Denison Reports Financial and Operational Results for Q2 2023

Financials

1

Denison Mines Corp. 

1100 – 40 University Ave 

Toronto, ON  M5J 1T1 

www.denisonmines.com 

PRESS RELEASE

Denison Reports Financial and Operational Results for Q2 2023

Toronto, ON – August 10, 2023. Denison Mines Corp. (‘Denison’ or the ‘Company’) (TSX: DML, NYSE American:

DNN) has filed its Condensed Consolidated Financial Statements and Management’s Discussion & Analysis (‘MD&A’)

for the quarter ended June 30, 2023. Both documents ar e or will be available on the Company’s website at

www.denisonmines.com, SEDAR+ (at www.sedarplus.ca) and EDGAR (at www.sec.gov/edgar.shtml). The highlights

provided below are derived from these documents and should be read in conjunction with them. All amounts in this

release are in Canadian dollars unless otherwise stated.

David Cates, President and CEO of Denison commented, “During the second quarter, Denison achieved a further

notable milestone associated with the advancement of our flagship Wheeler River Project (‘Wheeler River’)

with the completion of (i) a highly successful Feasibility Stud y (‘Phoenix FS’) evaluating the use of In-Situ-

Recovery (‘ISR’) mining for the high grade Phoenix uranium deposit (‘Phoenix’), and (ii) a positive cost update

(‘Gryphon Update’) to the Pre-Feasibility Study (‘PFS’) for the underground mine planned for the Gryphon

uranium deposit (‘Gryphon’).

As outlined in the Phoenix FS, Denison has successfully completed several years of technical de-risking,

which has cemented Phoenix’s position as one of the lowest-cost uranium development projects in the world.

Notably, the economics of Phoenix as an ISR mining operation remain exceptionally robust, despite industry-

wide cost inflation, while most contemporary uranium development projects have not yet been tested against

current cost inflation. The recent results of the Phoenix FS and Gryphon Update illustrate Denison’s unique

potential to become a meaningful uranium producer with multiple low-cost development assets.

Global support for the role of nuclear power in the clean energy transition continues to grow and uranium

buyers are increasingly priori tizing geopolitical stability. Denison is well funded, with over $235 million in

working capital and investments at the end of the second quarter, and focused on advancing Phoenix to a final

investment decision in anticipation of building a much-needed new source of Canadian uranium production.”

Highlights

 Feasibility Study for Wheeler River Phoenix deposit yields significant increase in economic results

In June 2023, Denison released the results of the Phoenix FS completed for ISR mining of Phoenix. The Phoenix FS

demonstrates robust economics including:

 Base case pre-tax NPV (8%) of $2.34 billion (100% owner ship-basis) representing a 150% increase in the base

case pre-tax NPV8% for Phoenix from the 2018 Pre-Feasibility Study (‘2018 PFS’).

 Very robust base case pre-tax Inter nal Rate of Return (‘IRR’) of 105.9%.

 Adjusted base case after-tax NPV 8% of $1.56 billion (100% basis) and IR R of 90.0% – with Denison’s effective

95% interest in the project equating to an adjusted base case after-tax NPV8% of $1.48 billion.

 Base case pre-tax and after-tax (adjusted) payback per iod of 10 months – equating to a reduction of 11 months

for the pre-tax payback period from the 2018 PFS.

 Optimized production profile, based on ISR mine planning efforts evaluating production potential for individual

well patterns – resulting in an increase to the planned ra te of production by approximately 43% during the first

five years of operations.

 Estimated pre-production capital costs of under $420 milli on (100% basis), yielding an impressive base case after-

tax (adjusted) NPV to initial capital cost ratio in excess of 3.7 to 1.

 Robust economics that easily absorb cost-inflation and design changes impacting both operating and capital

costs, confirming Phoenix’s position with estimated cash operating and all-in costs expected to be amongst the

lowest-cost uranium mines in the world.

 Phoenix FS plans aligned and costed to meet or exceed environmental criteria expected to be required by the

ongoing regulatory approval process.

 Updated mineral resource estimate, reflecting the resu lts of 70 drill holes completed in support of ISR de-risking

2

and resource delineation activities, which has upgraded 30.9 million pounds U 3O8 into measured mineral

resources, and increased the average grade of the Zone A high-grade domain. This zone is now estimated to

contain 56.3 million pounds U 3O8 in Measured and Indicated mineral re sources at an average grade of 46.0%

U3O8.

 Upgraded 3.4 million pounds U 3O8 into Proven mineral reserves, representing the equivalent of 85% of production

planned during the first calendar year of operations.

 Completion of Phoenix ISR De-Risking and Transition to Engineering Design

The Phoenix FS reflects independent third-party validation of the selection of the ISR mining method for Phoenix and

builds on the findings from a comprehensive and rigorous mult i-year technical de-risking process highlighted by the

highly successful completion of the leaching and neutralization phases of the Phoenix Feasibility Field Test (‘FFT’) in

late 2022. Through the technical de-risking process, Denison has acquired extens ive deposit-specific data and

developed a robust ISR mine planning model that involved eval uation of the production pot ential for individual well

patterns.

With technical de-risking of the project substantially co mplete, front-end engineering design efforts to support the

advancement of the planned Phoenix operation are already significantly progressed and the Company is on track to

transition into detailed design efforts, consistent with the Company's Outlook for 2023, before the end of the year.

 Cost update to the 2018 PFS for Wh eeler River Gryphon deposit confi rms the project remains to be

positioned amongst the lowest-cost uranium mines in the world

The scope of the Gryphon Update was targeted at the review and update of capital and operating costs. Mining and

processing plans remain largely unchanged from t he 2018 PFS aside from minor scheduling and construction

sequencing optimizations. The key points include:

 Base case pre-tax NPV (8%) of $1.43 billion (100% bas is) is a 148% increase in the base case pre-tax NPV8% for

Gryphon from the 2018 PFS.

 Strong base case pre-tax IRR of 41.4%.

 Base case after-tax NPV 8% of $864.2 million (100% basis) and IRR of 37.6% – with Denison’s effective 95%

interest in the project equating to a base case after-tax NPV8% of $821.0 million.

 Base case pre-tax payback period of 20 months, and base case after-tax payback period of 22 months – equating

to a reduction of 17 months for the pre-tax payback period from the 2018 PFS.

Importantly, Gryphon remains a highly val uable project that provides Denison wit h an additional source of low-cost

potential production to deploy significant free cash flows expected from Phoenix.

About Denison

Denison Mines Corp. was formed under the laws of Ontario and is a reporting issuer in all Canadian provinces and

territories. Denison’s common shares are listed on the To ronto Stock Exchange (the ‘TSX’) under the symbol ‘DML’

and on the NYSE American exchange under the symbol ‘DNN’.

Denison is a uranium exploration and development company with interests focused in the Athabasca Basin region of

northern Saskatchewan, Canada. The Company has an effective 95% interest in its flagship Wheeler River Uranium

Project, which is the largest undeveloped uranium project in the infrastructure rich eastern portion of the Athabasca

Basin region of northern Saskatchewan. In mid-2023, a Feasibility Study was completed for Wheeler River’s Phoenix

deposit as an ISR mining operation, and an update to the previously prepared PFS was completed for Wheeler River’s

Gryphon deposit as a conventional underground mining oper ation. Based on the respec tive studies, both deposits

have the potential to be competitive with the lowest cost uranium mining operations in the world. Permitting efforts for

the planned Phoenix ISR operation commenced in 2019 and ha ve advanced significantly, with licensing in progress

and a draft Environmental Impact Statement (‘EIS’) submitted for regulator and public review October 2022.

Denison’s interests in Saskatchewan also include a 22.5% ownership interest in the McClean Lake Joint Venture

(‘MLJV’), which includes several uranium deposits and the McClean Lake uranium mill, which is contracted to process

the ore from the Cigar Lake mine under a toll milling agreement, plus a 25.17% interest in the Midwest Main and

Midwest A deposits and a 67.41% interest in the Tthe Heldeth Túé (‘THT,’ formerly J Zone) and Huskie deposits on the

Waterbury Lake property. The Midwest Main, Midwest A, THT and Huskie deposits are located within 20 kilometres of

the McClean Lake mill.

Through its 50% ownership of Japan (Canada) Exploration Com pany, Ltd (‘JCU’), Denison holds additional interests

in various uranium project joint ventures in Canada, in cluding the Millennium project (JCU, 30.099%), the Kiggavik

project (JCU, 33.8118%) and Christie Lake (JCU, 34.4508%).

3

Denison’s exploration portfolio includes further interests in properties covering approximately 285,000 hectares in the

Athabasca Basin region.

Denison is also engaged in post-closure mine care and maintenance services through its Closed Mines group, which

manages Denison’s reclaimed mine sites in the Elliot Lake region and provides related services to third party projects.

Technical Disclosure and Qualified Person

The technical information contained in this press release has been reviewed and approved by Chad Sorba, P.Geo.,

Denison’s Director, Technical Services, and Andy Yackulic , P.Geo., Denison’s Director, Exploration, who are both

Qualified Persons in accordance with the requirements of NI 43-101.

Further details of the Phoenix FS and Gryphon Update are provided in Denison’s press release of June 26, 2023.

The results of the Phoenix FS and Gryphon Update are also detailed in a technical report entitled “NI 43-101

Technical Report on the Wheeler River Project Athabasca Basin, Saskatchewan, Canada,” with an effective date of

June 23, 2023 and dated August 8, 2023. The technical report is or will be available on the Company’s website at

www.denisonmines.com, on SEDAR+ (at www.sedarplus.ca) and on EDGAR (at www.sec.gov/edgar.shtml).

For more information, please contact

David Cates (416) 979-1991 ext. 362

President and Chief Executive Officer

Mac McDonald (416) 979-1991 ext. 242

Exec. Vice President & Chief Financial Officer

Follow Denison on Twitter @DenisonMinesCo

Non-GAAP Financial Measures

This release includes certain terms or performance measures commonly used in the mining industry that are not defined

under International Financial Reporting Standards (“IFRS”). Such non-GAAP performance measures, including NPV,

are included because the Company understands that investors use this information to determine the Company’s ability

to generate earnings and cash flows. The Company believes that conventional measures of performance prepared in

accordance with IFRS do not fully illustrate the ability of mines to generate cash flows. Non-GAAP financial measures

should not be considered in isolation as a substitute fo r measures of performance prepared in accordance with IFRS

and are not necessarily indicative of operating costs, operating profit or cash flows presented under IFRS. 

Cautionary Statement Regarding Forward-Looking Statements

Certain information contained in this pre ss release constitutes ‘forward-looking info rmation’, within the meaning of the applic able

United States and Canadian legislation concerning the business, operations and financial performance and condition of Denison.

Generally, these forward-looking statements c an be identified by the use of forward-look ing terminology such as ‘plans’, ‘expects’,

‘budget’, ‘scheduled’, ‘estimates’, ‘forecasts’, ‘intends’, ‘anticipates’, or ‘believes’, or the negatives and/or variations of such words and

phrases, or state that certain actions, events or results ‘may’, ‘could’, ‘would’, ‘might’ or ‘will be taken’, ‘occur’, ‘be achieved’ or ‘has

the potential to’.

In particular, this press release contains forward-looking information pertaining to the following: projections with respect to exploration,

development and expansion plans and objectives, including the results of the FS and the scope, objectives and interpretations of the

technical de-risking process for the proposed ISR operation for the Phoenix deposit, including the FFT, and the interpretation of the

results therefrom; expectations with respect to future evaluation and development of Phoenix, including front-end engineering design

and detailed design efforts; expectations regarding regulatory applications and approvals and the elements thereof, including the EIS;

expectations regarding the performance of the uranium market and global sentiment regarding nuclear energy; expectations regarding

Denison’s joint venture ownership interests; and expectations regarding the continuity of its agreements with third parties. Statements

relating to ‘mineral reserves’ or ‘mineral resources’ are deemed to be forward-looking information, as they involve the implied

assessment, based on certain estimates and assumptions that the mineral reserves and mineral resources described can be profitably

produced in the future.

Forward looking statements are based on the opinions and estimates of management as of the date such statements are made, and

they are subject to known and unknown risks, uncertainties and other factors that may c ause the actual results, level of activi ty,

performance or achievements of Denison to be materially different from those expre ssed or implied by such forward-looking

statements. For example, the results and underlying assumptions and interpretations of the FS as well as de-risking efforts suc h as

the ISR field programs discussed herein may not be maintained afte r further testing or be represent ative of actual conditions w ithin

the applicable deposits. In addition, Denison may decide or otherwise be required to extend its evaluation activities and/or discontinue

testing, evaluation and development work if it is unable to maintain or otherwise secu re the necessary approvals or resources ( such

as testing facilities, capital funding, etc.). Denison believes that the expectations reflected in this forward-looking inform ation are

4

reasonable, but no assurance can be given that these expectations will prove to be accu rate and results may differ materially f rom

those anticipated in this forward-looking information. For a discussion in respect of risks and other factors that could influence forward-

looking events, please refer to the factors discussed in the Company’s Annual Information Form dated March 27, 2023 under the

heading ‘Risk Factors’. These factors are not, and should not be, construed as being exhaustive.

Accordingly, readers should not place undue re liance on forward-looking statements. The forward-looking information contained i n

this press release is expressly qualified by this cautionary statement. Any forward-looking information and the assumptions made with

respect thereto speaks only as of the date of this press release. Denison does not undertake any obligation to publicly update or revise

any forward-looking information after the date of this press rel ease to conform such information to actual results or to change s in

Denison's expectations except as otherwise required by applicable legislation.