial activity in the Tigray region will

normalize in the near future, as it recovers from the impacts of the COVID pandemic and the political

unrest.

EAM has completed the planning and received government approval for the

$2,700,000

Phase 1

exploration program that will include 8,000 meters of diamond drilling, 115 line kilometers of

geophysical surveys, environmental, metallurgical studies and resource calculations/updates. The

initiation of the Phase 1 diamond drilling program is expected to begin immediately after the

Government declares the region ready for field operations.

EAM's management has confidence in the potential of the Company's exploration assets in the

Tigray region and looks forward continued participation in what has become an active and emerging

exploration sector.

The Company has equal confidence in progressive policy initiatives of the Ethiopian government

under the administration of the recently appointed Minister of Mines, His Excellency Takale Uma.

Ethiopia's

MoMP has undertaken a program of major reforms to improve the Ethiopian Mining

Proclamation designed to align government policy with the needs of international and domestic

resource investors. These policy revisions should result in significant growth in

Ethiopia's

mining

sector, promoting the interests of both artisanal miners and exploration and mining companies by

improving the ease of access to licenses and finance for Small to Medium Enterprises (SME) and

large-scale miners.

Based on the sale of the 70% interest of EAM's Ethiopian subsidiary, Tigray Resources Inc. ("TRI")

to Tibet Huayu Mining Co. Ltd (news release dated

February 8, 2019

), EAM retains the mineral

rights and all exploration obligations for the prospective targets not incorporated in the current

resources defined within the Terakimti, Mato Bula and Da Tambuk mining licenses ("EAM Mineral

Resources"). EAM will advance the exploration agenda with the objective to expand and upgrade the

current resource base and drill untested, high priority exploration prospects.

Listed below are the exploration targets that host potential to improve current resources and

potentially increase the total resource base (news release dated

May 7, 2018

). Highest priority

exploration targets that have potential to increase the resource base will be the focus of Phase 1

drilling.

The Mato Bula Trend Exploration Targets

The Mato Bula Trend Exploration Targets (CNW Group/East Africa Metals Inc.)

Halima Hill I.P

. – Represents a compelling target as a large, open (to depth and southward) I.P.

chargeability anomaly extending laterally 500 metres south beyond the established Mato Bula

mineralization. The currently defined copper/gold mineralization increases in silver and zinc

content locally in the south region of the resource. Being an open I.P. target, the feature

requires drill qualification and has potential, with mineralization identification, to represent a

significant spatial increase to the known mineralized footprint. A key intersection in this area

includes 24.50 metres grading 0.61 grams per tonne gold, 1.67% copper, 8.0 grams per tonne

silver, and 0.96% zinc, from 204.30 metres (WMD027- news release dated

January 15, 2015

).

Halima Hill

is considered a high priority target.

Mato Bula Central – Results from the 2017 infill drilling program identified areas of potential high

grade mineralization for step out drilling to depth in the central area of Mato Bula.

Silica Hill – Resource mineralization remains open to depth.

Silica Hill North – Interpretation of geology and mineralization has been revised and additional

drill targets have been identified with the objective to build upon an initial intersection of 22.91

metres at 14.34 grams per tonne gold including 8.50 metres at 36.92 grams per tonne gold,

from 101.09 metres drill depth (WMD032- news release dated

January 15, 2015

).

Mato Bula North

- A separate copper enriched area of the existing resource remains open

laterally and to depth and requires further delineation drilling.

Da Tambuk Silica Ridge – Two target areas of artisanal workings, silica alteration and

anomalous multi-element soil geochemistry remains to be trenched and drill tested.

Da Tambuk deposit – Infill and extension drilling required (deposit currently open to depth and

south).

The Terakimti, VEM09 and Mayshehagne Exploration Targets

The Terakimti, VEM09 and Mayshehagne Exploration Targets (CNW Group/East Africa Metals Inc.)

The Company has identified a corridor of anomalous surface geochemistry between the

Terakimti deposit and the VTEM09 prospect (a six kilometre separation). The VTEM09

prospect has yielded a number of precious metal-rich VMS related intersections, including 24.06

metres grading 1.88% copper, 3.08 grams per tonne gold, 66.4 grams per tonne silver, and

2.54% zinc, from 35.84 metres drill depth (diamond drill hole TVD009 - news release

dated March 27, 2017). Additional drill work warranted in the Terakimti area includes;

Supergene - High grade copper mineralization delineation drilling.

Primary - VMS mineralization delineation drilling.

VTEM09 – Following qualifying metallurgical work and potential resource work, additional

diamond drilling would be warranted.

Mayshehagne VMS trend - A separate VMS trend centres on the Mayshehagne prospect,

located three kilometres south of Terakimti. Precious metal enriched copper-zinc mineralization

has been identified at this prospect, including 21.19 metres grading 4.32% copper, 1.04 grams

per tonne gold, 35.9 grams per tonne silver, and 6.98% zinc, from 36.58 metres drill depth

(diamond drill hole HD011 – news release dated

March 27, 2017

).

Mayshehagne – Following qualifying metallurgical work and potential resource work, additional

diamond drilling would be warranted.

Furthermore, additional target generation is recommended through deep and downhole EM

programs over prospective terrains at Harvest and I.P surveying along the untested Mato Bula

Trend terrain at Adyabo.

Management Discussion

The Company believes the work and advancement on the projects completed to date indicate both

the commercial production potential of the defined deposits and the significant exploration potential

of this area within the Arabian Nubian Shield. Management continues to believe there is excellent

potential for resource expansion within the Harvest and Adyabo properties, as described in the

EAM's news release dated May 17, 2018.

Government approval for the extension of exploration licenses and the proposed 2020 drill program

has been received. The initiation of the Phase 1 diamond drilling program is expected to begin

immediately after the Government declares the region ready for field operations.

EAM currently has three approved Mining Agreements with Ethiopia's Ministry of MoMP; the

Terakimti Oxide deposit Mining license has been issued (news release dated December 7, 2017)

and Mining Agreements for the Mato Bula and Da Tambuk deposits have been approved and

licences issued. For the additional prospective targets of interest that are located on ground outside

of existing mining licences, the Company has received Extension/Inclusion agreements from the

MoMP to allow additional time to qualify targets as they may complement existing Licence

resources.

Andrew Lee Smith

, P.Geo., C.E.O., a Qualified Person under the definitions of National Instrument

43-101, has reviewed and approved the technical contents of this news release.

More information on the Company can be viewed at the Company's website:

www.eastafricametals.com

On behalf of the Board of Directors:

Andrew Lee Smith

, P.Geo., CEO

Cautionary Statement Regarding Forward-Looking Information

This news release contains "forward-looking information" within the meaning of applicable

Canadian securities legislation. Generally, forward-looking information can be identified by the use

of forward-looking terminology such as "anticipate", "believe", "plan", "expect", "intend", "estimate",

"forecast", "project", "budget", "schedule", "may", "will", "could", "might", "should", "indicate" or

variations of such words or similar words or expressions. Forward-looking information is based on

reasonable assumptions that have been made by

East Africa

as at the date of such information

and is subject to known and unknown risks, uncertainties and other factors that may cause the

actual results, level of activity, performance or achievements of

East Africa

to be materially

different from those expressed or implied by such forward-looking information, including but not

limited to: timing of receipt of mining permit; timing of mining development; projected heap leach

recoveries ; early exploration; the closing of the agreement with the exploration and development

company to advance the Magambazi Project or identify any other corporate opportunities for the

Company; mineral exploration and development; metal and mineral prices; availability of capital;

accuracy of

East Africa's

projections and estimates, including the initial mineral resource for the

Adyabo, Harvest and Magambazi Properties; interest and exchange rates; competition; stock price

fluctuations; availability of drilling equipment and access; actual results of current exploration

activities; government regulation; political or economic developments; foreign taxation risks;

environmental risks; insurance risks; capital expenditures; operating or technical difficulties in

connection with development activities; personnel relations; the speculative nature of strategic

metal exploration and development including the risks of diminishing quantities of grades of

reserves; contests over title to properties; and changes in project parameters as plans continue to

be refined, as well as those risk factors set out in in

East Africa's

management's discussion and

analysis for the three months and nine months ended

September 30, 2018

and for the year ended

December 31, 2017

, and

East Africa's

listing application dated

July 8, 2013

Mineral Resources

which are not Mineral Reserves do not have demonstrated economic viability. The contained gold,

copper and silver figures shown are in situ. No assurance can be given that the estimated

quantities will be produced. Forward-looking statements are based on assumptions management

believes to be reasonable, including but not limited to the timely closing of the financing; the timely

closing of the Handeni Property definitive agreement; the price of gold, silver, copper and zinc; the

demand for gold, silver, copper and zinc; the ability to carry on exploration and development

activities; the timely receipt of any required approvals; the ability to obtain qualified personnel,

equipment and services in a timely and cost-efficient manner; the ability to operate in a safe,

efficient and effective manner; the renewal or extension of exploration Licences; the regulatory

framework regarding environmental matters, and such other assumptions and factors as set out

herein. Although

East Africa

has attempted to identify important factors that could cause actual

results to differ materially from those contained in forward-looking information, there may be other

factors that cause results not to be as anticipated, estimated or intended. There can be no

assurance that such information will prove to be accurate, as actual results and future events could

differ materially from those anticipated in such information. The Company does not update or

revise forward looking information even if new information becomes available unless legislation

requires the Company do so. Accordingly, readers should not place undue reliance on forward-

looking information contained herein, except in accordance with applicable securities laws. Neither

TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies

of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

SOURCE

East Africa Metals Inc.

View original content to download multimedia:

http://www.newswire.ca/en/releases/archive/May2021/20/c8226.html

%SEDAR: 00034410E

For further information:

Nick Watters, Business Development, Telephone +1 (604) 488-0822,

Email [email protected], Website www.eastafricametals.com

CO: East Africa Metals Inc.

CNW 16:05e 20-MAY-21