NEWS RELEASE                       May 30, 2018 

TSX: DIAM                     Saskatoon, Saskatchewan 

STAR ‐ ORION SOUTH DIAMOND PROJECT  

TECHNICAL REPORT OF PRELIMINARY ECONOMIC ASSESSMENT FILED ON SEDAR 

Star Diamond Corporation (“Star Diamond” or the “Corporation”), is pleased to announce that the Technical 

Report of the independent Preliminary Economic Assessment (“PEA”) on the Star and Orion South Kimberlites 

(the “Star ‐ Orion South Diamond Project”, or “Project”) (see News Release dated April 16, 2018) has been filed 

on  SEDAR  (www.sedar.com).  The  Technical  Report  will  also  be  filed  on  the  Corporation’s  website 

(www.stardiamondcorp.com).  The  Star  and  Orion  South  Kimberlites  are  situated  in  the  Fort  à  la  Corne 

diamond  district  of  central  Saskatchewan,  Canada,  on  mineral  dispositions  held  100%  by  Star  Diamond.  The 

PEA estimates that 66 million carats of diamonds could be recovered in a surface mine over a 38‐year Project 

life, with a Net Present Value (“NPV”) (7%) of $2.0 billion after tax, an Internal Rate of Return (“IRR”) of 19% 

and an after‐tax payback period of 3.4 years after the commencement of diamond production.  

The  PEA  was  led  by  independent  mining,  processing  and  design  consultants,  with  support  from  the  Star 

Diamond technical team. The principal consultants include: SGS Canada Inc. ‐  Geostat (“SGS”); DRA Americas 

Inc.  (“DRA”),  CSA  Global  Geosciences  Canada  Ltd  (“CSA”)  and  ENGCOMP  Engineering  and  Computing 

Professionals Inc. (“ENGCOMP”). A number of other independent consulting firms and potential vendors also 

provided their study results to Star Diamond for use in developing the PEA.  

The  PEA  was  authored  by  the  following  independent  qualified  people:  W.  Douglas  Roy,  Senior  Associate 

Mining  Engineer  for  SGS,  a  registered  Professional  Engineer  in  the  Province  of  Nova  Scotia;  Daniel  Leroux, 

Global Business  Manager  –  Geological  and  Mining  Services  for  SGS,  a  registered  Professional  Geoscientist  in 

the Provinces of Ontario and Saskatchewan;   Lehman van Niekerk, Senior Process Engineer, DRA Projects SA 

(Pty) Ltd, a registered Professional Engineer with the Engineering Council of South Africa  and member of The 

Southern  African  Institute  of  Mining  and  Metallurgy;   Geoffrey  Wilkie,  Senior  Cost  Consultant  ENGCOMP,  a 

registered  Professional  Engineer  in  the  Province  of  Saskatchewan,  and  Leon  McGarry,  Senior  Resource 

Geologist,  CSA  Global  Geosciences  Canada  Ltd,  a  registered  Professional  Geoscientist  in  the  Province  of 

Ontario and Saskatchewan. 

About Star Diamond Corporation  

Star  Diamond  Corporation  is  a  Canadian  based  corporation  engaged  in  the  acquisition,  exploration  and 

development  of  mineral  properties.  Shares  of  the  Corporation  trade  on  the  TSX  Exchange  under  the  trading 

symbol “DIAM”. The Corporation’s Star ‐ Orion South Diamond Project is located in central Saskatchewan some 

60 kilometres east of the city of Prince Albert. The Project is in close proximity to established infrastructure, 

including paved highways and the electrical power grid, which provide significant advantages for future mine 

development.  

All technical information in this press release has been prepared under the supervision of George Read, Senior 

Vice‐President  of  Exploration  and  Development,  a  registered   Professional  Geoscientist  in  the  Provinces  of 

Saskatchewan and British Columbia; Mark  Shimell, Project  Manager, a registered Professional Geoscientist in 

the  Province  of  Saskatchewan;  and  William  van  Breugel,  Mine  Project  Engineer,  a  registered  Professional 

2 

Engineer in the Province of Saskatchewan, who are the Corporation’s “Qualified Persons” under the definition 

of NI 43‐101. 

Star  Diamond  commissioned  the  PEA  and  related  Technical  Report  for  the  Star  and  Orion  South  Kimberlites 

and, as such, the PEA and Technical Report are the sole responsibility of the Corporation. The PEA is based on 

exploration and evaluation work conducted up to and including March 2017. 

Caution Regarding Forward‐Looking Statements  

This news release contains forward‐looking statements as defined by certain securities laws, including the "safe harbour" 

provisions  of  Canadian  securities  legislation  and  the  United  States  Private  Securities  Litigation  Reform  Act  of  1995. 

Forward‐looking  information  is  often,  but  not  always,  identified  by  the  use  of  words  such  as  "anticipate",  "believe", 

"expect",  "plan",  "intend",  "forecast",  "target",  "project",  "guidance",  "may",  "will",  "should",  "could",  "estimate", 

"predict"  or  similar  words  suggesting  future  outcomes  or  language  suggesting  an  outlook.  In  particular,  statements 

regarding the Corporation's future operations, future exploration and development activities or other development plans 

constitute forward‐looking statements. By their nature, statements referring to mineral reserves, mineral resources, PEA 

or TFFE constitute forward‐looking statements.   

Forward‐looking statements in this press release include, but are not limited to, disclosure regarding the economics and 

project  parameters  presented  in  the  PEA,  including,  without  limitation,  IRR,  NPV  and  other  costs  and  economic 

information,  carats  of diamonds  to  be  recovered,  pre‐tax  payback period,  tonnes  of kimberlite  to be  mined,  carats  per 

tonne to be recovered (grade), diamond prices, life of mine, capital costs, length of pre‐production period and all data in 

Tables  1  through  6,  possible  events,  conditions  or  financial  performance  that  is  based  on  assumptions  about  future 

economic conditions and courses of action; the timing and costs of future development and exploration activities on the 

Corporation's projects; success of development and exploration activities; permitting time lines and requirements; time 

lines  for  further  studies;  planned  exploration  and  development  of  properties  and  the  results  thereof;  and  planned 

expenditures and budgets and the execution thereof as well as statements with respect to the Corporation’s objectives 

for the ensuing year. 

These  forward‐looking  statements  are  based  on  the  Corporation's  current  beliefs  as  well  as  assumptions  made  by  and 

information currently available to it and involve inherent risks and uncertainties, both general and specific. 

Risks exist that forward‐looking statements will not be achieved due to a number of factors including, but not limited to, 

developments in world diamond markets, changes in diamond prices, risks relating to fluctuations in the Canadian dollar 

and other currencies relative to the US dollar, changes in exploration, development or mining plans due to exploration 

results  and  changing  budget  priorities  of  the  Corporation  or  its  partners,  the  effects  of  competition  in  the  markets  in 

which  the  Corporation  operates,  the  impact  of  changes  in  the  laws  and  regulations  regulating  mining  exploration, 

development, closure, judicial or regulatory judgments and legal proceedings, operational and infrastructure risks and the 

additional risks described in the Corporation's most recently filed Annual Information Form, annual and interim MD&A. 

The  Corporation's  anticipation  of  and  success  in  managing  the  foregoing  risks  could  cause  actual  results  to  differ 

materially from what is anticipated in such forward‐looking statements. 

Although  management  considers  the  assumptions  contained  in  forward‐looking  statements  to  be  reasonable  based  on 

information currently available to it, those assumptions may prove to be incorrect. When making decisions with respect 

to  the  Corporation,  investors  and  others  should  not  place  undue  reliance  on  these  statements  and  should  carefully 

consider the foregoing factors and other uncertainties and potential events. Unless required by applicable securities law, 

the Corporation does not undertake to update any forward‐looking statement that is made herein. 

For further information: [email protected] or (306) 664‐2202 

www.stardiamondcorp.com 

‐  END  ‐