Discovery Announces 2023 Work Program & Budget for Cordero
Discovery Announces 2023 Work Program & Budget for Cordero
TORONTO, Jan. 12, 2023 -- Discovery Silver Corp. (TSX-V: DSV, OTCQX: DSVSF) (“Discovery” or the “Company”) is
pleased to outline its 2023 work program and budget for its Cordero project (“Cordero” or “the Project”) located in Chihuahua
State, Mexico. All amounts are presented in Canadian dollars unless otherwise stated.
Tony Makuch, Interim CEO, states: “We expect 2023 to be a pivotal year for the Company. Our Pre-Feasibility Study is on
track for completion later this month and is expected to position Cordero as one of the largest silver development projects
globally. The delivery of the PFS comes at a time when silver demand is expected to grow significantly and where there is an
obvious scarcity of large silver projects in the development pipeline.
Work on our Feasibility Study is already underway and will be focused on optimization opportunities including improved mining
and processing efficiencies. Alongside this work we have allocated drill metres to the exploration potential on our large, highly-
prospective land package.
We remain committed to working with all local stakeholders through our well-established ESG programs. We also plan to
initiate the construction permitting process in the first half of the year which has the potential to position the Project for a
construction decision in the second half of 2024. With a cash balance of over $45 million and no debt we remain well
positioned to fund our 2023 work program at Cordero budgeted at $26 million.”
PROJECT SCHEDULE & BUDGET
The Company anticipates delivering the Cordero Pre-Feasibility Study (“PFS”) by the end of the month. The Feasibility Study
(“FS”) is already being advanced and is expected to be completed in 1Q 2024. Construction permitting for Cordero will be
undertaken in-parallel with the FS work, with the submission of the Environmental Impact Statement (“Manifesto de Impacto
Ambiental” or “MIA”) expected to be made to the Mexican Federal Environmental Department (“SEMARNAT”) in the first half of
2023. Assuming a 12 to 18 month permitting timeline, this would position the Company to make a construction decision in the
second half of 2024.
The 2023 work programs are budgeted at $26 million. The Company is well positioned to fund this work with a cash balance of
over $45 million and no debt at the end of 2022.
2023 DRILL PLANS
Details on the allocation of the 26,500 metre 2023 drill program are provided below.
Item Details Drill Metres
Feasibility Study Engineering, hydrogeology & geotechnical drilling 17,500 m
Property-wide Targets Drill testing of four property-wide targets 9,000 m
Total 26,500 m
FEASIBILITY STUDY
The FS is expected to be completed in the first quarter of 2024. It is anticipated the study will use a similar approach to the
PFS, including staged expansions of the processing facility and the effective use of stockpiling to accelerate the payback
period. Key areas for optimization in the FS include improved mine unit production efficiencies through optimal mine equipment
selection and improved metallurgical performance and lower processing costs through rock type and oxide/sulphide blending
and reagent substitution. Further details on additional technical work supporting the FS include:
• Reserve definition – 28,500 m of drilling was completed in 2022 subsequent to the cut-off date for the PFS. This
drilling has been focused on upgrading the resource classification within the open pit and expanding and upgrading
resource blocks between the open pit and the Resource constraining pit shell. This drilling will be incorporated in a
Resource and Reserve update in conjunction with the completion of the FS.
• Metallurgical testwork
◦ Sulphides: additional variability testwork focused on further optimization opportunities in the comminution and
flotation circuits.
◦ Oxide/Sulphide blending: testing higher proportions of oxides (20% and higher) for the co-processing of oxides
and sulphides will be completed (PFS testwork focused on oxide-sulphide blends at ~10% oxides / ~90%
sulphides).
This testwork will be supported by additional mineralogy work aimed at increasing metallurgical recoveries and lowering
operating costs through optimizing rock type and oxide/sulphide blends.
• Mining – more detailed mine scheduling during the payback period will be completed along with an evaluation of
optimal bench height and mine equipment sizing to potentially increase the size of mining equipment and reduce unit
mining costs.
• Process design – the process design for the FS will incorporate the additional comminution testwork to be completed
in 2023. Work will focus on opportunities to increase throughput and decrease power and grinding media consumption.
Additional work will evaluate alternative flotation technologies, including Jameson Cells, as well as further optimization
of thickening and filtration systems. During the FS, detailed engineering is expected to be advanced to 25% of the total
engineering required for the Project build.
• Tailings storage facility – work will be focused on optimizing the tailing storage design as well as the water efficiency
and recirculation within the tailings storage facility. Further work will be completed on the option to use dry stacked
tailings (the PFS will assume high-density thickened tailings).
• Hydrogeology – three large-diameter pump test wells of the local aquifer are planned in 2023. These test wells will
supplement the six hydrogeology holes drilled in 2022 and will result in an updated assessment of pit dewatering
requirements and will form part of the basis for the site water balance in the FS. Additionally, a regional geophysics
survey and hydrogeological drilling are planned as part of a broader hydrogeological investigation of the local aquifer.
• Geotechnical – additional geotechnical site investigations of key infrastructure locations will be completed as part of
the FS. This work will be focused on the proposed locations of the tailings storage, waste rock storage, ore stockpile
and process plant facilities. Follow-up work on pit slope analysis is expected to be limited in scope given the detailed
geotechnical work completed to date.
• Power – an additional power study will be completed that will detail the technical specifications and support the
permitting process for the installed power line.
PROPERTY-WIDE EXPLORATION
Exploration on property-wide targets has been ongoing at Cordero since March 2021. Work completed to date includes
geological mapping, surface rock and soil sampling, geophysics and diamond drilling. The five main target areas identified to-
date are Sanson, Porfido Norte, Dos Mil Diez, Molino de Viento, and La Perla. Discovery completed 4,500 m of preliminary
reconnaissance drilling in 10 drill holes at Sanson and Porfido Norte in 2022.
In 2023 an initial 9,000 m drill program is planned across the four targets listed below. This program may be expanded
depending on the results of the initial program and if additional targets are identified by the geophysics surveys currently in
progress. A map showing the location of these target areas can be found at the following link: Property wide targets
• Sanson – Sanson is interpreted to sit above the source intrusion of the Cordero mineralization based on a large,
intense magnetic anomaly coincident with intense silica alteration and anomalous levels of molybdenum (100 – 400
ppm). Drilling in 2023 will target several large chargeability anomalies identified from a recently completed induced
polarization (“IP”) geophysics survey that covered the edge of the alteration zone. These targets are to the northeast
and northwest of the drilling completed at Sanson in 2022.
• Dos Mil Diez – drilling will target three chargeability anomalies identified by an IP survey completed in 4Q 2022. Dos
Mill Diez is located in area of mapped intrusives, veining and alteration and is situated directly to the southwest of the
Cordero resource area.
• La Perla – drill targeting is focused on a zone of anomalous silver from rock sampling within a very large alteration
footprint and high chargeability / low resistivity anomalies defined by the geophysics program completed in 2022.
• Cordero Deep Skarn – drilling in 2022 encountered strong skarn alteration that returned mineralized intervals at depth
in the northeast of the Cordero deposit. Several deep holes are planned to follow up on these previous intervals to vector
towards stronger skarn alteration that may have the potential to host high-grade mineralization.
ENVIRONMENT, SOCIAL & GOVERNANCE
Discovery made significant progress on its Environmental, Social and Governance (“ESG”) initiatives in 2022. Toward the end
of the year the Company received its official ESR Certification. This certification is issued by the Mexican Center for
Philanthropy to organizations that have demonstrated they operate in a socially and environmentally responsible manner. The
Company also received its Great Place to Work Certification which recognizes companies that create an outstanding
employee experience through building a workplace culture of trust, credibility, respect, pride and collaboration.
The Company is committed to maintaining full compliance with these certifications in 2023, and is working towards the
attainment of the following additional certifications:
• Clean Industry Certification – this certificate requires an audit by the Mexican government entity PROFEPA (Federal
Attorney’s Office for Environmental Protection) focused on the Company’s policies and procedures regarding waste
management, ecological footprint, water, emissions, soil, biodiversity and other environmental compliance.
• Safe Industry Certification (Level 2) – this certificate is issued by the Mexican Government’s Secretary of Labor and
requires full legal compliance with over 20 Health and Safety Standards as outlined by the Mexico Federal Government.
• International Association for Sustainable Economy (“IASE”) Qualification – the IASE certification is a globally-
recognized three-tiered qualification requiring compliance with the highest professional and ethical standards for ESG
professionals worldwide. Currently nine employees have completed Level 1 (foundational) and two employees have
completed Level 2 (intermediate). It is anticipated that several more employees will complete Levels 1 and 2 in 2023
with two employees aiming to complete the final Level 3 (expert).
Discovery will also continue to advance its community programs through the course of the year. In 2022, the Company signed
an alliance with the Parral municipality aimed at improving access to social services for vulnerable groups in the local
population, specifically in relation to medical assistance. Through this alliance the Company donated a mobile medical unit to
the Parral municipality and provided assistance with the construction of a local medical clinic. In 2023, Discovery will continue
to sponsor the supply of equipment and medicine to the medical unit and clinic to maintain the capacity of these facilities to
serve approximately 70,000 people per annum. The Company will continue with its other social programs, as described in its
second annual ESG report, to support stakeholders within the Parral municipality in 2023.
About Discovery
Discovery’s flagship project is its 100%-owned Cordero project, one of the world’s largest silver deposits. The PEA completed
in November 2021 demonstrates that Cordero has the potential to be developed into a highly capital efficient mine that offers
the combination of margin, size and scaleability. Cordero is located close to infrastructure in a prolific mining belt in Chihuahua
State, Mexico. Continued exploration and project development at Cordero is supported by a strong balance sheet with cash of
approximately C$45 million and no debt.
On Behalf of the Board of Directors,
Tony Makuch, P.Eng
Interim CEO
For further information contact:
Forbes Gemmell, CFA
VP Corporate Development
Phone: 416-613-9410
Email: [email protected]
Website: www.discoverysilver.com
Sample analysis and QA/QC Program
The true width of the veins is estimated to be approximately 70% of the drilled width. Assays are uncut except where
indicated. All core assays are from HQ drill core unless stated otherwise. Drill core is logged and sampled in a secure core
storage facility located at the project site 40km north of the city of Parral. Core samples from the program are cut in half, using
a diamond cutting saw, and are sent to ALS Geochemistry-Mexico for preparation in Chihuahua City, Mexico, and
subsequently pulps are sent to ALS Vancouver, Canada, which is an accredited mineral analysis laboratory, for analysis. All
samples are prepared using a method whereby the entire sample is crushed to 70% passing -2mm, a split of 250g is taken
and pulverized to better than 85% passing 75 microns. Samples are analyzed for gold using standard Fire Assay-AAS
techniques (Au-AA24) from a 50g pulp. Over limits are analyzed by fire assay and gravimetric finish. Samples are also
analyzed using thirty three-element inductively coupled plasma method (“ME-ICP61”). Over limit sample values are re-assayed
for: (1) values of zinc > 1%; (2) values of lead > 1%; and (3) values of silver > 100 g/t. Samples are re-assayed using the ME-
OG62 (high-grade material ICP-AES) analytical package. For values of silver greater than 1,500 g/t, samples are re-assayed
using the Ag-CON01 analytical method, a standard 30 g fire assay with gravimetric finish. Certified standards and blanks are
routinely inserted into all sample shipments to ensure integrity of the assay process. Selected samples are chosen for
duplicate assay from the coarse reject and pulps of the original sample. No QAQC issues were noted with the results reported
herein.
Qualified Person
Gernot Wober, P.Geo, VP Exploration, Discovery Silver Corp., is the Company’s designated Qualified Person for this news
release within the meaning of National Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101”) and has
reviewed and validated that the information contained in this news release is accurate.
TECHNICAL NOTES & FORWARD-LOOKING STATEMENTS:
The most recent technical report for the Cordero Project is the 2021 Preliminary Economic Assessment (PEA). The PEA was
completed by Ausenco Engineering Canada Inc. with support from AGP Mining Consultants Inc. and Knight Piésold and Co.
(USA). The full technical report supporting the PEA is available on Discovery’s website and on SEDAR under Discovery Silver
Corp.
The PEA assumed average life-of-mine recovery assumptions for sulphide material of 84% for Ag, 19% for Au, 86% for Pb and
85% for Zn. The PEA assumed oxide recovery assumptions of 56% for Ag and 63% for Au for crushed feed and 36% for Ag
and 35% for Au for uncrushed ROM feed.
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture
Exchange) accepts responsibility for the adequacy or accuracy of this release.
This news release is not for distribution to United States newswire services or for dissemination in the United States.
This news release does not constitute an offer to sell or a solicitation of an offer to buy nor shall there be any sale of any of the
securities in any jurisdiction in which such offer, solicitation or sale would be unlawful, including any of the securities in the
United States of America. The securities have not been and will not be registered under the United States Securities Act of
1933, as amended (the “1933 Act”) or any state securities laws and may not be offered or sold within the United States or to,
or for account or benefit of, U.S. Persons (as defined in Regulation S under the 1933 Act) unless registered under the 1933
Act and applicable state securities laws, or an exemption from such registration requirements is available.
Cautionary Note Regarding Forward-Looking Statements
This news release may include forward-looking statements that are subject to inherent risks and uncertainties. All statements
within this news release, other than statements of historical fact, are to be considered forward looking statements. Forward-
looking statements including, but not limited to Discovery’s future plans and objectives regarding the Cordero Project , and the
prospect of further discoveries there, the 2023 workplan and budget, the timing of release of the Pre-Feasibility Study and the
Feasibility Study, which constitute forward looking information that involve various risks and uncertainties. Although Discovery
believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such
statements are not guarantees of future performance and actual results or developments may differ materially from those
described in forward-looking statements. Factors that could cause actual results to differ materially from those described in
forward-looking statements include fluctuations in market prices, including metal prices, continued availability of capital and
financing, and general economic, market or business conditions. There can be no assurances that such statements will prove
accurate and, therefore, readers are advised to rely on their own evaluation of such uncertainties. Discovery does not assume
any obligation to update any forward-looking statements except as required under applicable laws.