Toronto, Ontario--(Newsfile Corp. - February 25, 2025) -

Compass Gold Corp. (TSXV: CVB)

(Compass

or

the Company)

is pleased to provide an update on its plans to produce gold at the

Massala prospect located along the 15 km Tarabala Trend, which is contained within the Company's

Sikasso Property in southern Mali.

Highlights

Environmental and social impact studies are expected to be completed within the next 30

days. All other requirements for the granting of Small Mining Permit are complete.

Compass team is assisting with the optimization of the existing SMAT mining facility,

where ore processing and gold recovery will occur under a Co-Production Agreement

Subject to receiving the Small Mine Permit, commercial production is on track to

commence by early Q2

Issuance of a Small Mining Permit will allow for total production of up to 160,000 ounces

of gold over an initial four-year term

Compass CEO Larry Phillips,

said, "Our Compass team has nearly completed the required work for

our application for a Small Mining Permit at the Massala prospect, with the remaining environmental and

social impact studies to be finalized within the next few weeks.. The co-production agreement with the

nearby SMAT processing facility puts Compass in the unique position of being ready to commence

production within days of receiving a Small Mining Permit.

Subject to the timely issuance of our permit,

we remain confident that we're on track to initiate production within the next two months.

He added,

"We are keen to commence production at Massala in this current environment of record gold

prices approaching US$3,000 per ounce. Our objective at this first small mine operation at Massala is to

demonstrate that careful, cost-effective, near-surface mining can bring immediate economic benefit to

Mali as well as our surrounding community and our Compass shareholders. Most importantly, the

Compass team, with decades of successful operating experience in Mali, is fully committed to gold

production that is transparent and compliant with the applicable regulations and proper international

standards of safety and accountability."

Ready to Go

As previously reported (

See Compass news release dated January 6, 2025

), documentation of a

number of studies is required by the Malian Mining Ministry ("the Ministry") as key components of the

Company's Small Mine Permitting application. The most important of these studies, the project viability

study* and mine closure plan, have been completed. An environmental and social impact study, including

a community development plan, are now being completed. Meanwhile, community engagement

negotiations are also ongoing to ensure cordial relations are maintained in the project area and the

surrounding communities.

The SMAT facility, located 2 km from the Massala mine site, is adjacent to Compass's proposed

Massala-Tarabala mining permit. Compass's technical team continues working with SMAT and an

independent engineering group to complete a modification of the existing mining facility in order to start

improved processing of

SMAT gold ore. The plant will also process bulk sampling of our Massala ore in

the coming weeks. This sampling, together with the initial processing of SMAT ore, will provide crucial

information about gold recovery and the optimal calibration of the crushing, processing and recovery

facilities. The objective of the Company's co-production agreement with its Malian partner, SMAT, is to

design a mining operation with the capacity to process up to 100 tonnes per hour. This total targeted

annual gold production and ore processing will fall within the provisions of the Malian Mining Code for

Small Mines, as proclaimed in July of last year

(

See Compass news release dated August 19, 2024

)

.

This code allows for mining a maximum of 200,000 tonnes per year and the production of 160,000

ounces of gold over a four-year period.

(*The project viability study required by the Malian authorities is not a CIM-defined Feasibility Study

outlined in NI 43-101, since no NI 43-101 class resource estimation or metallurgy study are required.)

About Compass Gold Corp.

Compass, a public company having been incorporated into Ontario, is a Tier 2 issuer on the TSX-V.

Through the 2017 acquisition of MGE and Malian subsidiaries, Compass holds gold exploration permits

located in Mali that comprise the Sikasso Property. The exploration permits are located in three sites in

southern Mali with a combined land holding of 1,173 sq. km. The Sikasso Property is located in the

same region as several multi-million-ounce gold projects, including Morila, Syama, Kalana and Komana.

The Company's Mali-based technical team, led in the field by Dr. Madani Diallo and under the

supervision of Dr. Sandy Archibald, P.Geo, is conducting the current exploration program. They are

examining numerous anomalies first noted in Dr. Archibald's August 2017 "National Instrument 43-101

Technical Report on the Sikasso Property, Southern Mali."

Qualified Person

This news release has been reviewed and approved by EurGeol. Dr. Sandy Archibald, P.Geo,

Compass's Technical Director, the Qualified Person for the technical information in this news release

under National Instrument 43-101 standards.

Forward-Looking Information

This news release contains "forward-looking information" within the meaning of applicable securities

laws, including statements regarding the Company's planned exploration work and management

appointments. Readers are cautioned not to place undue reliance on forward-looking information.

Actual results and developments may differ materially from those contemplated by such information.

The statements in this news release are made as of the date hereof. The Company undertakes no

obligation to update forward-looking information except as required by applicable law.

For further information, please contact:

Compass Gold Corporation

Compass Gold Corporation

Larry Phillips - Pres. & CEO

Greg Taylor - Dir. Investor Relations & Corporate Communications

[email protected]

[email protected]

T: +1 416-596-0996 X 302

T: +1 416-596-0996 X 301

Website:

www.compassgoldcorp.com

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS

THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS

RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.

To view the source version of this press release, please visit

https://www.newsfilecorp.com/release/242162