Denison Reports Impressive Financial and Operational Results for 2023 Including Significant Increase in Phoenix ISR Project Economics and a $134 Million Gain on Physical Uranium Holdings
1
Denison Mines Corp.
1100 – 40 University Ave
Toronto, ON M5J 1T1
www.denisonmines.com
PRESS RELEASE
Denison Reports Impressive Financial and Operational Results for 2023
Including Significant Increase in Phoenix ISR Project Economics and
a $134 Million Gain on Physical Uranium Holdings
Toronto, ON – February 29, 2024. Denison Mines Corp. (‘Denison’ or the ‘Company’) (TSX: DML, NYSE American:
DNN) today filed its Audited Consolidated Financial St atements and Management’s Discussion & Analysis (‘MD&A’)
for the year ended December 31, 2023. Both documents are or will be available on the Company’s website at
www.denisonmines.com, SEDAR+ (at www.sedarplus.ca) and EDGAR (at www.sec.gov/edgar.shtml). The highlights
provided below are derived from these documents and should be read in conjunction with them. All amounts in this
release are in Canadian dollars unless otherwise stated.
The Company reported earnings per share (‘EPS’) from continuing operations of $0.11 for the year ended December
31, 2023, representing a 450% increase from the 2022 EPS of $0.02, driven by the recognition of a significantly larger
gain on the Company’s physical uranium holdings offset by operating expenses primarily related to the Company’s
advancement of its flagship Wheeler River Project.
A description of the Company’s plans and budget for 2024 (‘2024 Outlook’) is included in the MD&A.
David Cates, President and CEO of Denison commented, “The sheer magnitude of Denison’s numerous
operational accomplishments in 2023 refl ects an extraordinarily productive ti me for our Company. With the
completion of the Phoenix Feasib ility Study in June, we have cemente d Phoenix’s position as a globally
leading uranium development project, showcasing Denis on’s industry leadership in the de-risking and
application of the In-Situ Recovery mining method in th e Athabasca Basin. The results from an updated Pre-
Feasibility Study for the Gryphon deposit, completed as part of a newly issued Technical Report for the
Company’s flagship Wheeler River property, also demonstrate the significant potential additional leverage that
comes from Denison’s diversified portfolio of projects.
We achieved a notable milestone for the project in 2023 with the signing of a Shared Prosperity Agreement
with English River First Nation supporting the development and operation of Wheeler River. The SPA reflects
ERFN’s consent to the advancement of the project and acknowledges that Wheeler River is located within
ERFN’s Ancestral Lands. The SPA further describes a mutual commitment to maintain an open, respectful,
and cooperative relationship between Denison and ERFN to ensure mutual prosperity as the development and
operation of the project progresses.
Significant progress has also been made in support of permitting the planned Phoenix ISR mine, consistent
with our plans and objective to achie ve first production in 2027 or 2028. The Company has responded to
multiple rounds of technical comments and information requests from both the Provincial and Federal
regulators in respect of its draft Environmental Impact Statement and has successfully reduced the number of
outstanding requests, including confirmation from the Saskatchewan Ministry of Environment that it is
satisfied with our responses and that Denison may proceed to finalize the EIS for provincial approval.
The evolution of the uranium market in 2023 has been quite interesting and has had a significant positive
impact on Denison’s balance sheet. With the uranium price rising from US$48/lb U3O8 at the start of the year
to US$91/lb U3O8 at year end, Denison’s strategic physical uranium holdings have appreciated considerably –
driving the Company’s highest earnings per share since 20 07. It is apparent that the uranium market has
entered a new phase and we are pleased to see the market recognize the gr owing scarcity of available future
uranium production and that higher prices are required to incentivize sufficient new uranium production to
meet current and growing demand. Importantly, the higher price environment follows an initial wave of long-
term contracting that has already incentivized a seri es of mine restarts from the industry’s incumbent
producers. This transition to a production cost-based market environm ent is consistent with Denison’s
expectations and validates the Company’s tireless wo rk to advance Phoenix towards a final investment
decision during several challenging years of negative uranium market conditions.
2
Our hard work in past years has paved the way for an incredibly exciting time for our Company as we focus
on delivery of our Phoenix ISR project. As outlined in our 2024 Outlook, the Company’s expected priorities for
Phoenix include advancement of detailed design engineering, long-lead procurement, permitting, and project
financing. In parallel, we plan to continue to pursue opportunities to drive additional value from our diverse
project portfolio – including preparations for the re start of uranium mining at McClean Lake, a robust
exploration program, and advancement of both the Midw est and Waterbury Lake projects through the next
stages of technical and economic evaluations.”
Highlights
Exceptional annual earnings fr om continuing operations driven by $134 million ga in on physical uranium
investments
During 2023, the Company’s earnings from continuing operations of $89.4 million ($0.11 per share) were driven by
an impressive $134.2 million fair value gain on the Co mpany’s investments in physical uranium. The Company
acquired 2.5 million pounds U3O8 in 2021 at an average price of $36.67 per pound U3O8 (US$29.66 per pound U3O8).
In the fourth quarter, the Company sold 200,000 pounds U3O8 at an average selling price of $99.50 per pound U3O8
(US$73.38 per pound U3O8), representing a realized gain on sale of $12.6 million (US$8.8 million). As at December
31, 2023, the Company’s remaining uranium portfolio has increased in value by 228% to $120.35 per pound U 3O8
(US$91.00 per pound U3O8) for an aggregate value of approximately $276.8 million (US$209.3 million).
Feasibility Study for Wheeler River Phoenix deposit yields significant increase in project economics
In June 2023, Denison released the results of the Feasibili ty Study (‘Phoenix FS’) completed for In-Situ Recovery
(‘ISR’) mining of the high-grade Phoenix uranium deposit (‘Phoenix’), which is part of the Company’s flagship Wheeler
River Project (‘Wheeler River’ or the ‘Project’).
The Phoenix FS demonstrates robust economics including:
Base case pre-tax Net Present Value (‘NPV’) (8%) of $2.34 billion (100% ownership-basis) representing a 150%
increase in the base-case pre-tax NPV8% for Phoenix from the 2018 Pre-Feasibility Study (‘2018 PFS’).
Very robust base-case pre-tax Internal Rate of Return (‘IRR’) of 105.9%.
Adjusted base case after-tax NPV 8% of $1.56 billion (100% basis) and IR R of 90.0% – with Denison’s effective
95% interest in the project equating to an adjusted base case after-tax NPV8% of $1.48 billion.
Base case pre-tax and after-tax (adjusted) payback per iod of 10 months – equating to a reduction of 11 months
for the pre-tax payback period from the 2018 PFS.
Optimized production profile, based on ISR mine planning efforts evaluating production potential for individual
well patterns – resulting in an increase to the planned ra te of production by approximately 43% during the first
five years of operations.
Estimated pre-production capital costs of under $420 million (100% basis), yielding an impressive base-case
after-tax (adjusted) NPV to initial capital cost ratio in excess of 3.7 to 1.
Robust economics that easily absorb cost-inflation and design changes impacting both operating and capital
costs, confirming Phoenix’s estimated cash operating an d all-in costs to be amongst the lowest-cost uranium
mining projects in the world.
Phoenix FS plans aligned and costed to meet or exceed environmental criteria expected to be required by the
ongoing regulatory approval process.
Updated mineral resource estimate, reflecting the resu lts of 70 drill holes completed in support of ISR de-risking
and resource delineation activities, which has upgraded 30.9 million pounds U 3O8 into measured mineral
resources. The updated mineral resource also resulted in an increase to the average grade of the Zone A high-
grade domain, which is now estimat ed to contain 56.3 million pounds U 3O8 in Measured and Indicated mineral
resources at an average grade of 46.0% U3O8.
Upgraded 3.4 million pounds U 3O8 into Proven mineral reserves, representing the equivalent of 85% of production
planned during the first calendar year of operations.
Phoenix ISR de-risking completed and focus transitions to engineering design
The Phoenix FS reflects independent third-party validation of the selection of the ISR mining method for Phoenix and
builds on the findings from a comprehensive and rigorous multi-year technical de-risking process highlighted by the
highly successful completion of the le aching and neutralization phases of the Phoenix Fe asibility Field Test (‘FFT’)
in late 2022.
Through the technical de-risking process, Denison acquired extensive deposit-specific data and developed a robust
ISR mine planning model that involved evaluation of the pr oduction potential for individual well patterns. With
3
technical de-risking of the application of ISR at Phoenix substantially complete, Denison undertook front-end
engineering design (‘FEED’) to support the advancement of the planned Phoenix operat ion and, with the results
thereof substantially complete, is transitioning into detailed engineering design.
Landmark Shared Prosperity Agreement signed with English River First Nation
In September 2023, Denison announced the signing of a Shared Prosperity Agreement (‘SPA’) with English River
First Nation (‘ERFN’) supporting the development and operation of Wheeler River. The SPA received support from
a substantial majority of ERFN members who participated in a ratification vote on its key terms.
The signing of the SPA follows years of active enga gement, including a four-month-long ERFN-led community
consultation process ahead of the ratification vote, and represents a significant mile stone in the history of both
Denison's relationship with ERFN and the Project.
The SPA acknowledges that the Project is located within ERFN’s Ancestral Lands and provides Denison with ERFN’s
consent to advance the Project. Additionally, the SPA outli nes a shared recognition that ERFN is the Knowledge
Keeper of the culture, wa ys, customs, and values of ERFN in rela tion to the environment and its Members and
reflects ERFN’s desire to prioritize sustainability. Amongst other key commitments, the SPA provides ERFN and its
Members with (i) an important role in environmental monitoring and management, and (ii) benefits from community
investment, business opportunities, employment and training opportunities, and financial compensation. Overall, the
SPA describes a mutual commitment to maintain an open, respectful, and cooperative relationship between Denison
and ERFN to ensure mutual prosperity as the development and operation of the Project progresses.
Phoenix Environmental Impact Statement (‘EIS’) advanced through regulatory review
Denison’s draft EIS for Phoenix was submitted to the Sa skatchewan Minister of Envi ronment (‘SKMOE’) and the
Canadian Nuclear Safety Commission (‘CNSC’) in late 2022. The EIS submissi on outlines the Company’s
assessment of the potential effects, including applicable mitigation measures, of the proposed ISR uranium mine and
processing plant planned for Phoenix, and reflects several years of baseline environmental data collection, technical
assessments, plus extensive engagement and consultation with Indigenous and non-Indigenous interested parties.
In the first quarter of 2023, the Company received technical comments and information requests from both regulatory
agencies and the Company has provided technical responses to both the Provincial and Federal regulators.
In August 2023, reflective of the extensive efforts undertaken by and for the Company, the CNSC deemed complete
the Company’s responses to the approximately 250 Federal comments from the CNSC. In November 2023, a second
round of information requests was received from the CNSC. Following the successful resolution of the outstanding
comments from the Federal Indigenous Review Team, the Company expects to then be in position to submit a final
version of EIS for consideration at a future hearing of the CNSC.
In October 2023 the Saskatchewan Ministry of Environment confirmed its satisfaction with Denison’s comment
responses and proposed EIS updates. The confirmation would allow Denison to finalize the EIS for the purpose of
obtaining a Provincial Environmental Assessment (‘EA’ ) approval, however this would delink the currently
coordinated Provincial – Federal EA process, which is not expected to provide a meaningful schedule advantage for
the Phoenix project. Denison plans to submit one version of the final EIS to both au thorities once the Federal
information requests have been resolved.
Phoenix ISR Feasibility Field Test Recovered Solution Management phase completed
In November 2023, the Company ann ounced the successful completion of the recovered solution management
phase of the FFT. The FFT was designed to use the existing commercial-sca le ISR test pattern to perform a
combined assessment of the Phoenix deposit’s hydraulic flow properties along with the leaching characteristics that
had been assessed through the metallurgical core-leach testing program. The prior phases of the FFT, completed in
2022, were highlighted by the recovery of 14,400 pounds of U3O8 dissolved in solutions generated during the leaching
and neutralization phases of the test.
The solution recovered during the FFT was stored on site and this final phase of the FFT involved the treatment of
the recovered solution via an on-site purpose-built treatment syst em. Following treatment, a uranium precipitate
product and a treated effluent were produced. The mine ralized precipitates have been recovered from the process
with over 99.99% efficiency. The treat ed effluent was tested to ensure compliance with permit conditions before
being injected into a designated subsurface area.
4
Cost update to the 2018 PFS for Wheeler River Gryphon deposit (‘Gryphon’) confirms the project’s position
amongst the lowest-cost uranium mining projects in the world
During 2023, the Company also completed a cost updat e (‘Gryphon Update’) to the 2018 PFS for conventional
underground mining of the basement-hosted Gryphon d eposit. The scope of the Gryphon Update was targeted at
the review and update of capital and oper ating costs. Mining and processing pl ans remain largely unchanged from
the 2018 PFS aside from minor scheduling and construction sequencing optimizations. The key points include:
Base case pre-tax NPV (8%) of $1.43 billion (100% bas is) is a 148% increase in the base-case pre-tax NPV8% for
Gryphon from the 2018 PFS.
Strong base-case pre-tax IRR of 41.4%.
Base case after-tax NPV 8% of $864.2 million (100% basis) and IRR of 37.6% – with Denison’s effective 95%
interest in the project equating to a base case after-tax NPV8% of $821.0 million.
Base case pre-tax payback period of 20 months, and base ca se after-tax payback period of 22 months – equating
to a reduction of 17 months for the pre-tax payback period from the 2018 PFS.
Importantly, Gryphon remains a highly valuable project that provides Denison with an additional source of low-cost
potential production to deploy significant free cash flows expected from Phoenix.
$113 million raised through equity financings to fund operations and the advancement of Phoenix
In October 2023, Denison completed a bought deal public offering resulting in the issuance of 37,000,000 shares at
a price of $2.03 (US$1.49) per share for total gross proc eeds of $75.1 million (US$55.1 million). Throughout 2023,
Denison also issued 19,786,160 shares under its At-The-Market (‘ATM’) equity program at an average price of $1.91
per share for aggregate gross proceeds of $37.9 million.
Waterbury Lake inaugural ISR field test program completed
In November 2023, the Company announced the completion of an inaugural ISR field test program at the Tthe
Heldeth Túé uranium deposit (‘THT’) on the Waterbury Lake property. The program included (i) the installation of an
eight well ISR test pattern designed to collect an initial database of hydrogeological data, (ii) testing of a permeability
enhancement technique, (iii) the completion of hydrogeologic test work, highlighted by the achievement of hydraulic
conductivity values consistent with those from the 2020 Preliminary Econom ic Assessment (‘PEA’), and (iv) the
execution of an ion tracer test whic h established a 10 hour breakthrough time between the injection and extraction
wells, while also demonstrating hydraulic control of the injected solution. Overall, the program successfully achieved
each of its planned objectives.
Midwest internal concept study completed to examine potential application of ISR mining method
The Company completed an internal conceptual mining study examining the potential application of ISR at the
Company’s 25.17% owned Midwest Project (‘Midwest’). The concept study was prepared by Denison during 2022
and formally issued to the Midwest Joint Venture (‘MWJV’) in early 2023. Based on the positive results of the concept
study, the MWJV provided Denison with approval to complete additional ISR-related work, to be undertaken for
Midwest in 2023 and 2024.
Moon Lake South discovery of high-grade uranium mineralization
In April 2023, Denison reported the discovery of high-grade sandstone hosted uranium mineralization approximately
30 metres above the unconformity in drill hole MS 23-10A, which was completed as part of the 2023 winter exploration
program at the Moon Lake South property. The intersection in MS 23-10A returned 2.46% U 3O8 over 8.0 metres,
including a sub-interval grading 3.71% U3O8 over 4.5 metres. This result represents the best drill hole completed on
the Moon Lake South property to date and is a high priority for follow-up exploration.
$15 million strategic investment in F3 Uranium Corp.
In October 2023, the Company completed a $15 million strategic investment in F3 Uranium Corp. (‘F3’) in the form
of unsecured convertible debentures (the ‘Debentures’), which carry a 9% coupon and will be convertible at Denison’s
option into common shares of F3 at a conversion price of $0.56 per share. F3 has the right to pay up to one third of
the quarterly interest payable by issuing common shares. F3 will also have certain redemption rights on or after the
third anniversary of the date of issuance of the Debentures and/or in the event of an F3 change of control.
Executive team changes undertaken in 2023
In December 2023, Denison announced the promotion of Ms. Elizabeth Sidle to the position of Chief Financial Officer,
in addition to her position as the Company’s Vice President Finance. Ms. Sidle joined Denison in 2016, advancing
5
to the position of Vice President Finance in 2021. Ms. Sidle had been serving as Denison’s Interim Chief Financial
Officer since September 1, 2023, during a temporary medical leav e of absence of the Co mpany’s previous Chief
Financial Officer and since his departure from Denison in late October 2023.
Denison also announced the addition of Mr. Geoff Smith to the position of Vice President Corporate Development &
Commercial. Mr. Smith will be focused on supporting Denison’s investor and customer engagement, the evaluation
and execution of growth opportunities and financing arrangements, and the developm ent and oversight of the
Company’s uranium sales and contracting strategies.
About Denison
Denison Mines Corp. was formed under the laws of Ontario and is a reporting issuer in all Canadian provinces and
territories. Denison’s common shares are listed on the To ronto Stock Exchange (the ‘TSX’) under the symbol ‘DML’
and on the NYSE American exchange under the symbol ‘DNN’.
Denison is a uranium exploration and development company with interests focused in the Athabasca Basin region of
northern Saskatchewan, Canada. The Company has an effective 95% interest in its flagship Wheeler River Uranium
Project, which is the largest undeveloped uranium project in the infrastructure rich eastern portion of the Athabasca
Basin region of northern Saskatchewan. In mid-2023, a Feasibility Study was completed for Wheeler River’s Phoenix
deposit as an ISR mining operation, and an update to the previously prepared PFS was completed for Wheeler River’s
Gryphon deposit as a conventional underground mining oper ation. Based on the respec tive studies, both deposits
have the potential to be competitive with the lowest cost uranium mining operations in the world. Permitting efforts for
the planned Phoenix ISR operation commenced in 2019 and ha ve advanced significantly, with licensing in progress
and a draft Environmental Impact Statement (‘EIS’) submitted for regulator and public review October 2022.
Denison’s interests in Saskatchewan also include a 22.5% ownership interest in the McClean Lake Joint Venture
(‘MLJV’), which includes several uranium deposits and the McClean Lake uranium mill, which is contracted to process
the ore from the Cigar Lake mine under a toll milling agreement, plus a 25.17% interest in the Midwest Main and
Midwest A deposits and a 69.35% interest in the Tthe Heldeth Túé (‘THT,’ formerly J Zone) and Huskie deposits on the
Waterbury Lake property. The Midwest Main, Midwest A, THT and Huskie deposits are located within 20 kilometres of
the McClean Lake mill.
Through its 50% ownership of Japan (Canada) Exploration Com pany, Ltd (‘JCU’), Denison holds additional interests
in various uranium project joint ventures in Canada, in cluding the Millennium project (JCU, 30.099%), the Kiggavik
project (JCU, 33.8118%) and Christie Lake (JCU, 34.4508%).
Denison’s exploration portfolio includes further interests in properties covering approximately 385,000 hectares in the
Athabasca Basin region.
Technical Disclosure and Qualified Person
The technical information contained in this press release has been reviewed and approved by Chad Sorba, P.Geo.,
Denison’s Vice President Technical Services and Project Evaluation, and Andy Yackulic, P.Geo., Denison’s Vice
President Exploration, who are both Qualified Persons in accordance with the requirements of NI 43-101.
Further details of the Phoenix FS and Gryphon Update are provided in Denison’s press release of June 26, 2023. The
results of the Phoenix FS and Grypho n Update are also detailed in a technical report entitled “NI 43-101 Technical
Report on the Wheeler River Project Athabasca Basin, Saskatchewan, Canada,” with an effective date of June 23,
2023 and dated August 8, 2023. The technical report is available on the Company’s website at www.denisonmines.com,
on SEDAR+ (at www.sedarplus.ca) and on EDGAR (at www.sec.gov/edgar.shtml).
For more information, please contact
David Cates (416) 979-1991 ext. 362
President and Chief Executive Officer
Geoff Smith (416) 979-1991 ext. 358
Vice President Corporate Development & Commercial
Follow Denison on Twitter @DenisonMinesCo
Non-GAAP Financial Measures
This release includes certain terms or performance measures commonly used in the mining industry that are not defined
under International Financial Reporting Standards (‘IFRS’). Such non-GAAP performance measures, including NPV,
6
are included because the Company understands that investors use this information to determine the Company’s ability
to generate earnings and cash flows. The Company believes that conventional measures of performance prepared in
accordance with IFRS do not fully illustrate the ability of mines to generate cash flows. Non-GAAP financial measures
should not be considered in isolation as a substitute fo r measures of performance prepared in accordance with IFRS
and are not necessarily indicative of operating costs, operating profit or cash flows presented under IFRS.
Cautionary Statement Regarding Forward‐Looking Statements
Certain information contained in this pre ss release constitutes ‘forward-looking info rmation’, within the meaning of the applic able
United States and Canadian legislation concerning the business, operations and financial performance and condition of Denison.
Generally, these forward-looking statements c an be identified by the use of forward-look ing terminology such as ‘plans’, ‘expects’,
‘budget’, ‘scheduled’, ‘estimates’, ‘forecasts’, ‘intends’, ‘anticipates’, or ‘believes’, or the negatives and/or variations of such words and
phrases, or state that certain actions, events or results ‘may’, ‘could’, ‘would’, ‘might’ or ‘will be taken’, ‘occur’, ‘be achieved’ or ‘has
the potential to’.
In particular, this press release contains forward-looking information pertaining to the following: projections with respect to exploration,
development and expansion plans and objectives, including the results of the FS and the scope, objectives and interpretations of the
technical de-risking process for the proposed ISR operation for the Phoenix deposit, including the FFT, and the interpretation of the
results therefrom; expectations with re spect to future evaluation and development of Phoenix, including engineering design effo rts,
long-lead item procurement; expec tations regarding regulatory applications and approvals and the elements thereof, including th e
EIS; expectations with respect to Company resources and project financing; expectati ons regarding the performance of the uraniu m
market and global sentiment regarding nucl ear energy; expectations rega rding Denison’s joint venture ownership interests; and
expectations regarding the continui ty of its agreements with third parties. Statem ents relating to ‘mineral reserves’ or ‘miner al
resources’ are deemed to be forward-looking information, as they involve the impli ed assessment, based on certain estimates and
assumptions that the mineral reserves and mineral resources described can be profitably produced in the future.
Forward looking statements are based on the opinions and estimates of management as of the date such statements are made, and
they are subject to known and unknown risks, uncertainties and other factors that may c ause the actual results, level of activi ty,
performance or achievements of Denison to be materially different from those expre ssed or implied by such forward-looking
statements. For example, the results and underlying assumptions and interpretations of the FS as well as de-risking efforts suc h as
the ISR field programs discussed herein may not be maintained afte r further testing or be represent ative of actual conditions w ithin
the applicable deposits. In addition, Denison may decide or otherwise be required to extend its evaluation activities and/or discontinue
testing, evaluation and development work if it is unable to maintain or otherwise secu re the necessary approvals or resources ( such
as testing facilities, capital funding, etc.). Denison believes that the expectations reflected in this forward-looking inform ation are
reasonable, but no assurance can be given that these expectations will prove to be accu rate and results may differ materially f rom
those anticipated in this forward-looking information. For a discussion in respect of risks and other factors that could influence forward-
looking events, please refer to the factors discussed in the MD&A dated February 29, 2024 under the heading ‘Risk Factors’. These
factors are not, and should not be, construed as being exhaustive.
Accordingly, readers should not place undue re liance on forward-looking statements. The forward-looking information contained i n
this press release is expressly qualified by this cautionary statement. Any forward-looking information and the assumptions made with
respect thereto speaks only as of the date of this press release. Denison does not undertake any obligation to publicly update or revise
any forward-looking information after the date of this press rel ease to conform such information to actual results or to change s in
Denison's expectations except as otherwise required by applicable legislation.
Cautionary Note to United States Investors Concerning Estimates of Mineral Resources and Mineral Reserves:
This news release may use the terms ‘measured’, ‘indicated’ and ‘inferred’ mineral resources. United States investors are advis ed
that such terms have been prepared in accordance with the defin ition standards on mineral reserves of the Canadian Institute of
Mining, Metallurgy and Petroleum referred to in NI 43-101 and are recognized and required by Canadian regulations. ‘Inferred mineral
resources’ have a great amount of uncertainty as to their existence, and as to t heir economic and legal feasibility. Under Cana dian
rules, estimates of inferred mineral resources may not form the basis of feasibility or other economic studies. United States investors
are cautioned not to assume that all or any part of an inferred mineral resource exists and/or will ever be upgraded to a higher category,
nor assume that all or any part of measured or indicated mineral resources will ever be converted into mineral reserves.
Effective February 2019, the United States Securities and Exchange Commission (‘SEC’) adopted amendments to its disclosure rules
to modernize the mineral property disclosure requirements for issuers whose securities are registered with the SEC under the
Exchange Act and as a result, the SEC now recognizes estimates of ‘measured mineral resources’, ‘indicated mineral resources’ and
‘inferred mineral resources’. In addition, the SEC has amended it s definitions of ‘proven miner al reserves’ and ‘probable mineral
reserves’ to be ‘substantially similar’ to the corresponding definitions under the CIM Standards, as required under NI 43-101. However,
information regarding mineral resources or mineral reserves in Denison's disclosure may not be comparable to similar informatio n
made public by United States companies.