Discovery Announces 2024 Work Program for Cordero

Exploration Programs

Discovery Announces 2024 Work Program for Cordero

January 24, 2024, Toronto, Ontario - Discovery Silver Corp. (TSX: DSV, OTCQX: DSVSF)

(“Discovery” or the “Company”) is pleased to outline its 2024 work program for its Cordero

project (“Cordero” or “the Project”) located in Chihuahua State, Mexico.

Tony Makuch, President and CEO, states: “2024 is expected to be a transformational year for

the Company. Our Feasibility Study is nearing completion and is on track to be delivered later

this quarter. The study will incorporate an additional 35,000 m of drilling that highlighted the

potential to extend the mine life beyond the 18 years outlined in the Pre -Feasibility Study, as

well as the results from recent metallurgical testwork that demonstrated higher silver

payabilities and reduced reagent consumption.

“The Feasibility Study is expected to position Cordero as the only silver development stage

asset in the industry that will produce more than 30 million ounces of silver -equivalent

production annually once built. This impressive scale is accompanied by a long mine life,

excellent capital efficiency due to staged expansions of the process plant and operating costs

in the bottom half of the cost curve, emphasizing the strategic importance of Cordero within

the silver space. In 2024, we also look forward to moving our way through the permitting and

project financing process with the objective of reaching a construction decision in late 2024 or

early 2025. We remain well funded to deliver on our key milestones this year with a cash

balance at the end of 2023 of approximately C$60 million.”

ENGINEERING & PROJECT DEVELOPMENT

The Feasibility Study (“FS” or the “Study”) is expected to be delivered later this quarter. The

FS will incorporate staged expansions of the processing facility to maximize the capital

efficiency of the Project and will in clude an additional 35,000 m of reserve definition and

expansion drilling, the results from the FS metallurgical testwork program as well as additional

geotechnical and hydrogeology data collected in 2023. The Company will also provide an

updated resource estimate concurrent with the results of the Study.

Following the delivery of the FS the Company plans to commence Front-End Engineering

Design (“FEED”) work for the Project. This engineering work consists of early project planning

and will enable the Company to place orders for long lead- time items and to award the

EPC/EPCM contract for the development of the Project.

The Company plans to progress all financing options for the Project through the course of

2024. These options include equity, debt, offtake, joint ventures, partnerships, lease financing

on major equipment, streams, royalties and other strategic alternatives.

NEWS RELEASE

PERMITTING

The two principal environmental permits required for the construction, operation and closure

of Cordero are:

1. Environmental Impact Assessment (“Manifestacion de Impacto Ambiental” or “MIA”)

2. Change of Land Use (“Cambio de Uso de Suelo” or “CUS”)

Both permits are subject to review and approval by the Secretaría de Medio Ambiente y

Recursos Naturales (“SEMARNAT”), Mexico’s federal agency for natural resources and the

environment.

The Company formally submitted for evaluation its MIA in August 2023. The MIA incorporates

extensive social and environmental work programs completed by the Company’s team in

Mexico since 2020 in conjunction with multiple reviews by third-party consultants. The review

process of the MIA submission by SEMARNAT is ongoing.

The CUS submission is supported by a Change of Land Use Study known as an Estudio

Tecnico Justificativo ( “ETJ”). Compilation of the ETJ by the Company and third -party

consultants will be finalized in the coming months with formal submission of the CUS expected

to be made by 3Q 2024.

KEY DE-RISKING ITEMS

Power: impact assessment and power installation studies were completed in 2023 confirming

that there is sufficient capacity in the existing power grid to supply the Project with power for

operations at peak throughput levels. The FS will include detailed capital cost estimates for the

standard upgrades required at the Camargo II substation and for the installation of a 74-

kilometre powerline from the substation to Cordero. The Company has identified three potential

routes for the powerline. Work in 2024 for the powerline will consist of finalizing the powerline

route, surface rights access negotiations, permitting and engineering for both the Camargo II

substation upgrade and the new powerline to site. The option to use renewable energy sources

at site to supplement grid power will also be evaluated.

Surface Rights: in 2023 the Company secured the surface rights that correspond with the

planned open pit and key infrastructure locations at Cordero. In 2024, the Company will focus

on acquiring ancillary surface rights where appropriate as well as securing long- term access

and lease agreements for nearby land as required.

Hydrology: the two potential sources of water for the Project are local groundwater and water

from local water treatment plants in the region. The Company has completed a hydrogeological

assessment through its Mexican specialist consultant Investigacion y Desarrollo de Acuiferos

y Ambiente (“IDEAS”) utilising data from hydrogeology drilling and pump test wells. Initial

results indicate the potential for sufficient local groundwater for Phase 1 of the project (mill

throughput of ~25,000 tonnes per day). In addition, M3 Engineering & Technology recently

completed a technical review on the scope and cost to source water from local water treatment

plants. The results from this review will be incorporated in the upcoming FS.

In 2024, the Company plans to initiate the permitting process for the zoning of the groundwater

rights it already owns. The Company also plans to advance engineering work for the required

upgrades to the water treatment plant and accompanying water pipeline.

EXPLORATION

In 2024, the Company plans to complete mapping and sampling of new target areas along with

2,500 m of drilling. Key target areas include La Perla (10 km south of Cordero), Dos Mil Diez

(immediately southwest of Cordero) and Porfido Norte (10 km north of Cordero).

• La Perla – targeting is focused on a zone of anomalous silver from rock sampling within

a very large alteration footprint and high chargeability / low resistivity anomalies defined

by the geophysics program completed in 2022. Historical mine workings are also present

within a northeast trending structural corridor (parallel to the orientation of the main

mineralized trends at Cordero).

• Dos Mil Diez – further mapping and sampling is planned to support the evaluation of

chargeability anomalies identified during an IP survey completed in 2022. Dos Mill Diez is

located in an area of mapped intrusives, veining and alteration, directly to the southwest

of Cordero.

• Porfido Norte – additional mapping and sampling is planned to define targets within a

northeast trending structural corridor in this area.

The planned drill program for 2024 may be expanded depending on the results of the mapping

and sample program and initial drilling. A map showing the location of these target areas can

be found at the following link: Property Wide Targets

About Discovery

Discovery’s flagship project is its 100%-owned Cordero project, one of the world’s largest silver

deposits. The PFS completed in January 2023 demonstrates that Cordero has the potential to

be developed into a highly capital efficient mine that offers the combination of margin, size and

scaleability. Cordero is located close to infrastructure in a prolific mining belt in Chihuahua

State, Mexico.

On Behalf of the Board of Directors,

Tony Makuch, P.Eng

President, CEO & Director

For further information contact:

Forbes Gemmell, CFA

VP Corporate Development

Phone: 416-613-9410

Email: [email protected]

Website: www.discoverysilver.com

Qualified Person

Gernot Wober, P.Geo, VP Exploration, Discovery Silver Corp., is the Company's designated

Qualified Person for this news release within the meaning of National Instrument 43- 101

Standards of Disclosure for Mineral Projects (“NI 43-101”) and has reviewed and validated that

the information contained in this news release is accurate.

The most recent technical report for the Cordero Project is the 2023 Preliminary Feasibility

Study for the Company’s Cordero project. The report was completed by Ausenco with support

from AGP, Knight Piésold and Hard Rock and is available on Discovery’s website and on

SEDAR under Discovery Silver Corp.

FORWARD-LOOKING STATEMENTS:

Neither TSX Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Exchange) accepts

responsibility for the adequacy or accuracy of this release.

This news release is not for distribution to United States newswire services or for dissemination in the United States.

This news release does not constitute an offer to sell or a solicitation of an offer to buy nor shall there be any sale of any of the

securities in any jurisdiction in which such offer, solicitation or sale would be unlawful, including any of the securities in the United

States of America. The securities have not been and will not be registered under the United States Securities Act of 1933, as

amended (the “1933 Act”) or any state securities laws and may not be offered or sold within the United States or to, or for account

or benefit of, U.S. Persons (as defined in Regulation S under the 1933 Act) unless registered under the 1933 Act and applicable

state securities laws, or an exemption from such registration requirements is available.

Cautionary Note Regarding Forward-Looking Statements

This news release may include forward- looking statements that are subject to inherent risks and uncertainties. All statements

within this news release, other than statements of historical fact, are to be considered forward looking. Although Discovery believes

the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not

guarantees of future performance and actual results or developments may differ materially from those described in forward-looking

statements. Statements include but are not limited to the timing and results of the feasibility study and the anticipated capital and

operating costs, sustaining costs, net present value, internal rate of return, payback period, process capacity, average annual

metal production, average process recoveries, concession renewal, permitting of the Project, anticipated mining and processing

methods, proposed pre- feasibility study production schedule and metal production profile, anticipated construction period,

anticipated mine life, expected recoveries and grades, anticipated production rates, infrastructure, social and environmental

impact studies, the completion of key de-risking items, including the timing of receipt permits, availability of water and power,

availability of labour, tax rates and commodity prices that would support development of the Project. Information concerning

mineral resource/reserve estimates and the economic analysis thereof contained in the results of the pre-feasibility study are also

forward-looking statements in that they reflect a prediction of the mineralization that would be encountered, and the results of

mining, if a mineral deposit were developed and mined. Forward- looking statements are statements that are not historical fact s

which address events, results, outcomes or developments that the Company expects to occur. Forward- looking statements are

based on the beliefs, estimates and opinions of the Company’s management on the date the statements are made and they

involve a number of risks and uncertainties. Factors that could cause actual results to differ materially from those described in

forward-looking statements include fluctuations in market prices, including metal prices, continued availability of capital and

financing, and general economic, market or business conditions. There can be no assurances that such statements will prove

accurate and, therefore, readers are advised to rely on their own evaluation of such uncertainties. Discovery does not assume

any obligation to update any forward- looking statements except as required under applicable laws. The risks and uncertainties

that may affect forward- looking statements, or the material factors or assumptions used to develop such forward- looking

information, are described under the heading "Risks Factors" in the Company’s Annual Information Form dated March 30, 2023,

which is available under the Company’s issuer profile on SEDAR at www.sedarplus.ca.