Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

DBG.V ·

Doubleview Gold Corp. Announces Positive Preliminary Economic Assessment for the Hat Project; Robust Base-Case Economics with Strategic Scandium Upside NPV:

Economic Studies

Doubleview Gold Corp.

TSX.V: DBG

OTC: DBLVF

FSE: A1W038

470 Granville St. Suite #814

Vancouver, BC, V6C 1V5

T :604.678.9587

F :778.379.3899

E : [email protected]

W:www.doubleview.ca

Doubleview Gold Corp. Announces Positive Preliminary Economic

Assessment for the Hat Project; Robust Base-Case Economics with

Strategic Scandium Upside

NPV:

• After-tax NPV(5%) of C$6.73 billion and IRR of 23% at Consensus Metal

Prices

• After-tax NPV(5%) of C$13.53 billion and IRR of 39% at Spot Metal Prices.

NPV Including scandium and the associated processing circuit:

• After-tax NPV(5%) of C$6.94 billion an IRR of 19% at Consensus Metal

Prices

• After-tax NPV(5%) of C$14.52 billion and IRR of 32% at Spot Metal Prices.

Vancouver, British Columbia, March 02, 2026—Doubleview Gold Corp (TSX-V: DBG / OTCQB: DBLVF

/ GERMANY: 1D4) ("Doubleview" or the “Company”) is pleased to announce the results of its

Preliminary Economic Assessment (PEA) of its 100%-owned polymetallic Hat porphyry project (“Hat”

or “the Project” ), in northwestern British Columbia. With major content of copper, gold, cobalt ,

silver, and scandium, Hat becomes an important source of critical minerals.

Three processing scenarios were evaluated —Scenario A1 (A1) a Cu –Au-Ag-Co flotation base case

using current testwork recoveries1, Scenario A2 (A2), the same base case using expected recoveries1,

and Scenario B (B), a Cu–Au-Ag-Co flowsheet with an added hydrometallurgical circuit and scandium

recovery circuit —with results indicating the Project is financially attractive even without the

scandium component.

Highlights:

• Robust Project Economics: The PEA demonstrates a high -margin operation with an After -

Tax NPV(5%) of C$4.96 billion (A1), C$6.73 billion (A2), or C$6.94 billion (B), and an IRR of

19% (A1), 23% (A2), or 19% (B) at analyst consensus metal prices 2. Using a spot -price

scenario3, the Project delivers a compelling after-tax NPV(5%) of C$11.05 billion (A1), 13.53

billion (A2), or C$14.52 billion (B) and an IRR of 34% (A1), 39% (A2), or 32% (B).

• Sensitivity Highlight: Project economics show the greatest leverage to overall metal prices,

with NPV (5%) ranging from C$3.2 billion to C$10.2 billion (IRR: 14%–32%) at ±20% on all

metals; even under additional +20% CAPEX and +20% OPEX sensitivities, applied on top of

a 25% contingency already embedded in the base case, all scenarios deliver IRRs of 16% or

Doubleview Gold Corp.

TSX.V: DBG

OTC: DBLVF

FSE: A1W038

470 Granville St. Suite #814

Vancouver, BC, V6C 1V5

T :604.678.9587

F :778.379.3899

E : [email protected]

W:www.doubleview.ca

better, and Scenario B provides additional scandium oxide upside with NPV (5%) of C$6.2

billion–C$7.7 billion (IRR: 18%–20%) at ±40% metal price.

• Tier 1 Scale and Longevity: The mine plan supports a multi -decade life of 25 years at a

120,000 tonnes -per-day processing rate, underpinned by a resource base of 609 Mt at

0.43% CuEq4 in the Measured and Indicated categories and 503 Mt at 0.41% CuEq 4 in the

Inferred category.

• High-Output Production Profile B: Envisioned as a conventional large -scale open -pit

operation, the Project is expected to produce an average of over 74 kt of copper, 254 koz

of gold, 376 koz of silver and 2.7 kt of cobalt annually during the first 10 years, with life-of-

mine (LOM) average production of 67.6 kt Cu, 217 koz Au, 348 koz Ag, 2.5 kt Co, and 128

tonnes of scandium oxide per year. (NOTE: projected cobalt to be about 68% of North

America’s cobalt production based on 2024 production)

• Strategic Importance for Critical Minerals: The Project is positioned as a primary North

American source of copper, scandium, and cobalt. With approximately 2.42 billion pounds

of copper, 80 million pounds of cobalt and 2,415 tonnes of scandium oxide contained 5 in

the Measured and Indicated categories, the Project represents an important discovery of

critical minerals.

• Stable, Supportive Jurisdiction: Located in a premier mining district in British Columbia, the

Project benefits from a stable regulatory environment. The Company is committed to

engaging with local First Nations in a respectful manner and to working toward positive and

constructive relationships as the Project advances.

• Catalyst for Development: The PEA serves as the technical foundation for an immediate

transition into a Pre-Feasibility Study (PFS), providing a clear roadmap for early works and

permitting activities in 2026 and 2027.

Farshad Shirvani, President and CEO of Doubleview Gold Corp., commented, “The results of this PEA

confirm the scale, strength and long-term potential of the Hat Project. Delivering a post-tax NPV(5%)

of up to C$6.94 billion and IRR of up to 23% at consensus prices, and even stronger metrics at spot

prices, validates years of disciplined exploration and technical work by our team. Hat is

demonstrating Tier 1 characteristics with a 25-year mine life, strong annual production profile and

meaningful free cash flow generation. Importantly, the Project stands on its own without reliance

on scandium, while still preserving significant upside from critical minerals as markets mature. We

are excited to advance Hat to Pre-Feasibility and continue building a major Canadian critical metals

project.”

Doubleview acknowledges that the Project is located on the traditional territories of the Tahltan

Nation and the Taku River Tlingit First Nation, and recognizes their enduring relationship to and

stewardship of the land and waters. Doubleview is committed to respectful, transparent, and

ongoing engagement with First Nations and local communities whose territories overlap the Project

area and access rou tes, with a focus on protecting water and the environment and advancing

responsible development.

Doubleview Gold Corp.

TSX.V: DBG

OTC: DBLVF

FSE: A1W038

470 Granville St. Suite #814

Vancouver, BC, V6C 1V5

T :604.678.9587

F :778.379.3899

E : [email protected]

W:www.doubleview.ca

PEA OVERVIEW

The PEA contemplates a conventional open-pit mine and processing operation with a 25-year mine

life at a 120,000 t/d (42 Mt/a) plant throughput. Two processing pathways were evaluated, A1 and

its alternative, A2, and B: the first alternative, A, is a Cu–Au–Ag–Co flotation concentrator with two

recovery cases based on current metallurgical testwork , and A2, reflecting expected performance

(Figure 1); and B , a full circuit that retains the base flowsheet and adds a downstream

hydrometallurgical scandium recovery circuit (Figure 2).

The tailings storage facility is a centreline-raised facility built with compacted cycloned sand from

tailings underflow , and engineered drainage for stability, with site -contact waters (including

seepage and pit dewatering) recycled to the process plant and final closure involving pond drainage

and reclamation. The Project is expected to rely on grid power via an extended transmission line.

Tables 1 to 3 summarize the key results of the PEA, including production, operating costs, capital

expenditures, and the principal financial metrics; the sections that follow provide additional detail

on the underlying assumptions, project design, and study outcomes.

Table 1: PEA Study Summary—Production

Metric Unit Scenario A1 Scenario A2 Scenario B

Mining Summary

Strip ratio t:t 1.60

Production Summary LOM

Average Annual Throughput Mt 42

CuEq Head Grade6, 7 % 0.42

Cu Head Grade % 0.19

Au Head Grade g/t 0.19

Ag Head Grade g/t 0.51

Co Head Grade g/t 0.78

Sc Head Grade6 g/t 28.35

Cu Recovery % 80 89 858

Au Recovery % 66 75 898

Ag Recovery % 53 53 688

Co Recovery % 30 30 788

Sc Recovery % N/A 728

Overall Mass of Tailings to Process9 % N/A 12.5

Year of Production Start of Sc2O38 year N/A 4

Average Annual Cu Production kt 63.6 70.8 67.6

Total Cu Production kt 1,590.5 1,769.4 1,689.9

Average Annual Payable Cu kt 61.7 68.7 65.7

Total Payable Cu kt 1,542.8 1,716.3 1,642.2

Average Annual Au Production koz 161.1 183.1 217.3

Total Au Production koz 4,028.2 4,577.5 5,432.0

Doubleview Gold Corp.

TSX.V: DBG

OTC: DBLVF

FSE: A1W038

470 Granville St. Suite #814

Vancouver, BC, V6C 1V5

T :604.678.9587

F :778.379.3899

E : [email protected]

W:www.doubleview.ca

Metric Unit Scenario A1 Scenario A2 Scenario B

Average Annual Payable Au koz 153.1 173.9 207.5

Total Payable Au koz 3,826.8 4,348.7 5,188.6

Average Annual Ag Production koz 271.3 271.3 348.0

Total Ag Production koz 6781.6 6,781.6 8,700.9

Average Annual Payable Ag koz 244.1 244.1 318.6

Total Payable Ag koz 6,103.4 6,103.4 7,965.3

Average Annual Co Production kt 1.0 1.0 2.5

Total Co Production kt 23.9 23.9 62.2

Average Annual Payable Co kt 0.8 0.8 2.3

Total Payable Co kt 19.1 19.1 56.3

Average Annual Sc2O3 Production t N/A 128.4

Total Sc2O3 Production t N/A 3,209.5

Total Sc2O3 Payable t N/A 3,049.0

Table 2: PEA Study Summary—Operating Cost

Metric Unit Scenario A1 Scenario A2 Scenario B

Operating Cost

Average Mine Operating Costs C$/t-moved 2.32

Average Mine Operating Costs C$/t-milled 6.03

Processing Operating Cost10 C$/t-milled 7.93 7.93 10.84

Sc2O3 Processing Cost11 C$/kg Sc2O3 N/A 939.55

General & Administrative C$/t-milled 2.56 2.56 2.56

Total Operating Costs C$/t-milled 16.22 16.22 22.96

Table 3: PEA Study Summary—Capital Expenditure and Financial Metrics

Metric Unit Scenario A1 Scenario A2 Scenario B

Capital Expenditure

Initial Capital Costs C$M 3,552 3,601 3,828

Sustaining Capital Costs C$M 2,755 2,755 4,006

Closure and Reclamation Cost C$M 503

Financial Metrics

Exchange Rate CAD/USD 1.37

Long Term Copper Price US$/lb 4.88

Long Term Gold Price US$/oz 3,272.60

Long Term Silver Price US$/oz 50.22

Long Term Cobalt Price US$/lb 19.57

Long Term Scandium Oxide Price US$/kg N/A 1,500

Average Annual EBITDA C$M 886 1,071 1,242

Total EBITDA C$M 22,162 26,770 31,041

Doubleview Gold Corp.

TSX.V: DBG

OTC: DBLVF

FSE: A1W038

470 Granville St. Suite #814

Vancouver, BC, V6C 1V5

T :604.678.9587

F :778.379.3899

E : [email protected]

W:www.doubleview.ca

Metric Unit Scenario A1 Scenario A2 Scenario B

Average Annual Free Cash Flow (Pre-

tax) C$M 756 940 1,061

Free Cash Flow (Pre-tax)12 C$M 18,904 23,511 26,532

Total Provincial Tax (inc. BC Mineral

Tax) C$M (4,029) (5,090) (5,772)

Total Federal Tax C$M (1,274) (1,859) (2,170)

Total Taxes C$M (5,303) (6,949) (7,942)

Average Annual Free Cash Flow (Post-

tax) C$M 544 662 744

Free Cash Flow (Post-tax)12 C$M 13,601 16,562 18,591

Total Free Cash Flow (Pre-tax)13 C$M 15,352 19,910 22,704

Total Free Cash Flow (Post-tax)12 C$M 10,050 12,961 14,763

NPV 5% (Pre-tax) C$M 7,883 10,576 11,043

NPV 5% (Pre-tax) US$M 5,754 7,720 8,061

IRR (Pre-tax) % 24 29 23

Payback (Pre-tax) years Year 5 Year 4 Year 6

NPV 5% (Post-tax) C$M 4,963 6,727 6,937

NPV 5% (Post-tax) US$M 3,623 4,911 5,064

IRR (Post-tax) % 19 23 19

Payback (Post-tax) Years Year 6 Year 5 Year 7

Table 4 shows the Sensitivity analysis using after-tax NPV(5%) and after-tax IRR.

Table 4: Sensitivity Analysis

Variable

Case

(%) Metal Price

Scenario A1 Scenario A2 Scenario B

NPV (5%)

C$M

IRR

(%)

NPV (5%)

C$M

IRR

(%)

NPV (5%)

C$M

IRR

(%)

Base Case Consensus forecast 4,963 19 6,727 23 6,937 19

Copper Price -20 US$3.90/lb Cu 3,218 15 4,807 19 5,094 15

Copper Price +20 US$5.86/lb Cu 6,688 23 8,632 28 8,764 22

Gold Price -20 US$2,618.08/oz 3,625 16 5,223 19 5,201 16

Gold Price +20 US$3,927.12/oz 6,289 22 8,222 27 8,661 22

Metal Prices -20 All metal prices 1,708 10 3,165 14 2,650 11

Metal Prices +20 All metal prices 8,118 27 10,233 32 11,110 26

Initial CAPEX +20 Variable per Scenario 4,448 16 6,222 19 6,394 16

OPEX +20 Variable per Scenario 3,660 16 5,438 20 5,185 16

Scandium Oxide Price -40 US$900/kg Sc2O3 6,159 18

Scandium Oxide Price +40 US$2,100/kg Sc2O3 7,714 20

MINERAL RESOURCE ESTIMATE

Doubleview Gold Corp.

TSX.V: DBG

OTC: DBLVF

FSE: A1W038

470 Granville St. Suite #814

Vancouver, BC, V6C 1V5

T :604.678.9587

F :778.379.3899

E : [email protected]

W:www.doubleview.ca

Doubleview Gold Corp announced an update of the Mineral Resource estimate (MRE). This estimate

followed the Micon International Ltd. (Micon) Mineral Resource estimate with an effective date of

July 17, 2024 . This MRE incorporates significant new data from the 2024 and 2025 exploration

campaigns, with an effective date of February 4, 2026, and superseded the 2024 Micon estimate.

Table 5: Hat MRE at a 0.2% CuEq Cut‑Off Effective February 4, 2026

Mineral

Resource

Classification

Tonnage

(Mt)

Average Grade Metal Content

CuEq

(%)

Cu

(%)

Au

(g/t)

Co

(g/t)

Ag

(g/t)

CuEq

(Blb)

Cu

(Blb)

Au

(Moz)

Co

(Mlb)

Ag

(Moz)

Measured 272 0.44 0.22 0.18 76.26 0.37 2.61 1.11 1.41 35.6 2.17

Indicated 337 0.43 0.21 0.19 76.81 0.39 3.21 1.31 1.81 44.5 2.88

Total M+I 609 0.43 0.21 0.18 76.57 0.38 5.82 2.42 3.22 80.1 5.05

Inferred 503 0.41 0.18 0.19 76.62 0.38 4.57 1.72 2.77 66.2 4.19

Table 6: Hat MRE at a 0.2% CuEq Cut-Off as of February 4, 2026, Scandium Oxide Resources

Mineral Resource

Classification

Tonnage

(Mt)

Sc Tonnage1

(Mt)

Average Grade

Sc (g/t)

Metal Content

Sc2O3 2 (t)

Measured 272 34 28.79 1,081

Indicated 337 42 28.76 1,334

Total M+I 609 76 28.77 2,415

Inferred 503 63 28.69 1,996

Notes:

1 Scandium tonnages represent 12.5% of the mineralized material by category, reflecting the proportion of tailings

expected to be processed through a dedicated scandium leach circuit under current metallurgical design constraints.

2 Scandium oxide metal content have been calculated using the metallurgical recovery of 72% and conversion factor

from Sc to Sc2O3 of 1.534.

• Mineit’s Qualified Person, Tomasz Wawruch, FAusIMM, completed the MRE, and has reviewed and approved the

technical disclosure related to the MRE contained in this news release. Mr. Wawruch is a senior geology and

mineral resource consultant independent of Doubleview. Mr. Gilles Arseneau, PhD., P.Geo., of ARSENEAU

Consulting Services Inc., provided an independent review of this MRE.

• Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

• The estimate of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation,

socio-political, marketing, or other relevant issues.

• Inferred Mineral Resources are considered too speculative geologically to have economic considerations applied

to them that would enable them to be categorized as Mineral Reserves.

• The Mineral Resource Estimate was prepared in accordance with the Canadian Institute of Mining, Metallurgy

and Petroleum (CIM) Definition Standards for Mineral Resources and Mineral Reserves (2014), and CIM MRMR

Best Practice Guidelines (2019).

• The effective date of the MRE is February 4, 2026.

• Metal contents have been calculated using the following metallurgical recovery factors: Cu = 85%, Au = 89%,

Co = 78%, and Ag = 68%.

• Economic assumptions used include US4.80/lb Cu, US20.00/lb Co, US3,200/oz Au, US46/oz Ag, and a 2% NSR

royalty.

• Mineral Resources are reported within optimized open pit constraints and 0.2% CuEq cut-off grade, based on a

C7.93/t milled processing cost and C2.90/t milled general and administrative cost, with a mining cost of C3.01/t

plus incremental mining cost increasing by C0.015/t for every bench below the reference level of 1,125 mRL.

Doubleview Gold Corp.

TSX.V: DBG

OTC: DBLVF

FSE: A1W038

470 Granville St. Suite #814

Vancouver, BC, V6C 1V5

T :604.678.9587

F :778.379.3899

E : [email protected]

W:www.doubleview.ca

• CuEq calculations do not include scandium. The formula used to calculate CuEq is:

CuEq = [(((Ag × 46.0 × 0.68)/31.1035) + ((Au × 3200 × 0.89)/31.1035) + 0.0001 × (Co × 20.0 × 0.78 × 22.0462) + 0.0

001 × (Cu × 4.8 × 22.0462 × 0.85))/(4.8 × 22.0462 × 0.85)], where all input variables are expressed in (ppm) and

CuEq is expressed in percent (%).

• Rounding may result in minor variations between individual values and totals; such differences are not considered

material to the MRE.

• Mineral Resource classification reflects the level of geological confidence and satisfies the uncertainty criteria

appropriate for exploration and resource development. Additional drilling will be required to reduce uncertainty

to the level expected for production planning.

• The MRE reflects the geological interpretation, drill-hole spacing, and estimation parameters available at the time

of modelling. Any additional drilling is expected to influence the current outcome by improving confidence in the

estimates and refining the geometry of the mineralized domains.

• The Mineral Resource results are presented in situ within the optimized pit. Mineralized material outside the pit

has not been considered as a part of the current MRE tabulation. Calculations used metric units (metres, tonnes,

g/t).

• A total of 97 diamond drill holes, comprising 49,548 m of core, were incorporated into the Mineral Resource

Estimate. All drilling data used in the MRE were subject to standard QA/QC validation prior to inclusion.

PROCESSING SCENARIOS

The PEA evaluates two processing scenarios: (A) a conventional Cu –Au–Ag–Co flotation

concentrator at 120,000 t/d (42 Mt/a) with two recovery cases—A1 based on metallurgical testwork

completed by Sepro Laboratories (Langley, BC) and A2 reflecting target/exp ected performance—

and (B) a full circuit that retains the base flowsheet and adds a downstream hydrometallurgical

scandium recovery circuit.

The concentrator consists of crushing, grinding, flotation, concentrate handling, and tailings

management, producing both a saleable approximately 25% Cu concentrate with co -product gold

and by-product silver-cobalt credits and a pyrite concentrate enriche d in cobalt; in the full -circuit

case, the pyrite concentrate is roasted to generate sulphuric acid and a calcine that is then processed

to recover cobalt, gold, silver, and copper; after stripping it will be precipitated as a sulphide to be

admixed to the copper concentrate to improve grade, with the acid used to leach flotation tailings

for scandium recovery, noting that the scandium circuit is a newer chemical process compared with

the otherwise industry-standard flowsheet.

Under A1 or A2 (Figure 1), the flowsheet produces a single saleable product—a copper concentrate

with payable gold credits; the pyrite concentrate is not treated or marketed in this case and is only

processed in B where the hydrometallurgical circuit enables recovery of cobalt (and additional Au–

Ag) and supports the scandium circuit (Figure 2), which is planned to be constructed in a phased

approach commencing in Year 3 of operations.

Doubleview Gold Corp.

TSX.V: DBG

OTC: DBLVF

FSE: A1W038

470 Granville St. Suite #814

Vancouver, BC, V6C 1V5

T :604.678.9587

F :778.379.3899

E : [email protected]

W:www.doubleview.ca

Figure 1: Grinding and Flotation Flowsheet; Scenarios A1/A2 Report Copper Concentrate Only, while the

Cobalt–Pyrite Flotation Stream Shown Is Included Only in Scenario B

Scenario B only