Denison Announces Completion of

Inaugural ISR Field Test Program at Midwest

Toronto, ON – June 3, 2 024. Denison Mines Corp. (“Denison”) (TSX: DML; NYSE American: DNN) is

pleased to announce it has completed the inaugural In -Situ Recovery (“ISR”) field test program (the

“Program”) at Denison’s 25.17% owned Midwest Ur anium Project (“Midwest”). The Program involved

drilling 10 small diameter boreholes within the Midwest Main deposit primarily undertaken to evaluate site-

specific conditions for ISR mining. A series of tests were successfully performed on each borehole, creating

an extensive database of geological, hydrogeological , geotechnical, and metallurgical data and validating

certain key assumptions in the previously completed internal conceptual mining study (the “Concept Study”)

evaluating the potential use of ISR mining at Midwest (see Press Release dated April 12, 2023).

Denison carried out the Program in collaboration wi th Orano Canada Inc. (“Orano Canada”), as operator

and owner of 74.83% of the Midwest Joint Venture (“MWJV”). Midwest is located approximately 25

kilometres, by existing roads, from the Denison-Orano Canada owned McClean Lake Operation (see

Figure 1), which is currently processing ore for the Cigar Lake mine under a toll milling agreement and has

excess licensed processing capacity. Orano Canada is part of the Orano Group, which is recognized as a

leading international operator in t he field of nuclear materials, with activities including uranium mining,

conversion, enrichment, and other fuel services.

David Cates, Denison’s President and Chief Executive Officer, commented “Denison would like to thank

Orano Canada for its support and encouragement of our joint efforts to evaluate the Midwest Main

deposit for potential future extraction via ISR mining. Orano has significant global expertise in ISR

mining and Denison brings industry leadership in the advancement of ISR mining in the Athabasca

Basin region – allowing the joint venture to assemble a very strong team to carry out and oversee

this inaugural test program.

The Program achieved its planned objectives, and the results provide preliminary validation that

the Midwest Main deposit possesses the characteristics necessary for an ISR operation.

Accordingly, further evaluation is warranted and, building on the Concept Study and incorporating

the data acquired in the test program, we are proceeding with a Preliminary Economic Assessment

(“PEA”) for ISR mining. Midwest represents Deni son’s third project evaluated for potential ISR

mining in the Athabasca Basin.”

Highlights from the Program include the following:

 Confirmed Hydraulic Conductivity: Pump and injection tests validated hydraulic connectivity in

the test wells within the mineralized zone and ac hieved hydraulic conductivity values (a measure

of permeability) consistent with the Concept Study. Sufficient per meability within the mineralized

zone is a key criterion for the successful deployment of the ISR mining method.

 Demonstrated the Effectivenes s of Permeability Enhancement: One method of permeability

enhancement was succ essfully deployed within two wells, demonstrating the suitability of the

method to the Midwest Main deposit. Effici ency of permeability enhancement was verified by

comparison of pre- and post-permeability enhancement hydraulic testing.

 Metallurgical Samples Defined and Co llected for Leaching Characteristics: Core samples

representative of the Midwest deposit were co llected during the Program for use in future

metallurgical tests to determine the leaching characteristics.

2024 ISR Field Test Program

The 2024 ISR field test program was designed to vali date various deposit-specific characteristics of the

Midwest Main deposit, and to collect a database of geotechnical, hydrogeological, and metallurgical data

to further evaluate the ISR mining conditions present at the deposit.

Ten small-diameter test wells were installed within the Midwest Main deposit during the Program – including

a 4-well test pattern (the “Test Pattern”) and 6 individual wells to test specific areas of the deposit for various

characteristics. The Test Pattern included one inject ion well, one extraction well, a recharge well, and a

monitoring well outfitted with a multi-channel vibrating wire piezometer. The six additional wells were drilled

to their target depths and, as applicable, outfitted with well screens and/or pressure monitoring devices to

facilitate hydrogeological testing. All wells were decommi ssioned at conclusion of the Program consistent

with regulatory commitments. See Figures 2 and 3 for an illustration of the well locations within the northeast

portion of the Midwest Main deposit.

Core collected from the test wells within the mineral ized zone is also expected to be used to verify and

update the current mineral resource estimate for the deposit and support future wellfield design and mineral

processing assessments.

Successful Completion of Hydrogeologic Test Work

The Program included the completion of various pump, injection, and packer tests designed to assess the

permeability of the Midwest Main deposit.

The test program measured pressure changes within the mineralized zone, which provides evidence of the

deposit’s hydraulic conditions and is indicative of the potential for the movement of mining solution in an

ISR mining operation. Sufficient permeability within the mineralized zone is a key criterion for the successful

deployment of the ISR mining method.

The results from the hydrogeological testing at Midwes t Main produced hydraulic conductivity values that

are consistent with those assumed in the Concept Study.

Additional supportive test work completed during th e Program included permeability and porosity tests

conducted either downhole or on mineralized drill core recovered during the test program.

Demonstration of the Effectiveness of Permeability Enhancement Method

One method of permeability enhancement was successf ully evaluated on two test wells within the

mineralized zone, with efficacy ve rified by the comparison of pr e- and post-permeability enhancement

hydraulic conductivity tests. Permeability enhancement has been demonstrated to increase and normalize

hydraulic conductivity in the area proximal to the wellbore, allowing for increased contact of injected fluids

within the mineralized zone in order to maximize uranium recoveries in an ISR mining environment.

Collection of Other Supporting Datasets

In addition to the tests described above, data and samples were collected from the drill core recovered from

the test wells to facilitate: (1) t he assessment of matrix permeability, to inform an initial model of the

hydrogeological variations of the deposit; (2) geot echnical evaluations; (3) sediment analysis using

Standard Penetration Test (“SPT”) for measuring mud depths and the overburden below lake bottom; and

(4) testing of compressive and tensile strength for incorporation into future geotechnical assessments.

About Midwest

Midwest is situated in the eastern portion of the Athabasca Basin region in northern Saskatchewan. The

property is approximately one kilometre from the Po ints North Landing airstrip and about 25 kilometres

west, by existing roads, from the McClean Lake Mill, which is jointly owned by Denison (22.5%) and Orano

Canada (77.5%). Access to Midwest is by both road and air. Goods are transported to the site by truck

over an all-weather road connecting with the provincial highway system . Air transportation is provided

through the Points North airstrip (See Figure 1).

Initial exploration work at Midwest began in 1966, and Denison first became an owner of the project in 1987.

In 2007, Orano Canada completed an internal study ev aluating the feasibility of mining the Midwest Main

deposit via open pit mining methods with processing of the resulting ore at the McClean Lake Mill. The

MWJV subsequently advanced the project through the environmental assessment process as an open pit

mine and the final version of the Midwest Pr oject Environmental Impact Statement was

approved in September 2012.

The MWJV is currently evaluating the viability of a number of potential options for the future development

of the Midwest Main deposit, including ISR. Even if a mining method is selected, any future development

by the MWJV will be subject to various review and approval processes, including MWJV approval

processes, provincial and federal regulatory review, and engagement.

About Denison

Denison is a uranium mining, exploration and development company with interests focused in the

Athabasca Basin region of northern Sa skatchewan, Canada. Denison has an effective 95% interest in its

flagship Wheeler River Uranium Project, which is the largest undeveloped uranium project in the

infrastructure rich eastern portion of the Athabasca Basin region of northern Saskatchewan. In mid-2023,

the Phoenix Feasibility Study was completed for the P hoenix deposit as an ISR mining operation, and an

update to the previously prepared 2018 Pre-Feasibility Study was completed for Wheeler River's Gryphon

deposit as a conventional underground mining operation. Based on the respective studies, both deposits

have the potential to be competitive with the lowest cost uranium mining operations in the world. Permitting

efforts for the planned Phoenix ISR operation commenced in 2019 and have advanced significantly, with

licensing in progress and a draft Environmental Impact Study submitted for regulatory and public review in

October 2022.

Denison's interests in Saskatchewan also include a 22.5% ownership interest in the McClean Lake Joint

Venture (“MLJV”), which includes unmined uranium deposits (planned for extraction via the MLJV's SABRE

mining method starting in 2025) and the McClean Lake uranium mill (currently utilizing a portion of its

licensed capacity to process the ore from the Cigar Lake mine under a toll milling agreement), plus a 25.17%

interest in the MWJV’s Midwest Main and Midwest A deposits, and a 69.35% interest in the Tthe Heldeth

Túé (”THT”) and Huskie deposits on the Waterbury Lake Property. The Midwest Main, Midwest A, THT and

Huskie deposits are located within 20 kilometres of the McClean Lake mill. Tak en together, Denison has

direct ownership interests in properties covering ~384,000 hectares in the Athabasca Basin region.

Additionally, through its 50% ownership of JCU (Canada) Exploration Company, Limited (“JCU”), Denison

holds additional interests in various uranium project joint ventures in Canada, including the Millennium

project (JCU, 30.099%), the Kiggavik project (JCU, 33.8118%), and Christie Lake (JCU, 34.4508%).

In 2024, Denison is celebrating its 70th year in uranium mining, exploration, and development, which began

in 1954 with Denison’s first acquisition of mining claims in the Elliot Lake region of northern Ontario.

For more information, please contact

David Cates (416) 979-1991 ext 362

President and Chief Executive Officer

Geoff Smith (416) 979-1991 ext 358

Vice President Corporate Development & Commercial

Follow Denison on X (formerly Twitter) @DenisonMinesCo

Qualified Persons

The disclosure of scientific or technical informat ion contained in this release has been reviewed and

approved, as applicable, by Mr. Chad Sorba, P.Geo., Denison's Vice President, Technical Services &

Project Evaluation or Mr. Andrew Yackulic, P. Geo. , Denison's Vice President, Exploration, who are

Qualified Persons in accordance with the requirements of NI 43-101.

Cautionary Statement Regarding Forward-Looking Statements

Certain information contained in this news release constitutes ‘forward-looking information’, within the meaning of the applicable United

States and Canadian legislation, concerning the business, operations and financial performance and condition of Denison. Generally,

these forward-looking statements can be identif ied by the use of forward-looking termi nology such as ‘potential’, ‘plans’, ‘expects’,

‘budget’, ‘scheduled’, ‘estimates’, ‘forecasts’, ‘intends’, ‘anticipates’, or ‘believes’, or the negatives and/or variations of such words and

phrases, or state that certain actions, events or results ‘may’, ‘could’, ‘would’, ‘might’ or ‘will’ ‘be taken’, ‘occur’ or ‘be achieved’.

In particular, this news release contains forward-looking information pertaining to the following: scope, objectives and interp reted

results of the ISR test program; future plans and objective s for Midwest, including further studies, analysis and a potential f uture

resource estimate update and PEA; and expecta tions regarding its joint venture ownersh ip interests and the continuity of its

agreements with its partners and third parties.

Forward looking statements are based on the opinions and estimates of management as of the date such statements are made, and

they are subject to known and unknown risks, uncertainties and other factors that may c ause the actual results, level of activi ty,

performance or achievements of Denison to be materially different from those expre ssed or implied by such forward-looking

statements. For example, the modelling and assumptions upon whic h the plans for Midwest are based may not be maintained after

further work is completed. In addition, Denison may decide or otherwise be required to discontinue testing, evaluation and other work

if it is unable to maintain or otherwise secure the necessary resources (such as testing facilities, capital funding, joint ven ture

approvals, regulatory approvals, etc.). Deni son believes that the expectations reflect ed in this forward-looking information a re

reasonable but no assurance can be given that these expectations will prove to be accu rate and results may differ materially fr om

those anticipated in this forward-looking information. For a discussion in respect of risks and other factors that could influence forward-

looking events, please refer to the factor s discussed in Denison’s Annual Informati on Form dated March 28, 2024 or subsequent

quarterly financial reports under the heading ‘Risk Factors’. These factors are not, and should not be construed as being, exhaustive.

Accordingly, readers should not place undue re liance on forward-looking statements. The forward-looking information contained i n

this news release is expressly qualified by this cautionary statement. Any forward-looking information and the assumptions made with

respect thereto speaks only as of the date of this news release. Denison does not undertake any obligation to publicly update or revise

any forward-looking information after the date of this news rel ease to conform such information to actual results or to changes in

Denison's expectations except as otherwise required by applicable legislation.

Figure 1: Midwest Site Location Map

Figure 2: Midwest Main Test Pattern and Well Locations - Plan View

Figure 3: Midwest Main Test Pattern and Well Locations – Long Section View