Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

DPM.TO ·

Dundee Precious Metals Announces Positive Preliminary Economic Assessment for the Čoka Rakita Project in Serbia, including IRR of 33% and NPV of $588M

Economic Studies

1

Dundee Precious Metals Announces Positive Preliminary Economic Assessment for the

Čoka Rakita Project in Serbia, including IRR of 33% and NPV of $588M

Toronto, May 1, 2024 – Dundee Precious Metals Inc. (TSX: DPM) (“DPM” or “the Company”) is pleased

to announce the results of a preliminary economic assessment (“PEA”) for its Čoka Rakita project in Serbia.

The PEA supports an underground mining operation with an 850,000 tonne per annum processing facility

and an initial 10-year mine life, and highlights Čoka Rakita’s potential to offer meaningful production growth

with attractive all-in sustaining costs and very robust economics at a $1,700 per ounce gold price

assumption. Based on the positive results of the PEA, the Company is proceeding with a pre -feasibility

study (“PFS”) and project permitting activities.

PEA Highlights

(All dollar amounts in this news release are expressed in U.S. dollars, unless otherwise noted. The reader is advised that the PEA is

preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to have the economic

considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that the PEA

will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.)

Čoka Rakita project PEA highlights

(Based on a $1,700 per ounce gold price)

Throughput capacity 850,000 tonnes per annum

Average annual gold production (life of mine) 129,000 ounces of gold

Average annual gold production (first five full years) 164,000 ounces of gold

Average cash cost1 (life of mine) $605 per ounce of gold

Average all-in sustaining cost1 (life of mine) $715 per ounce of gold

Initial capital expenditures $381 million

Free cash flow1 (life of mine) $891 million

NPV (after-tax, 5% discount)2 $588 million

IRR (after tax)2 33%

• High margin production profile: Annual production expected to average 164,000 ounces of gold (first

five full years) with all -in sustaining costs expected to be in the lowest quartile, providing the potential

for very strong margins.

• Robust returns highlight an attractive project at a $1,700 per ounce gold price assumption: After-

tax NPV of $588 million with an IRR of 33% and payback after 2.4 years. The project’s economics are

even more attractive in today’s gold price environment (see page 5 for a sensitivity table).

1 Cash cost per ounce of gold sold, all-in sustaining cost per ounce of gold sold and free cash flow are non-GAAP financial measures or ratios and have

no standardized meaning under IFRS Accounting Standards (“IFRS”) and may not be comparable to similar measures used by other issuers. As the

Čoka Rakita project is not in production, the Company does not have historical non-GAAP financial measures nor historical comparable measures

under IFRS, and therefore the foregoing prospective non-GAAP financial measures or ratios may not be reconciled to the nearest comparable measures

under IFRS. Refer to the “Non-GAAP Financial Measures” section on page 10 of this news release for more information, including a detailed description

of each of these measures.

2 Current legislation in Serbia allows for tax relief for large investments for a maximum period of 10 years, subject to certain conditions. The PEA assumes

that the Čoka Rakita project is eligible for this tax relief and the effective income tax rate applied is 0% over the project’s 10 -year mine life.

2

• Attractive organic growth opportunity leveraging DPM’s mining, processing , and regional

expertise: Čoka Rakita benefits from established infrastructure, including nearby existing roads and

power lines. The project is located in close regional proximity to DPM’s existing operations in Bulgaria

and the PEA leverages the Company’s underground mining and processing expertise in terms of mining

methods and flowsheet. The Company has had a local presence in Serbia since 2004 and has

developed strong relationships in the region and will continue to proactively engage with all stakeholders

as the project advances.

• Significant exploration potential across four exploration licences : DPM is continuing its scout

drilling program focused on aggressively pursuing additional skarn targets on the Čoka Rakita licence

and the Company’s three additional licences to the north and the south.

“The PEA confirms our view that Čoka Rakita is a very robust project with the potential to add strong

economic returns and very high-margin gold production growth to our portfolio,” said David Rae, President

and Chief Executive Officer of Dundee Precious Metals.

“The results of the PEA are a testament not only to the quality of Čoka Rakita, but also our exploration and

technical teams who have accelerated the project from the initial discovery we announced in 2023 to a PEA

in under 16 months.

“As a stand-alone project offering a 33% IRR at a gold price of $1,700 per ounce, Čoka Rakita is a very

attractive asset, and we also continue to be excited by the exploration potential we are seeing at Čoka

Rakita and the three adjacent licences we hold . We are continuing to aggressively explore for additional

skarn targets in the area.”

Preliminary Economic Assessment Overview

The PEA contemplates underground mining of the Čoka Rakita project with a relatively standard

comminution, gravity and flotation flowsheet to treat 850,000 tonne s per annum of material, producing

saleable gravity and flotation concentrates.

The project is located approximately 35 kilometres northwest of the city of Bor in Serbia, which is a region

of the country with a long mining history, is proximal to existing roads and power lines and is approximately

320 kilometres northwest of DPM’s Chelopech mine in Bulgaria , which will allow easy access to existing

technical support functions . The project is also a strong fit with the Company’s underground mining and

processing expertise.

The PEA assumes start of construction in mid-2026 with first production of concentrate targeted for the first

half of 2028.

3

Key Operating and Financial Assumptions and Metrics

Assumptions

Gold price $ per ounce $1,700

Government royalty (NSR) % 5.0

Production and costs

Mineable Mineral Resource million tonnes 7.9

Average grade mined (life of mine) grams per tonne 5.68

Annual throughput tonnes per annum 850,000

Average grade processed (life of mine) g/t 5.68

Average metallurgical recovery % 88.8

Mine life years 10

Total gold produced (life of mine) million ounces 1.3

Life of mine gold payable % 98.4

Average annual gold production (life of mine) thousand ounces 129

Average annual gold production (first five years) thousand ounces 164

Life of mine operating unit costs

$ million $ per tonne processed

Mining $295 $37

Processing $134 $17

Filtered tailings and paste fill $41 $5

General & administrative $99 $13

Total cash costs1 $569 $72

All-in sustaining cost1 $ per gold ounce $715

Capital estimates

Initial capital $ millions $381

Sustaining capital (life of mine) $ millions $83

Closure costs3 $ millions $31

Project economics

Free cash flow (after tax)1,2 $ millions $891

NPV (after-tax, 5% discount)2 $ millions $588

IRR (after-tax)2 % 33%

Payback period years 2.4

1 Cash costs, all-in sustaining cost and free cash flow are non-GAAP measures. Refer to the “Non-GAAP Financial Measures” section

on page 10 of this news release for more information.

2 Current legislation in Serbia allows for tax relief for large investments for a maximum period of 10 years, subject to certain conditions.

The PEA assumes that the Čoka Rakita project is eligible for this tax relief and the effective income tax rate applied is 0% over the

project’s 10-year mine life.

3 Closure costs include a non-recoverable VAT of approximately $3 million.

The PEA is preliminary in nature and includes Inferred Mineral Resource estimates that are considered too

speculative geologically to have the economic considerations applied to them that would enable them to be

categorized as Mineral Reserves, and there is no certainty that the PEA will be realized. Mineral Resources

that are not Mineral Reserves do not have demonstrated economic viability.

4

Mining and Processing

The PEA mine plan assumes access from surface through twin declines and a spiral ramp to truck the

mined material to surface . Leveraging DPM’s experience and expertise from its underground Chelopech

mine, the anticipated mining method is conventional sublevel long-hole open stoping and paste backfill.

The PEA is based on a process flowsheet consisting of crushing and grinding to a P 80 of 53 µm, followed

by gravity concentration and sulphide flotation. The gravity concentrate will be marketable directly to gold

refineries, and the sulphide flotation concentrate will be suitable for processing by smelters in the region.

Average payability for the flotation concentrate is expected to be 97. 4%, and average payability for the

gravity concentrate is expected to be 99.8%, with a combined life of mine weighted average of 98.4%.

The PEA demonstrates a mineable Mineral Resource of 7.9 million tonnes above a cut -off grade of 2.5 g/t

for an initial mine life of 10 years, with two years of pre-production mine development. Average life of mine

gold production is expected to be approximately 129,000 ounces per year from an average gold head grade

of 5.68 g/t. Production in the first five full years is expected to average 164,000 ounces per year from an

average gold head grade of 6.70 g/t.

The production schedule as outlined in the PEA is presented in the table below:

Unit Total /

average

Pre

production Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10

Material mined Kt 7,941 57 558 860 853 853 853 853 850 857 857 491

Gold grade g/t 5.68 6.87 6.65 6.49 7.55 7.36 6.31 5.77 4.36 3.63 4.34 3.74

Material

processed Kt 7,941 - 615 860 853 853 853 853 850 857 857 491

Gold grade g/t 5.68 - 6.67 6.49 7.55 7.36 6.31 5.77 4.36 3.63 4.34 3.74

Recoveries

Gravity % 43.3 - 44.4 44.2 45.2 45.0 44.0 43.5 41.8 40.8 41.8 40.9

Flotation % 45.5 - 44.5 44.7 43.9 44.0 44.8 45.2 46.6 47.4 46.6 47.3

Combined % 88.8 - 88.9 88.9 89.1 89.0 88.8 88.7 88.4 88.2 88.4 88.2

Gold production Koz. 1,286 - 117 159 184 180 154 140 105 88 106 52

As part of the PFS, DPM will be evaluating several opportunities to optimize the mine plan and flowsheet ,

including optimizing the mine access development schedule to gain earlier access to the high-grade core

of mineralization . Additionally, opportunities to enhance the mine plan include optimizing the mine

sequencing and mining method parameters to enhance the grade and production profile.

5

Capital Expenditures

The initial project capital costs are expected to be approximately $381 million, which includes development

of the underground mine, construction of an 850,000 tonne per annum processing plant , a 5-million tonne

Dry Mine Waste Facility , and additional infrastructure, including haul and access roads, water treatment,

power supply and site services.

$ millions

Initial capital estimates

Mining $76

Processing $61

Infrastructure $97

Total direct costs $234

EPCM $27

Owners cost $25

Commissioning & inventory $9

Other $17

Total indirect cost $78

Contingency $69

Total initial capital expenditures $381

Sustaining and closure

Sustaining capital expenditures (average per year) $8

Closure costs3 $31

DPM will explore the potential to utilize existing processing infrastructure from the Company’s 850,000

tonne per annum processing facility currently in use at the Ada Tepe operation in Bulgaria, where mine life

is expected to end in 2026. While this is not currently expected to reduce initial capital expenditures, DPM

sees several potential benefits, including de -risking the project timeline in terms of long -lead items and

supply chain risk, as well as the ability to leverage the Company’s processing exper tise and maintenance

practices.

Čoka Rakita Gold Price Sensitivity Estimates

The table below shows the gold price sensitivity for the project, with the base case shaded in grey.

Gold price sensitivities

Average gold price

($/oz.)

$1,500

Base case

$1,700

$1,900

$2,100

NPV

(after-tax, 5% discount) $412 million $588 million $765 million $941 million

IRR

(after-tax) 26% 33% 39% 45%

3 Closure costs include a non-recoverable VAT of approximately $3 million.

6

Mineral Resource Estimate

The maiden Mineral Resource estimate (“MRE”) for the Čoka Rakita project, with an effective date of

November 16, 2023 (outlined in the table below) forms the basis of the mine design and schedule for the

PEA. The MRE is based on 81,000 metres of drilling at 30 -metre by 30-metre drill spacing in the core of

the deposit and up to 60 -metre by 60 -metre grid spacing on the periphery. For more information on the

Mineral Resource Estimate for Čoka Rakita , refer to the Čoka Rakita technical report entitled “Maiden

Mineral Resource Estimate – Čoka Rakita Gold Project, Serbia” with an effective date of November 16,

2023 (report date January 24, 2024) , available on our website at www.dundeeprecious.com and filed on

SEDAR+ at www.sedarplus.ca.

The ongoing infill drilling program at Čoka Rakita is designed to allow the conversion of the current Inferred

Mineral Resource estimate to the Indicated Mineral Resource category, with approximately 12,000 metres

drilled to date in 2024. Results from infill drilling continue to confirm the continuity of the mineralization and

have returned high-grade intercepts. Refer to the news release dated February 26, 2024 for more

information and for a review of recent results from infill drilling.

Čoka Rakita Mineral Resource Estimate

(Effective date November 16, 2023)

Resource category Tonnes

(Mt)

Gold grade

(g/t)

Contained gold

(K oz.)

Silver grade

(g/t)

Contained silver

(K oz.)

Inferred 9.79 5.67 1,783 1.21 382

Total 9.79 5.67 1,783 1.21 382

1) Mineral Resources are reported within smoothed MSO underground mining shapes generated at a 2 g/t Au cut -off and a minimum width constraint

of 5.0 m x 5.0 m x 2.5 m, to ensure Mineral Resources meet reasonable prospects for eventual economic extraction (“ RPEEE”) criteria. The cut-off

value of 2 g/t assumes $1,700/oz. The smoothing process allows for blocks below the cut-off to be included within the final shapes in order to emulate

the internal dilution that would be experienced during underground mining as per CIM Estimation of Mineral Resources and Mineral Reserves Best

Practices Guidelines prepared by the CIM Mineral Resource and Mineral Reserve Committee and adopted by the CIM Council on Nov ember 29,

2019.

2) Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

3) Figures have been rounded to reflect that this is an estimate and totals may not match the sum of all components .

Next Steps

In parallel to its exploration and infill drilling activities, DPM is advancing various activities to accelerate the

project development timeline , including geotechnical and hydrogeological drilling programs, further

metallurgical variability and optimization testwork, as well as several mining, processing and engineering

trade-off studies. All of these activities will form the basis of the PFS, which has been initiated by DPM and

is expected to be completed by the first quarter of 2025.

As a result of advancing Čoka Rakita to a PFS, DPM now expects its 2024 evaluation expenses to be

between $30 million to $35 million . This is an increase from the previous guidance of between $10 million

and $13 million, which was largely related to the costs of completing the PEA, as well as costs related to

geotechnical and condemnation drilling and permitting activities that are expected to occur over the course

of 2024.

7

Permitting and Stakeholder Engagement

Consistent with its approach across all operations and projects, DPM seeks to build and maintain strong

partnerships with local communities and governments. The Company has had a local presence in Serbia

since 2004 and has developed strong relationships in the region and will continue to proactively engage

with all stakeholders as the project advances.

Planning for the project will be focused on ensuring responsible environmental management and social

development in -line with industry best practices. DPM is committed to working closely with local

communities around the Čoka Rakita project to understand and support local development opportunities,

with a focus on maximizing benefits of the project for Serbia.

Permitting preparation activities are underway with a detailed timeline in order to support commencement

of construction in mid-2026, with good support and engagement from key regional and national authorities.

The Company has initiated preparations related to the environmental impact assessment (“EIA”), including

monitoring for baseline studies related to surface water, ground water, air quality and biodiversity, and plans

to initiate soil monitoring and a social study over the course of 2024 . The EIA is expected to be submitted

in the first quarter of 2026.

Ongoing Scout Drilling Program to Further Define Exploration Potential

The Company is aggressively pursuing additional potential skarn targets thr ough its scout drilling

campaigns within the Čoka Rakita licence , including a focus on the newly identified copper -gold manto

skarn mineralization at the Dumitru Potok and Frasen targets. Following the initial positive results reported

in the Company’s news release dated February 26, 2024 , several additional holes have been completed

which consistently exhibited the presence of polymetallic skarn alteration and mineralization within reactive

lithological units, particularly at the boundary of conglomerates and marbles, as well as fertile diorite and

monzodiorite dykes similar in appearance to the causative intrusion at Čoka Rakita, confirming DPM’s

conceptual targeting model. Since the start of 2024 , approximately 10,000 metres of scout and

condemnation drilling has been completed.

At Dumitru Potok, new holes DPDD012A and DPDD014B both intercepted strata-bound copper-gold manto

skarn mineralization at locations 40 metres to the south and 500 metres to the west, respectively, of

previously drilled hole s DPDD012. Hole DPDD017, which was collared 700 metres northeast of Čoka

Rakita and is still being drilled down toward the deeper marble target, has already encountered shallower

sandstones with strong skarn alteration exhibiting copper -gold mineralization. Five holes at Dumitru Potok

(DPDD016 through DPDD020) are currently in progress.

At Frasen, a new hole, BIDD226, was collared 1,300 metres north of Čoka Rakita, also intercepted both

the deeper strata-bound copper-gold manto skarn mineralization at a depth of approximately 600 metres,

as well as the shallower sandstone skarn copper-gold mineralization at a depth of about 150 metres. These

intercepts extend the footprint of the deeper copper -gold manto skarn target 450 metres north from

previously drilled BIDD223 and 550 met res northwest from the Dumitru Potok DPDD014B intercept and

8

highlight the potential for additional Čoka Rakita-like skarn mineralization on the property. A follow-up hole

(BIDD027) is currently being drilled to test extensions to the south of this target area.

On the Potaj Čuka and Pešter Jug exploration licences the Company has defined numerous targets and

aims to complete a magneto-telluric survey prior to the start of an aggressive drilling campaign in planned

to commence late in the second quarter of 2024.

Drilling recommenced on the Umka exploration licence with one additional hole completed during April

2024. The hole was collared on the western flank of the same large monzonite batholith that controls the

mineralization at Čoka Rakita and has confirmed the presence of sandstones with moderate to strong skarn

alteration, as well as fertile diorite and monzodiorite dykes, believed to be the causative intrusions. A second

hole to test extensions of this target at depth and laterally is currently being drilled.

For 2024, DPM has budgeted between $20 million and $22 million for exploration activities in Serbia and

plans to complete over 50,000 metres of exploration drilling on the property as it aggressively explores for

additional high-grade skarn targets.

For more information , refer to the news related dated February 26, 2024, and the Čoka Rakita technical

report entitled “Maiden Mineral Resource Estimate – Čoka Rakita Gold Project, Serbia” with an effective

date of November 16, 2023 (report date January 24, 2024) , both of which are available on our website at

www.dundeeprecious.com and filed on SEDAR+ at www.sedarplus.ca.

Technical Information and Technical Report Filing

The PEA and other scientific and technical information contained in this news release were prepared in

accordance with the Canadian regulatory requirements set out in National Instrument 43-101, Standards

of Disclosure for Mineral Projects (“NI 43-101”), and has been reviewed and approved by:

• Maria O’Connor, Technical Director Mineral Resources, of Environmental Resources Management Ltd.

(“ERM”) for mineral resource estimate;

• Daniel ( Niel) Morrison, P. Eng., Principal Process Engineer with DRA Global Limited (“DRA") for

metallurgical testwork and recovery methods;

• Stephan Blaho, P.Eng. MBA, Senior Principal Mining Engineer of WSP Global Inc . (“WSP”) for

underground mining methods and related mine infrastructure;

• Ninoslav Pavlovic, M. Sc., P. Eng., Senior Process Engineer for Backfill, Responsible Mining Solutions

Corp for paste backfill;

• Marcello Locatelli, P. Eng., Project Manager with DRA for project infrastructure;

• Eric Sellars, P. Eng., Consultant Geotechnical Engineer, SLR Consulting (Canada) Ltd. (“SLR”) for

tailings and waste rock management facilities;

• Luis Vasquez, M. Sc., P. Eng., Principal Hydrotechnical Engineer, SLR for site wide water balance;

• Kevin Leahy, PhD, CGeol, SiLC, of ERM for environmental studies, permitting, and social impact;