Vancouver, British Columbia--(Newsfile Corp. - October 24, 2022) -
District Metals Corp. (TSXV:
DMX) (FSE: DFPP); ("District" or the "Company")
is pleased to announce the identification of four
new high priority targets on the polymetallic Gruvberget Property located in the Bergslagen Mining
District of south-central Sweden. Detailed soil sampling grids have been completed over the new target
areas, and Ionic Leach (IL) geochemical results are expected back before the end of 2022.
The four new target zones were identified through compilation work that comprised our recent SkyTEM
geophysical survey results (
see news release
) in conjunction with geological and historical exploration
data on the Property.
New Target Areas (Figures 1 and 2):
Target zone 1: Backen
A Joint Venture (JV) between LKAB and BP Minerals discovered
two high grade
polymetallic boulders (up to 15% Zn, 4.8% Cu and 23 g/t Ag)
1
at the Backen zone in
1980s. The JV was unable to locate the bedrock source for these boulders, which looks to
be potentially sourced further to the north-northwest from the JV's area of work.
Target zone 2: Gyllingen
Boliden drilled seven short holes into "sphalerite mineralization" (zinc sulphide)
in
the mid-1980s. Three drill hole collars were located in the field where the drilling direction
was observed as parallel to the geological trend. No detailed information is available on
these historical mineralized drill holes, but the
Gyllingen zone coincides with a high
priority magnetic and conductive anomaly from our recent SkyTEM survey
.
Target zone 3: North zone extension
The LKAB-BP Minerals JV conducted exploration work north of the Gruvberget North zone,
which included drilling geophysical anomalies with 918 m in six holes during 1984.
Historical drilling extended polymetallic mineralization to the north of the North zone
with a plunge to the north.
Drill hole 84-GRU-03 returned 1.0 m of 1.1% Zn and 47 g/t Ag
that was within a larger interval of lower grade mineralization
2
.
Target zone 4: South zone extension
A
magnetic high anomaly located about 300 m south-southwest from the
Gruvberget South zone
was drilled with 363.5 m in three holes by NSG (exploration
division of Geological Survey of Sweden) in 1982.
All three drill holes encountered a 6.0
to 7.0 m wide zone with weak polymetallic mineralization
that returned up to 0.1% Cu,
0.08% Pb, 0.09% Zn
3
that is
interpreted as a potential aureole around a mineralized
zone
.
Garrett Ainsworth, CEO of District, commented: "Following our successful maiden drill program at the
North Gruvberget zone during the Spring-Summer of 2022, we thoroughly reviewed all publicly available
data sets along with our recently interpreted SkyTEM magnetic and conductive anomalies, which has
identified four new high priority targets. We believe that these targets have high potential to extend
known polymetallic mineralized bodies or to host new bodies of polymetallic mineralization, and we look
forward to testing them in the next phase of drilling.
"To further optimize our drill target prioritization, we have conducted a detailed soil sampling grid over
each of the four target areas that include Backen, Gyllingen, North zone extension, and the South zone
extension. We previously carried out a soil sample orientation survey over and adjacent north of the
North zone, which established IL analysis as the most effective analytical method to identify blind
polymetallic mineralization in bedrock that is covered by 2 to 20 m of glacial overburden.
"Any soil geochemical anomalies identified at the four target areas that are coincident with existing
geophysical anomalies and historical mineral occurrences will assist with drill target prioritization."
Background
The Geological Survey of Sweden (SGU) have scanned and digitized the majority of their paper archive,
which is publicly accessible via their web service 'GeoLagret'. Here, you can (geographically) search
and download geological maps, data and reports, including relinquished exploration data by previous
exploration companies previously active in the area of interest.
The historic Gruvberget South zone had historic bulk test production from 1926 to 1936 and 1987 to
1989 that totaled approximately 40,000 tonnes at 90 g/t Ag, 5.1% Zn, 1.9% Pb, and 0.3% Cu
4
. The
Gruvberget South and North zones were previously owned by the Bredenberg family under the name AB
Gruvbergsgruvan from 1900 to 1999. Past reports detailed how various mining companies (including the
LKAB-BP Minerals JV, Stora Kopparberg and Boliden) tried to negotiate a deal with the Bredenberg
family, but were not successful
2,3
.
LKAB started regional exploration activities within the Gruvberget Property in 1978 that included
bedrock mapping, boulder hunting, various soil sampling campaigns and both airborne and ground
geophysical surveys
1,2,5
. This generated various target areas which were mainly investigated through a
JV between LKAB and BP Minerals from 1983 to 1986. Boliden staked a small exploration license north
of Gyllingen Lake (1982-1988) where their historical drilling encountered zinc sulphide mineralization
with seven short drill holes, and NSG (Exploration division SGU) explored south of the Gruvberget South
zone (1982)
3
.
The Company has recently completed a detailed soil sampling program at the four high priority target
areas. The soil samples will be analyzed using IL analysis, which was determined as the most effective
analytical method from a successful soil sampling orientation survey. At each target area, soil samples
were recovered 40 m along lines that were 100 m apart, and grids were planned according to a glacial
direction from the north. Duplicate soil samples were collected at every 20
th
sample location. High
priority drill targets will be selected based on soil geochemical anomalies coincident with SkyTEM
geophysical anomalies and historical mineral occurrences.
Figure 1: SkyTEM Geophysical Data with Four New High Priority Targets
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/7971/141608_7f1d8655a47f49da_002full.jpg
Figure 2: Detailed Soil Sampling Grids at Four New High Priority Targets
To view an enhanced version of this graphic, please visit:
https://images.newsfilecorp.com/files/7971/141608_7f1d8655a47f49da_003full.jpg
References
1
Letho, T. (1984). Project 3817 - Gruvberget 1-May - 31-Dec-1984. Exploration report LKAB/BP
Minerals. Report No. Bsg 84-373
2
Letho, T. (1984). Project 3817 - Gruvberget 1-April - 31-Dec-1983. Exploration report LKAB/BP
Minerals. Report No. Bsg 84-342
3
Hammergren, P. (1982). Prospekteringsborrning inom Utmälet Luttjärnsgruvan. Exploration report
Sverige Geologiska AB - NSG. BRAP 82594
4
Ripa, M. (2015). Malmer, industriella mineral och bergarter i Dalarnas län. Geological Survey of
Sweden (SGU). Rapporter och meddelanden 139, Del 1
5
Flood, B. (1982). Prospekteringsarbeten i Gruvbergsomrädet (Leksand), Kopparbergs Län Juni 1978
till Mars 1982. Exploration report LKAB Prospektering AB. Grb 276
Technical Information
All scientific and technical information in this news release has been prepared by, or approved by
Garrett Ainsworth, PGeo, President and CEO of the Company. Mr. Ainsworth is a qualified person for
the purposes of National Instrument 43-101 -
Standards of Disclosure for Mineral Projects.
The soil samples in this news release were logged and bagged before submittal to ALS Geochemistry
in Malå, Sweden where the samples were prepared for analysis. A 50 gram soil sample was sent to
ALS Geochemistry in Ireland (an accredited mineral analysis laboratory) for analysis. Ionic Leach
samples use a static sodium cyanide leach with a highly sensitive ICP-MS finish ("ME-MS23").
Some of the data disclosed in this news release is related to historical drilling and exploration results.
District has not undertaken any independent investigation of the sampling nor has it independently
analyzed the results of the historical exploration work in order to verify the results. District considers the
historical drilling and exploration results relevant as the Company is using this data as a guide to plan
exploration programs. The Company's current and future exploration work includes verification of the
historical data through drilling.
Mr. Ainsworth has not verified any of the information regarding any of the properties or projects referred
to herein other than the Gruvberget Property. Mineralization on any other properties referred to herein is
not necessarily indicative of mineralization on the Gruvberget Property.
About District Metals Corp.
District Metals Corp. is led by industry professionals with a track record of success in the mining
industry. The Company's mandate is to seek out, explore, and develop prospective mineral properties
through a disciplined science-based approach to create shareholder value and benefit other
stakeholders.
The advanced exploration stage Tomtebo Property is located in the Bergslagen Mining District of south-
central Sweden is the Company's main focus. Tomtebo comprises 5,144 ha and is situated between the
historic Falun Mine and Boliden's Garpenberg Mine that are located 25 km to the northwest and
southeast, respectively. Two historic polymetallic mines and numerous polymetallic showings are located
on the Tomtebo Property along an approximate 17 km trend that exhibits similar geology, structure,
alteration and VMS/SedEx style mineralization as other significant mines within the district.
Mineralization that is open at depth and along strike at the historic mines on the Tomtebo Property has
not been followed up on, and modern systematic exploration has never been conducted on the Property.
For further information on the Tomtebo Property, please see the technical report entitled "NI 43-101
Update Technical Report on the Tomtebo Project, Bergslagen Region of Sweden" dated effective
October 15, 2020 and amended and restated on February 26, 2021, which is available on SEDAR at
www.sedar.com
.
On Behalf of the Board of Directors
"
Garrett Ainsworth
"
President and Chief Executive Officer
(604) 288-4430
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in
policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of
this release.
Cautionary Statement Regarding "Forward-Looking" Information.
This news release contains certain statements that may be considered "forward-looking information" with respect to the Company within the
meaning of applicable securities laws. In some cases, but not necessarily in all cases, forward-looking information can be identified by the use of
forward-looking terminology such as "plans", "targets", "expects" or "does not expect", "is expected", "an opportunity exists", "is positioned",
"estimates", "intends", "assumes", "anticipates" or "does not anticipate" or "believes", or variations of such words and phrases or statements that
certain actions, events or results "may", "could", "would", "might", "will" or "will be taken", "occur" or "be achieved" and any similar expressions. In
addition, any statements that refer to expectations, predictions, indications, projections or other characterizations of future events or
circumstances contain forward-looking information. Statements containing forward-looking information are not historical facts but instead
represent management's expectations, estimates and projections regarding future events. Forward-looking statements in this news release
relating to the Company include, among other things, statements relating to the Company's planned exploration activities, including its drill target
strategy and next steps for the Gruvberget Property; and the Company's interpretations and expectations about the results on the Gruvberget
Property.
These statements and other forward-looking information are based on opinions, assumptions and estimates made by the Company in light of its
experience and perception of historical trends, current conditions and expected future developments, as well as other factors that the Company
believes are appropriate and reasonable in the circumstances, as of the date of this news release, including, without limitation, assumptions
about the reliability of historical data and the accuracy of publicly reported information regarding past and historic mines in the Bergslagen
district; the Company's ability to raise sufficient capital to fund planned exploration activities, maintain corporate capacity; and stability in financial
and capital markets.
Forward-looking information is necessarily based on a number of
opinions, assumptions and estimates that, while considered reasonable by the
Company as of the date such statements are made, are subject to known and unknown risks, uncertainties, assumptions and other factors that
may cause the actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such
forward-looking information, including but not limited to risks associated with the following: the reliability of historic data regarding the Tomtebo
Property; the Company's ability to raise sufficient capital to finance planned exploration (including incurring prescribed exploration expenditures
required by the Tomtebo Purchase Agreement, failing which the Tomtebo Property will be forfeited without any repayment of the purchase price);
the Company's limited operating history; the Company's negative operating cash flow and dependence on third-party financing; the uncertainty of
additional funding; the uncertainties associated with early stage exploration activities including general economic, market and business
conditions, the regulatory process, failure to obtain necessary permits and approvals, technical issues, potential delays, unexpected events and
management's capacity to execute and implement its future plans; the Company's ability to identify any mineral resources and mineral reserves;
the substantial expenditures required to establish mineral reserves through drilling and the estimation of mineral reserves or mineral resources;
the Company's dependence on one material project, the Tomtebo Property; the uncertainty of estimates used to calculated mineralization figures;
changes in governmental regulations; compliance with applicable laws and regulations; competition for future resource acquisitions and skilled
industry personnel; reliance on key personnel; title matters; conflicts of interest; environmental laws and regulations and associated risks,
including climate change legislation; land reclamation requirements; changes in government policies; volatility of the Company's share price; the
unlikelihood that shareholders will receive dividends from the Company; potential future acquisitions and joint ventures; infrastructure risks;
fluctuations in demand for, and prices of gold, silver and copper; fluctuations in foreign currency exchange rates; legal proceedings and the
enforceability of judgments; going concern risk; risks related to the Company's information technology systems and cyber-security risks; and risk
related to the outbreak of epidemics or pandemics or other health crises, including the recent outbreak of COVID-19. For additional information
regarding these risks, please see the Company's Annual Information Form, under the heading "Risk Factors", which is available at
www.sedar.com
. These factors and assumptions are not intended to represent a complete list of the factors and assumptions that could affect the
Company. These factors and assumptions, however, should be considered carefully. Although the Company has attempted to identify factors that
would cause actual actions, events or results to differ materially from those disclosed in the forward-looking statements or information, there may
be other factors that cause actions, events or results not to be as anticipated, estimated or intended. Also, many of such factors are beyond the
control of the Company. Accordingly, readers should not place undue reliance on forward-looking statements or information. The forward-looking
information is made as of the date of this news release, and the Company assumes no obligation to publicly update or revise such forward-looking
information, except as required by applicable securities laws.
All scientific and technical information contained in this news release has been prepared by or reviewed and approved by Garrett Ainsworth,
PGeo, President and CEO of the Company. Mr. Ainsworth is a qualified person for the purposes of National Instrument 43-101 - Standards of
Disclosure for Mineral Projects.
To view the source version of this press release, please visit
https://www.newsfilecorp.com/release/141608