Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

EAM.V ·

East Africa Metals Provides Update on Magambazi Mine Plan Development

Corporate Updates

East Africa Metals Provides Update on

Magambazi Mine Plan Development

VANCOUVER, BC

,

Dec. 17, 2021

/CNW/ -

East Africa Metals Inc.

(TSXV: EAM) ("East Africa" or

the "Company") is pleased to provide an update on the progress of the engineering and mine

development work at the Magambazi mine in the Handeni region of the Federal Republic of

Tanzania

.

With the successful completion of the tailings processing in the third quarter of 2021, the technical

team for PMM Mining Company Limited ("PMM") are focused on the development of hard-rock

mining operations.

Phase I of the mining operations will be initiated on surface from two open pit resources, the "North

and "South" pits. These pits will be established on areas of the deposit representing approximately

15 percent of the recently upgraded one-million ounce Measured and Indicated resource (see

October 19, 2021

, press release).

Phase II of the mining operations will be conducted from underground where the resource within the

Magambazi ridge will be accessed from the valley floor,

200m

below the surface operations, to take

full advantage of gravity in the mining process.

Engineering work is progressing and detailed plans for mining operations and surface equipment

installations are expected to be complete early

January 2022

Infrastructure required to initiate and support surface mining operations continues to be upgraded

and expanded to increase milling capacity sufficient for surface open-pit operations. Development of

the access road to the South Pit site is underway.

3D perspective view of the Magambazi ridge and resource (looking northeast) (CNW Group/East

Africa Metals Inc.)

The processing flow-sheet continues to be refined and expanded to support the hard-rock mining

operations. The plans for the expansion of the crushing and grinding circuit continue to be developed.

Staged upgrades to the flow-sheet and processing plant will initially expand the capacity of the

existing circuit to 1,000 tonnes per day and ultimately to a capacity capable of supporting a 40,000

ounce production rate per year within forty-eight months of commissioning of the hard-rock mining

operations.

East Africa Metals has completed the formation of its Tanzanian gold trading company, "EMG

Royalty Plc.", in order to facilitate the acquisition of the Company's share of gold production from

the Magambazi mine. Under the terms of the sale purchase agreement with PMM, EAM holds the

rights to acquire 30% of the gold produced from the mining operations for a payment equal to the

per ounce cash costs of mining and processing plus 15%.

According to Q2 2021 processing reconciliations provided to EAM by PMM the tailings operations

produced a total of 645 ounces of gold. EAM's share of the Q2 2021production is 169 ounces with a

current value of

US$275,000

. The final transfer of the Magambazi mining licenses to PMM and

reconciliation of Q3 2021 processing are expected to be completed in early

January 2022

.

Andrew Lee Smith

, P.Geo., C.E.O., a Qualified Person under the definitions of National Instrument

43-101, has reviewed and approved the technical contents of this news release

About East Africa Metals

The Company's principal assets include a 30% Net Profits Interest in the Mato Bula and Da Tambuk

mines (collectively "Adyabo Property") and a 70% project interest in the Harvest polymetallic VMS

Exploration Project in the Tigray Region of

Ethiopia

. In addition, the Company has a 30% Net

Streaming Interest in the Magambazi Mine in the Tanga Region of Tanzania.

The Mato Bula and Da Tambuk mines are four kilometres apart and will be developed

simultaneously. The development of the mining operations is scheduled to begin during the second

half of 2021.

East Africa

retains exploration rights on areas of the properties outside the Mato Bula, Da Tambuk

and Terakimti mining licenses in all Ethiopian projects and anticipates the commencement of

exploration drilling to test priority targets during the second half of 2021.

EAM has invested

US$66.8M

in African exploration since 2005 and identified a total of 2.8 million

ounces of gold and gold-equivalent resources representing an average discovery cost per ounce of

US$24

.

The current Global Project Resources discovered by EAM include:

Project Resources (Au + Au

eqv

Metal ounces)

Project

Category

Au +Au

eqv

ounces

Adyabo Project, Ethiopia

(

EAM 30% Net Profit Interest)

Indicated

446,000

Inferred

551,000

Harvest Project, Ethiopia

(EAM = 70% Project Interest)

Indicated

469,000

Inferred

426,000

Handeni Project, Tanzania

(EAM = 30% Streaming Royalty Interest)

Measured & Indicated

*

1,006,000

Inferred

*

1,800

* Resource calculated based on 0.40 gAu/t cut-off – see October 19, 2021 press release for details)

More information on the Company can be viewed at the Company's website:

www.eastafricametals.com

.

On behalf of the Board of Directors:

Andrew Lee Smith

, P.Geo., CEO

Cautionary Statement Regarding Forward-Looking Information

This news release contains "forward-looking information" within the meaning of applicable

Canadian securities legislation. Generally, forward-looking information can be identified by the use

of forward-looking terminology such as "anticipate", "believe", "plan", "expect", "intend", "estimate",

"forecast", "project", "budget", "schedule", "may", "will", "could", "might", "should", "indicate",

"confident" or variations of such words or similar words or expressions. Forward-looking

information is based on reasonable assumptions that have been made by the Company as at the

date of such information and is subject to known and unknown risks, uncertainties and other

factors that may cause the actual results, level of activity, performance or achievements of the

Company to be materially different from those expressed or implied by such forward-looking

information, including but not limited to: statements regarding present and future plans and

objectives of the Company, the ability of PMM to meet minimum annual production, the ability of

PMM to make the payment if the minimum annual production is not met, the ability of PMM to

carry out hard rock mining operations, the Company's expected cash flows from royalties, the

negotiation of a definitive agreement with Zijin reflecting the anticipated structure and timing

outlined herein; the negotiation of a definitive agreement reflecting the anticipated structure and

timing outlined herein; delays with respect to required payments and regulatory approvals; results

of the due diligence review; the ability of Tibet Huayu to develop and operate the Ethiopia Adyabo

Project within the required laws and agreements; the ability of PMM to develop and operate the

Tanzanian Magambazi Project within the required laws and agreements; recoverability of the

Ethiopian and Tanzanian VAT receivable; early exploration; the ability of

East Africa

to identify any

other corporate opportunities for the Company; the possibility that the Company may not be able to

generate sufficient cash to service its planned operations and may be force to take other options;

the risk the Company may not be able to continue as a going concern; the possibility the Company

will require additional financing to develop the Ethiopian Projects into a mining operation; the risks

associated with obtaining necessary licenses or permits including and not limited to Ethiopian

Government approval of EAM Mineral Resources extensions for the Company's Ethiopian

Properties and Projects; risks associated with mineral exploration and development; metal and

mineral prices; the demand for precious and base metals; availability of capital; accuracy of the

Company's Projections and estimates, including the initial and any updates to the mineral resource

for the Adyabo, Harvest and Handeni Projects; realization of mineral resource estimates; interest

and exchange rates; competition; stock price fluctuations; the ability to carry on exploration and

development activities; actual results of exploration activities; availability of drilling equipment and

access; the ability to obtain qualified personnel, equipment and services in a timely and cost-

efficient manner; the regulatory framework including and not limited to license approvals, social

and environmental matters; the ability to operate in a safe, efficient and effective manner

government regulation; political or economic developments; foreign taxation risks; environmental

risks; insurance risks; capital expenditures; operating or technical difficulties in connection with

development activities; personnel relations; the speculative nature of strategic metal exploration

and development including the risks of contests over title to properties; and changes in project

parameters as plans continue to be refined, as well as those risk factors set out in the Company's

filings with securities regulators. Mineral Resources, which are not Mineral Reserves, do not have

demonstrated economic viability. The estimate of mineral resources may be materially affected by

environmental, permitting, legal, title, taxation, sociopolitical, marketing, or other relevant issues.

The quantity and grade of reported inferred mineral resources as the estimation is uncertain in

nature and there has been insufficient exploration to define any inferred mineral resources as an

indicated or measured mineral resource and it is uncertain if further exploration will result in

upgrading inferred mineral resources to an indicated or measured mineral resource category. The

contained gold, copper and silver figures shown are in situ. No assurance can be given that the

estimated quantities will be produced. Although the Company has attempted to identify important

factors that could cause actual results to differ materially from those contained in forward-looking

information, there may be other factors that cause results not to be as anticipated, estimated or

intended. There can be no assurance that such information will prove to be accurate, as actual

results and future events could differ materially from those anticipated in such information. The

Company does not update or revise forward looking information even if new information becomes

available unless legislation requires the Company to do so. Accordingly, readers should not place

undue reliance on forward-looking information contained herein, except in accordance with

applicable securities laws.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this

release.

SOURCE

East Africa Metals Inc.

View original content to download multimedia:

http://www.newswire.ca/en/releases/archive/December2021/17/c3777.html

%SEDAR: 00034410E

For further information:

Nick Watters, Business Development, Telephone +1 (604) 488-0822,

Email [email protected], Website www.eastafricametals.com

CO: East Africa Metals Inc.

CNW 16:05e 17-DEC-21