Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

DPM.TO ·

Dundee Precious Metals Extends Life of Mine Plan to 2032 for the Chelopech Mine in Bulgaria; Provides Mineral Reserve and Mineral Resource Update and Highlights from Exploration Activities (All monetary figures in this news release are expressed in U.S. dollars

Exploration Programs

1

Dundee Precious Metals Extends Life of Mine Plan to 2032 for the

Chelopech Mine in Bulgaria; Provides Mineral Reserve and Mineral Resource Update

and Highlights from Exploration Activities

(All monetary figures in this news release are expressed in U.S. dollars unless otherwise stated)

Toronto, November 29, 2023 – Dundee Precious Metals Inc. (TSX: DPM) (“DPM” or “the Company”)

is pleased to provide an interim update to the Mineral Resource and Mineral Reserve estimate and life

of mine (“LOM”) plan for its Chelopech mine in Bulgaria. In 2023, DPM advanced its annual update for

Mineral Reserves and Mineral Resources in order to better align with the Company’s planning and

budgeting cycle.

Highlights

• Mine life extended to 2032: Proven and Probable Mineral Reserves of 1.6 million ounces (“Moz.”)

of gold and 305 million pounds (“Mlbs.”) of copper supports a mine life that now extends to 2032.

DPM successfully added 1% to contained ounces of gold with contained pounds of copper

decreasing by 2% relative to the previous Mineral Reserve estimate.

• Updated LOM plan with improved grades and recoveries : The updated LOM plan adds

approximately 128,000 ounces of recovered gold and 9 Mlbs. of recovered copper between 2024

and 2032. During this period, average LOM gold grade and copper grades increased by 5% and

3% respectively, and recoveries for gold increased by approximately 5%.

• Updated Measured and Indicated and Inferred Mineral Resource: Total Measured and Indicated

Mineral Resources, exclusive of Mineral Reserves, of 1.2 Moz. of gold and 265 Mlbs. of copper add

further potential to extend mine life. Additional Inferred Mineral Resource of 0.274 Moz. of gold and

67 Mlbs. of copper.

• Upside potential with in-mine and brownfield exploration: DPM continues to focus on extending

Chelopech’s mine life through its successful in -mine exploration program and an aggressive

brownfield exploration program. Positive results from drilling at the Sharlo Dere West and Sharlo

Dere prospects, located within the mine concession and proximal to existing Chelopech

underground development, highlight potential for further mine life extensions. Highlights from drilling

include 37.5 metres at 7.34 g/t AuEq, 5.69 g/t Au and 0.98% Cu from 184.5 metres depth (including

27 metres at 9.70 g/t AuEq, 7.58 g/t Au and 1.26% Cu from 193.5 metres) on EXT_555_04.1 DPM

has completed its initial phase of infill drilling with the objective of including a Mineral Resource

estimate for Sharlo Dere within its next Mineral Resource update for the Chelopech mine.

“I am pleased to report that we have continued our consistent track record of extending mine life at

Chelopech,” said David Rae, President and Chief Executive Officer of Dundee Precious Metals.

1 Refer to the Appendix on pages 16 to 20 of this news release for the full results from drilling at the Sharlo Dere and Sharlo

Dere West prospects.

2

“Next month will mark the 20 -year anniversary of DPM ’s acquisition of the Chelopech mine. Over this

period, we have transformed the mine into a modern and highly efficient operation, developed a strong

local team and established strong relationships with local stakeholders.

“Chelopech today has a mine life that extends to 2032 based on Mineral Reserves , a strong Mineral

Resource base, compelling exploration prospects and significant opportunities to continue our strong

track record of mine life extensions.”

Updated Mineral Reserve and Resource Estimate

The 2023 Mineral Reser ve and Mineral Resource estimate reflects the results of in -mine drilling and

production depletion as at May 31, 2023.

The updated Proven and Probable Mineral Reserve estimate for Chelopech of 1.6 Moz. of gold and 305

Mlbs. of copper support a nine -year mine life that extends to 203 2, not including potential for further

conversions of existing Mineral Resources and potential additional exploration success. Proven and

Probable Mineral Reserves decreased by 0.6 Mt of ore with contained gold increasing by 22,000 ounces

and contained copper decreasing by 6.3 Mlbs. relative to the previous 2022 Mineral Reserve estimate.

The updated Mineral Reserves estimate is shown below:

Chelopech Proven and Probable Mineral Reserve Estimate

(As at May 31, 2023)

Classification Tonnes

(kt)

Grades Metal Content

Au (g/t) Ag (g/t) Cu (%) Au (Koz.) Ag (Koz.) Cu (Mlbs.)

Proven Stopes 6,346 2.78 7.50 0.83 567 1,531 115.7

Broken stocks 48 3.45 8.53 0.83 5 13 0.9

Stockpiles 17 3.33 6.79 0.78 2 4 0.3

Total Proven 6,412 2.79 7.51 0.83 575 1,548 116.9

Probable Stopes 10,146 2.76 9.34 0.76 902 3,048 169.0

Development 1,082 2.78 8.63 0.81 97 300 19.4

Total Probable 11,228 2.77 9.28 0.76 998 3,348 188.4

Total Proven and Probable 17,639 2.77 8.63 0.79 1,573 4,896 305.3

1. The Mineral Reserves disclosed herein have been estimated in accordance with the CIM Definition Standards for Mineral Resourc es and

Mineral Reserves (the “CIM Definition Standards”, adopted by CIM Council on May 10, 2014).

2. Mineral Reserves have been depleted for mining as of May 31, 2023.

3. The Inferred Mineral Resources do not contribute to the financial performance of the project and are treated in the same way as waste.

4. The reference point at which the Mineral Reserves are defined is where the ore is delivered to the crusher.

5. Long term metal prices assumed for the evaluation of the Mineral Reserves are $1, 500/oz. for gold, $17.00/oz . for silver, and $ 3.25/lb. for

copper.

6. Mineral Reserves are based on a net smelter return-less-costs cut-off value of $0/t. The total cost applied was $55/t which is a sum of operational

costs of approximately $50/t and sustaining capital of $5/t.

7. All blocks include a complex NSR formula that differs for the three ore types within the Mineral Reserve and Mineral Resource. The NSR formula

utilizes long-term metal price s, metallurgical recoveries, payability terms , treatment charges, refining charges, penalty charges (deleterious

arsenic), concentrate transport costs, and royalties. For clarity of understanding of ore value, a simplified formula is pres ented here that

correlates to the complex formula for the average head grade . The simplified formula for general ore which comprises 97% of the Mineral

Reserve is NSR $/t = 26.091 x Cu% + 0.196 x Ag_g//t + 30.773 x Au_g/t.

8. Mineral Reserves account for unplanned mining dilution and ore loss that varies by orebody dimension and experience per mining block area ,

which on average were 6.9% for unplanned ore loss and 7.4% for unplanned dilution.

9. Mineral Reserves account for planned mining dilution and mining recovery through stope optimi zation and stope design. The stopes are

optimized to maximize net cash flow within the constraints of dilution and orebody extractable geometry. The planned dilution and recovery

depend on geotechnical, mineralization continuity controls and ore zone dimensions.

10. All stopes have been verified that they are profitable after considering the cost of capital development.

11. There is no known likely value of mining, metallurgical, infrastructure, permitting or other relevant factors that could materially affect the estimate.

The final two and a half years of operation occurs after the expiry of the mining concession contract. It is the opinion of DPM that the mining

permit will be extended.

12. Sum of individual table values may not equal due to rounding .

3

Measured and Indicated Mineral Resources, exclusive of Mineral Reserves, decreased by 1.0 million

tonnes (“Mt”), 120,000 ounces of gold and 16 Mlbs. of copper relative to the 2022 Mineral Resource

estimate. The decrease was largely a result of conversion to Mineral Reserves, partially offset by new

extensions to Mineral Resources achieved from in-mine drilling as well as a review of estimation

parameters during the update.

The Mineral Resource estimate is shown below and is effective as at May 31, 2023:

Chelopech Mineral Resource Estimate, exclusive of Mineral Reserves

(As at May 31, 2023)

Classification Tonnes Gold Silver Copper

(Mt) Grade (g/t) Moz. Grade (g/t) Moz. Grade (%) Mlbs.

Measured 8.1 2.49 0.649 8.76 2.283 0.85 152

Indicated 7.3 2.28 0.537 10.14 2.387 0.70 113

Total

Measured &

Indicated

15.4 2.39 1.185 9.41 4.669 0.78 265

Inferred 4.3 2.00 0.274 8.90 1.219 0.71 67

1. The Mineral Resources disclosed herein have been estimated in accordance with the CIM Definition Standards for Mineral Resources and

Mineral Reserves (CIM, 2014).

2. Tonnages are rounded to the nearest 0.1 million tonnes to reflect that this is an estimate.

3. Metal content is rounded to the nearest 1 thousand ounces or 1 million pounds to reflect that this is an estimate.

4. The Mineral Resources are reported exclusive of Mineral Reserves.

5. Metal prices assumed for the evaluation of the Mineral Resources are $1,700/oz. for gold, $17.00/oz. for silver, and $3.75/lb. for copper.

6. Mineral Resources are based on a NSR less costs cut-off value of US$0/t in support of reasonable prospects of eventual economic

extraction. The total cost applied was approximately $55/t which is a sum of operational costs of approximately $ 50/t and sustaining capital of

approximately $5/t.

7. All blocks include a complex NSR (Net Smelter Return) formula. The NSR formula utilises long term metal price, metallurgical recoveries,

payability terms. Treatment charges, refining charges, penalty charges, concentrate transport costs, and royalties. For clarity of understanding

of value, a simplified formula is presented here for the Measured and Indicated Resource where NSR US$/t = 33.870 x Cu % + 0.171 x Ag g/t

+ 37.937 x Au g/t.

Life of Mine Plan

The table below shows the updated LOM plan, reflecting the updated Mineral Reserve estimate. Annual

throughput rates have been optimized over the LOM, taking into account recent development rates as

mining extends into areas of the mine located further from existing infrastructure , as well as the grade

profile to maximize value.

Between 2024 and 2032, the updated LOM plan adds approximately 128,000 ounces of additional gold

production and 9 Mlbs of copper, with the average LOM gold and copper grades increasing by 5% and

3%, respectively, relative to the previous LOM plan outlined in the news release “ Dundee Precious

Metals Provides Updated Mineral Resource and Mineral Reserve Estimates for the Chelopech Mine in

Bulgaria” dated March 30, 2023.

The improved average grade is expected to be achieved by mining the crown pillars from Blocks 103

and 151 from 2025 onwards. During this period, gold recoveries increased by 5% relative to the previous

mine plan as a result of an improved ore blend over the LOM and updated recovery regression models

based on recent plant performance. This is partially offset by a reduction to the mining rate in order to

maintain development rates at 7,500 metres per annum and to optimize sustaining capital required . In

2026, the mining rate is planned to be reduced to 2 million tonnes per annum (“Mtpa”) and to 1.8 Mtpa

from 2027 onwards.

4

Current Life of Mine Plan

Unit 2024 2025 2026 2027 2028 2029 2030 2031 2032 Total / Average

Total Ore Processed Mt 2.2 2.2 2.0 1.8 1.8 1.8 1.8 1.8 0.8 16.2

Grade

Au g/t 2.90 2.92 2.92 3.07 2.56 2.75 2.54 2.54 2.02 2.75

Cu % 0.77 0.85 0.93 0.77 0.76 0.81 0.69 0.71 0.74 0.79

Recoveries

Copper Concentrate

Au % 54.3 58.3 53.7 54.1 57.1 62.0 61.3 56.2 56.1 56.9

Cu % 83.7 84.8 83.1 83.1 84.3 85.8 85.6 84.8 85.0 84.4

Pyrite concentrate

Au % 25.8 24.6 24.7 27.9 24.1 21.7 23.3 27.1 22.5 24.9

Production

Total Au K oz. 164 172 148 146 121 134 125 123 38 1,170

Total Cu1 Mlbs. 31 35 34 26 26 28 23 24 10 238

Note: Totals in the table above do not include 2023 production and therefore do not add to the Mineral Reserve estimate, which

reflects from May 2023 onward.

1. Total copper production reflects copper recovered from copper concentrate only. Copper recovered from pyrite concentrate is

not payable.

Previous Life of Mine Plan

Unit 2024 2025 2026 2027 2028 2029 2030 2031 Total / Average

Total Ore Processed Mt 2.2 2.2 2.2 2.2 2.2 2.2 2.2 0.6 16.0

Grade

Au g/t 2.93 2.99 2.76 2.52 2.27 2.89 2.16 1.91 2.62

Cu % 0.72 0.80 0.69 0.84 0.75 0.82 0.74 0.75 0.77

Recoveries

Copper Concentrate

Au % 56.2 55.6 54.4 41.5 55.5 49.5 52.3 48.2 52.1

Cu % 83.4 83.6 85.3 84.2 86.0 84.2 86.6 78.2 84.5

Pyrite concentrate

Au % 24.2 24.4 24.8 25.8 25.8 24.7 26.1 24.8 25.0

Production

Total Au K oz. 167 169 155 120 131 152 120 28 1,041

Total Cu1 Mlbs. 29 32 29 34 32 33 31 8 229

1. Total copper production reflects copper recovered from copper concentrate only. Copper recovered from pyrite concentrate is

not payable.

5

Several Optimization Activities Planned for 2024

DPM has several initiatives underway aimed at further optimizing Chelopech’s estimated Mineral

Reserves and Resources, and the life of mine plan, including:

• Recontouring the block model at a lower gold equivalent cut-off grade to align with the latest NSR

cut-off value assumptions, providing further potential to convert Mineral Resource into Mineral

Reserves;

• Enhancing development rates to improve productivity as the mine plan progresses into areas in the

mine located further from infrastructure; and

• Evaluating ore sorting technologies to unlock orebodies currently below existing NSR cut-off values

and minimize ore dilution from structurally controlled orebodies.

Three-Year Outlook

The updated LOM plan is in-line with the Company’s previously issued 202 3 guidance and three-year

outlook for Chelopech, as shown below.

2022

Results

2023

Guidance

2024

Outlook

2025

Outlook

Metals contained in concentrate produced

Gold (K oz.)

Copper (Mlbs.)

179

31

150 – 170

30 – 35

160 – 180

29 – 34

160 – 185

29 – 34

Cost of sales per tonne of ore processed(1)

($/t) 63 N/A N/A N/A

Cash cost per tonne of ore processed(1)

($/t) 50 53 – 58 N/A N/A

Sustaining capital expenditures

($ millions) $24 20 – 24 14 – 18 12 – 15

1. Cost of sales per tonne of ore processed represents Chelopech cost of sales divided by the volume of ore processed. Cash cost per tonne of ore

processed is a non-GAAP ratio and has no standardized meaning under International Financial Reporting Standards (“ IFRS”) and may not be

comparable to similar measures presented by other companies. Refer to the “Non-GAAP Financial Measures” section contained in the Company’s

Management’s Discussion and Analysis (the “ MD&A”) for the period ended September 30, 2023, which is available on the Company’s website

at www.dundeeprecious.com and on SEDAR + at www.sedarplus.ca, for a detailed description and reconciliation of this measure to the most

directly comparable measure under IFRS.

For more information regarding the Company’s 202 3 guidance and three -year outlook, including key

assumptions, qualifications and risks associated thereto, refer to the MD&A for the three and nine

months ended September 30, 2023, issued on November 7, 2023, available on the Company’s website

at www.dundeeprecious.com and on SEDAR+ at www.sedarplus.ca.

6

Further extending mine life through additional in-mine and brownfield exploration

DPM continues to focus on extending Chelopech’s mine life through its successful in-mine exploration

program and an aggressive brownfield exploration program. Priority initiatives include:

• In-mine drilling for Mineral Resource development;

• Infill drilling at the Sharlo Dere prospect within the mine concession to support a Mineral

Resource estimate;

• Converting the Sveta Petka exploration licence to a Commercial Discovery, after which DPM

intends to apply for concession rights in 2024 for the area, which is now designated as

Chelopech North; and

• Completion of an intensive drilling program at the Brevene exploration licence and application

for a Geological Discovery.

In-mine exploration: DPM continues to advance in -mine exploration activities focu sed on extending

Chelopech’s mine life. Priority targets within the Company’s near-term plans include:

• The Target North zone , which is located on the northern flank of the Chelopech mine concession

and is manife sted as an isolated, structurally and lithologically controlled intervals of high -

sulphidation type of mineralization. Several extensional drilling programs are planned for the target,

including testing the northern area of Block 19 for high -grade structurally controlled orebodies

between levels 450 to 500, and drilling to the west of Blo ck 147 to explore for similar bodies at a

depth of levels 200 to 500.

• Extensional drilling south-east from Block 700 is planned to better assess the economic significance

of the Quartz -Barite-Gold-Sulphide (QBGS) zone. This program is a continuation of previous

successful drilling campaigns and will focus on identifying an extension of the mineralized system

to the south-east and at depth.

Sharlo Dere: At the Sharlo Dere prospect, which is located approximately 500 metres northeast of the

eastern-most orebodies of the Chelopech mine and approximately 400 metres from current underground

infrastructure, DPM completed 8,407 metres of infill drilling at a 50-metre by 50 -metre spacing which

was designed to evaluate the continuity of the mineralized zones. The prospect comprises the main

Sharlo Dere zone (SD), as well as the lateral extensions termed the Sharlo Dere East (SDE) and the

Sharlo Dere West-Target 11 zones (SDW).

Results from recent drilling highlight the prospect’s potential for copper-gold mineralization along the

northeastern flank of the mine concession as a continuation of the Chelopech high-sulphidation system

(see Figure 2 and Appendix table 1).

7

Recent (2022 until present) significant intercepts from the Sharlo Dere prospects include:

• EX_SD_40 – 11 metres at 3.07 g/t AuEq, 1.85 g/t Au and 0.73% Cu from 303 metres depth and 6

metres at 4.18 g/t AuEq, 3.56 g/t Au and 0.37 % Cu from 327 metres depth

• EX_SD_51 – 14 metres at 3.76 g/t AuEq, 2.59 g/t Au and 0.70% Cu from 250 metres depth

• EX_SD_53 – 8 metres at 14.15 g/t AuEq, 9.34 g/t Au and 2.87% Cu from 610 metres depth

• EX_SDW_02 – 14 metres at 3.07 g/t AuEq, 1.61 g/t Au and 0.87% Cu from 573 metres depth

• EX_SD_51 – 14 metres at 3.76 g/t AuEq, 2.59 g/t Au and 0.70% Cu from 250 metres depth

• EXT11_555_03 – 6.2 metres at 7.54 g/t AuEq, 6.70 g/t Au and 0.50% Cu from 165 metres depth

• EXT11_555_04 – 37.5 metres at 7.34 g/t AuEq, 5.69 g/t Au and 0.98% Cu from 184.5 metres depth

(including 27 metres at 9.70 g/t AuEq, 7.58 g/t Au and 1.26% Cu from 193.5 metres)

See Appendix Table 1 on pages 14 to 18 for full results from drilling.

The Sharlo Dere, Sharlo Dere East and Sharlo Dere West prospects share the same geological

environment and show many similarities with the high -sulphidation style Chelopech copper -gold

mineralization. Mineralization is constrained by east -northeast and west -northwest striking deep

structural feeders and highly permeable sub -vertical phreatomagmatic breccia contacts within the

sedimentary Turonian Unit, that was intruded by a multi-phase dioritic intrusive complex. The distal and

upper part of the phreatomagmatic breccia pipes are represented by strata -bound hydro -magmatic

injections and surge flow deposits accompanied with sub -horizontal mineralized lenses/layers, which

were subsequently tilted according to the synformal basin architecture. A particular characteristic of the

Sharlo Dere area is the better preservation of the shallow syn-sedimentary exhalative sulphide

mineralization and subsequent reworked mineralized clasts in syn- to post-mineral debris flow deposits

(see Figure 3).

DPM has completed its initial phase of infill drilling with the objective of including a Mineral Resource

estimate for Sharlo Dere within the next Mineral Resource estimate update for the Chelopech mine, with

the longer-term goal to potentially convert these Mineral Resources into Mineral Reserves.

Sveta Petka: In March 2023, the Company filed a Commercial Discovery application with the Bulgarian

authorities for the Sveta Petka exploration licence, which includes the Wedge, West Shaft, Krasta and

Petrovden prospects, to allow the Company to apply for concession rights in 2024 for the area which is

now designated as Chelopech North.

Brevene: On the Brevene exploration licence surround ing the Chelopech mine concession, target

delineation and scout drill testing has been completed. The evaluation of Mineral Resource potential is

ongoing, and the data collected will be used to support an application for a Geological Discovery, which

is expected to be submitted before the end of the year.

8

Figure 1: Plan view of the Chelopech mining concession, Chelopech North Commercial Discovery and

Brevene exploration licences, indicating target zones for DPM’s 2024 in-mine and brownfield exploration

program as well as the section line (A-A’) shown in Figure 2.