Dundee Precious Metals Announces First Quarter 2017 Production Results and Provides Notice of First Quarter 2017 Financial Results

Production Results

DUNDEE PRECIOUS METALS ANNOUNCES FIRST QUARTER 2017 PRODUCTION

RESULTS AND PROVIDES NOTICE OF FIRST QUARTER 2017 FINANCIAL RESULTS

Toronto, Ontario, April 12, 2017 – Dundee Precious Metals Inc. (TSX: DPM) (“DPM” or “the

Company”) announced its mine and smelter production results for the three months ended March

31, 2017 and confirmed the timing of the release of first quarter 2017 operating and financial

results, together with the related conference call and webcast.

“We continue to make good progress on smelter optimization and remain on track with

construction at the Krumovgrad gold project ,” said Rick Howes, P resident and CEO. “With the

advance of the refractory reline at the Ausmelt by one quarter, we identified an opportunity to

benefit from an early introduction of the matte holding furnace that will serve to improve

performance at the smelter starting in the second quarter of 2017.”

Ore milled and metals production in the first quarter 2017 were in line with the Company’s 2017

guidance.

Production Highlights

First quarter 2017 mine and metals production at the Chelopech mine and complex concentrate

smelted at the Tsumeb smelter are provided below.

1. As disclosed in Management’s Discussion and Analysis (“MD&A”) for the period ended December 31, 2016 and issued on

February 15, 2017.

First quarter Chelopech gold and copper production was in line with the 2017 mine plan. Near-

term, it is expected that the mining sequence will result in higher gold and copper production in

copper concentrate as a result of mining higher grade zones in the planned mining sequence for

2017. Chelopech remains on track to achieve 2017 guidance.

At the Tsumeb smelter, the first quarter throughput was impacted by the advancement of the

Ausmelt shutdown into February from the original May -June timing to correct accelerated

refractory wear. Aligning the Ausmelt shutdown with the first con verter relines, scheduled for

Chelopech

Tsumeb

Consolidated

Year 2017

Consolidated

Guidance 1

Q1 2017 Q1 2017 Q1 2017

Ore milled (‘000s tonnes) 540.6 - 540.6 2,040 – 2,200

Metals contained in concentrates produced

Gold (‘000s ounces) 46.4 - 46.4 157 - 174

Copper (million pounds) 8.2 - 8.2 33.7 – 37.0

Payable metals in concentrates sold

Gold (‘000s ounces) 43.5 - 43.5 135 - 150

Copper (million pounds) 8.3 - 8.3 32.0 – 35.0

Complex Concentrate smelted (‘000s tonnes) - 41.6 41.6 210 - 240

2

February, allows the smelter to advance the installation of the holding furnace which is expected

to reduce the impact of the next converter relines on Ausmelt performance. Good progress was

made on converter and Ausmelt optimization through the quarter.

At Krumovgrad, earthworks continue to progress in accordance with the project plan, with first

concrete forecast to be poured in April as planned, and consistent with the project schedule to

commence operations in late 2018. In addition, the previously announced C$43.7 million strategic

equity investment by the European Bank for Reconstruction and Development closed on January

24, 2017. Proceeds will be used for the construction of the Krumovgrad Project and will serve to

further strengthen the Company’s financial position and flexibility during the construction phase

of this project.

First Quarter Results

The Company’s first quarter 2 017 operating and financial results are expected to be released

after market close on Wednesday, May 3, 2017. The press release, MD&A and consolidated

financial statements will be posted on SEDAR at www.sedar.com and on the Company’s website

at www.dundeeprecious.com.

The Company will hold a call and webcast to discuss its first quarter results on Thursday, May 4,

2017 at 9:00 am EST. The call will be hosted by Rick Howes, President and Chief Executive

Officer, who will be joined by Hume Kyle, Executive Vice President and Chief Financial Officer,

together with other members of the executive management team. The call will be accessible via

a live webcast and by telephone.

First Quarter 2017 Call and Webcast (Listen/View only)

Date: Thursday, May 4, 2017

Time: 9:00 am EST

Webcast: http://edge.media-server.com/m/p/af384njn

Canada and USA Toll Free: 1-866-223-7781

Outside Canada or USA: 416-340-2216

Replay: 905-694-9451

Replay Passcode: 8804791#

About Dundee Precious Metals

Dundee Precious Metals Inc. is a Canadian based, international gold mining company engaged

in the acquisition of min eral properties, exploration, development, mining and processing of

precious metals. The Company's operating assets include the Chelopech operation, which

produces a copper concentrate containing gold and silver and a pyrite concentrate containing

gold, located east of Sofia, Bulgaria; and the Tsumeb smelter, a complex copper concentrate

processing facility located in Namibia. DPM also holds interests in a number of developing gold

and exploration properties located in Bulgaria, Serbia, and northern Canada, including the

Krumovgrad gold project, which started construction in the fourth quarter of 2016 and is expected

to commence production in the fourth quarter of 2018, and its 10.7% interest in Sabina Gold &

Silver Corp.

Cautionary Note Regarding Forward Looking Statements

This press release contains “forward looking statements” that involve a number of risks and

uncertainties. Forward looking statements include, but are not limited to, statements with respect

to the future price of gold, copper, zinc, silver and acid, future toll rates, the estimation of mineral

reserves and resources, the realization of such mineral estimates, the timing and amount of

estimated future production and output, life of mine, costs of production, cash costs and other

cash me asures, capital expenditures, costs and timing of the development of new deposits,

3

success of exploration activities, success of permitting activities, permitting time lines, currency

fluctuations, requirements for additional capital, government regulation of mining operations,

environmental risks, reclamation expenses, the potential or anticipated outcome of title disputes

or claims and timing and possible outcome of pending litigation. Often, but not always, forward

looking statements can be identified by the use of words such as “plans”, “expects”, or “does not

expect”, “is expected”, “budget”, “scheduled”, “estimates”, “forecasts”, “outlook”, “intends”,

“anticipates”, or “does not anticipate”, or “believes”, or variations of such words and phrases or

that state that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken,

occur or be achieved. Forward looking statements are based on the opinions and estimates of

management as of the date such statements are made and they inv olve known and unknown

risks, uncertainties and other factors which may cause the actual results, performance or

achievements of the Company to be materially different from any other future results, performance

or achievements expressed or implied by the f orward looking statements. Such factors include,

among others: the actual results of current exploration activities; actual results of current

reclamation activities; conclusions of economic evaluations and economic studies; changes in

project parameters as plans continue to be refined; future prices of gold, copper, zinc, silver and

acid; future toll rates; possible variations in ore grade or recovery rates; failure of plant, equipment

or processes to operate as anticipated; accidents, labour disputes and other risks of the mining

industry; delays in obtaining governmental approvals or financing or in the completion of

development or construction activities, uncertainties inherent with conducting business in foreign

jurisdictions where corruption, civil unrest, political instability and uncertainties with the rule of law

may impact the Company’s activities; fluctuations in metal and acid prices, toll rates and foreign

exchange rates; unanticipated title disputes; claims or litigation; limitation on insurance coverage;

cyber attacks; as well as those risk factors discussed or referred to in the Company’s MD&A under

the heading “Risks and Uncertainties” and under the heading “Cautionary Note Regarding

Forward Looking Statements” which include further details on material assumptions used to

develop such forward looking statements and material risk factors that could cause actual results

to differ materially from forward looking statements, and other documents (including without

limitation the Company’s 2016 AIF) filed from time to time with the securities regulatory authorities

in all provinces and territories of Canada and available on SEDAR at www.sedar.com. There can

be no assurance that forward looking statements will prove to be accurate, as actual results and

future events could differ materially from those anticipated in such statements. Unless required

by securities laws, the Company undertakes no obligation to update forward looking statements

if circumstances or management’s estimates or opinions should change. Accordingly, readers are

cautioned not to place undue reliance on forward looking statements.

For further information please contact:

DUNDEE PRECIOUS METALS INC.

Rick Howes

President and

Chief Executive Officer

Tel: (416) 365-2836

[email protected]

Lori Beak

Senior Vice President,

Governance, and Corporate

Secretary

Tel: (416) 365-5165

[email protected]