Dundee Precious Metals Announces First Quarter 2018 Production Results and Provides Notice of First Quarter 2018 Financial Results

Production Results

DUNDEE PRECIOUS METALS ANNOUNCES FIRST QUARTER 2018 PRODUCTION

RESULTS AND PROVIDES NOTICE OF FIRST QUARTER 2018 FINANCIAL RESULTS

Toronto, Ontario, April 13, 2018 – Dundee Precious Metals Inc. (TSX: DPM) (“DPM” or “the

Company”) announced its mine and smelter production results for the three months ended March

31, 2018 and confirmed the timing of the release of first quarter 201 8 operating and financial

results, together with the related conference call and webcast.

“We had another strong quarter at Chelopech and continue to make good progress on smelter

optimization initiatives,” said Rick Howes, President and CEO. “We remain on budget with

construction at our Krumovgrad gold project with production of first concentrate on track for the

fourth quarter of 2018.”

Ore milled and metals production at Chelopech and concentrate smelted at Tsumeb in the first

quarter 2018 are tracking in line with the Company’s 2018 guidance.

Production Highlights

First quarter 2018 mine and metals production at the Chelopech mine and complex concentrate

smelted at the Tsumeb smelter are provided below.

1. As disclosed in Management’s Discussion and Analysis (“MD&A”) for the period ended December 31, 2017, issued on February

15, 2018 and available at www.sedar.com.

First quarter Chelopech gold and copper production exceeded our planned production due to

higher ore grades and is expected to return to planned levels for the remainder of the year in line

with guidance. Payable gold sold was in line with expected concentrate shipment schedules and

is expected to increase in the coming quarters due to the timing of shipments.

Continued improved refractory performance in the Ausmelt furnace at Tsumeb has enabled the

start of the annual maintenance shutdown to be deferred from March to May 2018. Oxygen plant

performance was much improved in the first quarter relative to previous quarters and further

upside remains as a result of continued optimization. Replacement of the furnace roof and some

off-gas repairs completed in the quarter, together with adverse summer weather conditions,

affected operating rates and downtime, and served to offset the improved operating performance.

Chelopech

Tsumeb

Year 2018 Consolidated

Guidance 1

Q1 2018 Q1 2018

Ore milled (000s tonnes) 558.1 - 2,100 – 2,200

Metals contained in concentrate produced

Gold (‘000s ounces) 57.3 - 165 – 195

Copper (million pounds) 9.3 - 33.7 – 40.4

Payable metals in concentrate sold

Gold (‘000s ounces) 35.2 - 140 – 170

Copper (million pounds) 6.1 - 31.0 – 37.0

Complex Concentrate smelted (‘000s tonnes) - 54.1 220 – 250

2

While concentrate smelted was below planned levels for the quarter, the smelter is expected to

return to targeted levels in line with 2018 guidance.

At Krumovgrad, earthworks relating to the construction of the Integrated Mine Waste Facility was

completed, and installation of major foundations , equipment and structural steel continued

through the quarter, as planned. The forecast capital cost remains at $162 to $168 million,

compared with the original estimate of $178 million, with first concentrate production on track for

the fourth quarter of 2018.

First Quarter 2018 Results

The Company’s first quarter 201 8 operating and financial results are expected to be released

after market close on Wednesday, May 2, 2018. The press release, MD&A and consolidated

financial statements will be posted on SEDAR at www.sedar.com and on the Company’s website

at www.dundeeprecious.com.

The Company will hold a call and webcast to discuss its first quarter results on Thursday, May 3,

2018 at 9:00 am EST. The call will be hosted by Rick Howes, President and Chief Executive

Officer, who will be joined by Hume Kyle, Executive Vice President and Chief Financial Officer,

together with other members of the executive management team. The call will be accessible via

a live webcast and by telephone.

First Quarter 2018 Call and Webcast (Listen/View only)

Date: Thursday, May 3, 2018

Time: 9:00 am EST

Webcast: https://edge.media-server.com/m6/p/4opr3ody

Canada and USA Toll Free: 1-844-264-2104

Outside Canada or USA: 1-270-823-1169

Replay: 1-855-859-2056

Replay Passcode: 9475048

About Dundee Precious Metals

Dundee Precious Metals Inc. is a Canadian based, international gold mining company engaged

in the acquisition of mineral properties, exploration, development, mining and processing o f

precious metals. The Company's operating assets include the Chelopech operation, which

produces a copper concentrate containing gold and silver and a pyrite concentrate containing

gold, located east of Sofia, Bulgaria; and the Tsumeb smelter, a complex c opper concentrate

processing facility located in Namibia. DPM also holds interests in a number of developing gold

and exploration properties located in Bulgaria, including the Krumovgrad gold project, which

started construction in the fourth quarter of 2016 and is expected to commence production in the

fourth quarter of 2018, Canada, Serbia and Armenia, and its 10.2% interest in Sabina Gold &

Silver Corp.

Cautionary Note Regarding Forward Looking Statements

This press release contains “forward looking statements” that involve a number of risks and

uncertainties. Forward looking statements include, but are not limited to, statements with respect

to the estimated capital costs, operating costs and other project economics with respect to

Krumovgrad; timing of development, permitting, construction, commissioning activities and

commencement of production in respect of Krumovgrad; timing of further optimization work at

Tsumeb and potential benefits of the rotary fur nace installation; the price of gold, copper, silver

and acid; toll rates; metals exposure and stockpile interest deductions; the estimation of Mineral

Reserves and Mineral Resources and the realization of such mineral estimates; the timing and

amount of e stimated future production and output, life of mine, costs of production, cash costs

3

and other cost measures, capital expenditures, and timing of the development of new deposits;

results of economic studies; success of exploration activities; success of pe rmitting activities;

permitting time lines; currency fluctuations; requirements for additional capital; government

regulation of mining and smelting operations; environmental risks; reclamation expenses;

potential or anticipated outcome of title disputes o r claims; and timing and possible outcome of

pending litigation. Often, but not always, forward looking statements can be identified by the use

of words such as “plans”, “expects”, or “does not expect”, “is expected”, “budget”, “scheduled”,

“estimates”, “forecasts”, “outlook”, “intends”, “anticipates”, or “does not anticipate”, or “believes”,

or variations of such words and phrases or that state that certain actions, events or results “may”,

“could”, “would”, “might” or “will” be taken, occur or be achieved. Forward looking statements are

based on the opinions and estimates of management as of the date such statements are made

and they involve known and unknown risks, uncertainties and other factors which may cause the

actual results, performance or achievements of the Company to be materially different from any

other future results, performance or achievements expressed or implied by the forward looking

statements. Such factors include, among others: the uncertainties with respect to the actual

results of current exploration activities; actual results of current reclamation activities; conclusions

of economic evaluations and economic studies; changes in project parameters as plans continue

to be refined; possible variations in ore grade or recovery rates; fai lure of plant, equipment or

processes to operate as anticipated; accidents, labour disputes and other risks of the mining

industry; delays in obtaining governmental approvals or financing or in the completion of

development or construction activities; uncertainties inherent with conducting business in foreign

jurisdictions where corruption, civil unrest, political instability and uncertainties with the rule of law

may impact the Company’s activities; fluctuations in metal and acid prices, toll rates and for eign

exchange rates; unanticipated title disputes; claims or litigation; limitation on insurance coverage;

cyber attacks; failure to successfully integrate MineRP’s business; failure to realize projected

synergies and financial results from MineRP business ; risks relating to operating a technology

business reliant on the ownership, protection and ongoing development of key intellectual

properties; as well as those risk factors discussed or referred to in the Company’s MD&A under

the heading “Risks and Uncer tainties” and under the heading “Cautionary Note Regarding

Forward Looking Statements” which include further details on material assumptions used to

develop such forward looking statements and material risk factors that could cause actual results

to differ materially from forward looking statements, and other documents (including without

limitation the Company’s most recent AIF) filed from time to time with the securities regulatory

authorities in all provinces and territories of Canada and available on SEDAR at www.sedar.com.

Although the Company has attempted to identify important factors that could cause actual actions,

events or results to differ materially from those described in forward looking statements, there

may be other factors that cause actions, events or results not to be anticipated, estimated or

intended. There can be no assurance that forward looking statements will prove to be accurate,

as actual results and future events could differ materially from those anticipated in such

statements. Unless required by securities laws, the Company undertakes no obligation to update

forward looking statements if circumstances or management’s estimates or opinions should

change. Accordingly, readers are cautioned not to place undue reliance on forward look ing

statements.

4

For further information please contact:

DUNDEE PRECIOUS METALS INC.

Rick Howes

President and

Chief Executive Officer

Tel: (416) 365-2836

[email protected]

Janet Reid

Manager, Investor Relations

Tel: (416) 365-25479

[email protected]