Capstone Copper Announces First Saleable Copper Concentrate at MVDP in Chile

Corporate Updates

1

June 25, 2024

Capstone Copper Announces First Saleable Copper

Concentrate at MVDP in Chile

Vancouver, British Columbia – Capstone Copper Corp. (“Capstone” or the “Company”) (TSX:CS)

(ASX:CSC) is pleased to announce that first saleable copper concentrate was produced at its Mantoverde

Development Project (“MVDP”) in Chile, as the mine advances commissioning and ramps up to full production

levels.

The unchanged key commissioning milestones at the MVDP include:

• First ore to the primary crusher – completed in Q4 2023

• First ore to the grinding circuit – completed in Q1 2024

• First saleable concentrate – completed in Q2 2024

• Achievement of nameplate operating rates – expected during Q3 2024

“First saleable copper concentrate production at MVDP is a significant milestone for Capstone. This

achievement is a testament to our dedicated and skilled teams , who continue to work towards a safe and

efficient ramp-up to nameplate operating rates . MVDP remains on track and on budget with our guidance

previously disclosed,” John MacKenzie, Capstone’s Chief Executive Officer, commented. “In July, we plan to

release an updated feasibility study for our Santo Domingo project , followed by a feasibility study for our

Mantoverde Optimized project later in the quarter , which will define the next phases of our value -accretive

production growth in the district.”

For a virtual tour of the Mantoverde Development Project please visit: https://vrify.com/decks/12698-

mantoverde-development-project

About MVDP

MVDP is expected to enable the mine to process 236 million tonnes of copper sulphide reserves (which

represent approximately 20% of total sulphide resources) over a 20- year expected mine life, in addition to

existing oxide reserves. The MVDP involves the addition of a sulphide concentrator (nominal 32,000 ore

tonnes per day) and tailings storage facility, and the expansion of the existing desalination plant and other

minor infrastructure.

About Capstone Copper Corp.

Capstone Copper Corp. is an Americas -focused copper mining company headquartered in Vancouver,

Canada. We own and operate the Pinto Valley copper mine located in Arizona, USA, the Cozamin copper -

silver mine located in Zacatecas, Mexico, the Mantos Blancos copper-silver mine located in the Antofagasta

region, Chile, and 70% of the Mantoverde copper-gold mine, located in the Atacama region, Chile. In addition,

we own the fully permitted Santo Domingo copper -iron-gold project, located approximately 30 kilometr es

northeast of Mantoverde in the Atacama region, Chile, as well as a portfolio of exploration properties in the

Americas.

Capstone Copper’s strategy is to unlock transformational copper production growth while executing on cost

and operational improvements through innovation, optimization and safe and responsible production

throughout our portfolio of assets. We focus on profitability and disciplined capital allocation to surface

stakeholder value. We are committed to creating a positive impact in the lives of our people and local

communities, while delivering compelling returns to investors by responsibly producing copper to meet the

world’s growing needs.

NEWS RELEASE

TSX:CS ● ASX:CSC ● capstonecopper.com

2

Further information is available at www.capstonecopper.com

Cautionary Note Regarding Forward-Looking Statements

This document may contain “forward-looking information” within the meaning of Canadian securities legislation

and “forward-looking statements” within the meaning of the United States Private Securities Litigation Reform

Act of 1995 (collectively, “forward-looking statements”). These forward-looking statements are made as of the

date of this document and the Company does not intend, and does not assume any obligation, to update these

forward-looking statements, except as required under applicable securities legislation.

Forward-looking statements relate to future events or future performance and reflect our expectations or

beliefs regarding future events. In certain cases, forward- looking statements can be identified by the use of

words such as “anticipate”, “approximately”, “believe”, “budget”, “ will”, “project”, “contemplate”, “estimate”,

“expected”, “forecas t”, “guidance”, “intend”, “plan”, “scheduled”, “target”, or variations of such words and

phrases, or statements that certain actions, events or results “be achieved” , “could”, “may”, “might”, “occur”,

“should”, “will be taken” or “would” or the negative of these terms or comparable terminology.

Forward-looking statements include, but are not limited to, statements with respect to the estimation of Mineral

Resources and Mineral Reserves, the timing of anticipated achievement of nameplate capacity and continued

levels of saleable copper and cost of the Mantoverde Development Project (“MVDP”), including but not limited

to the timing of achieving milestones and saleable concentrate, the amount of estimated future production,

the costs of production and capital expenditures and reclamation, the realization of Mineral Reserve estimates,

and the success of our mining operations.

By their very nature, forward- looking statements involve known and unknown risks, uncertainties and other

factors that may cause our actual results, performance or achievements to be materially different from any

future results, performance or achievements expressed or implied by the forward-looking statements. Such

factors include, amongst others, risks related to inherent hazards associated with mining operations,

permitting risks including but not limited to loss of permits or restrictions on permits, future prices of copper

and other metals, inflation, counterparty risks associated with sales of our metals, changes in general

economic conditions, availability and quality of water, accuracy of Mineral Resource and Mineral Reserve

estimates, operating in foreign jurisdictions with risk of changes to governmental regulation, compliance with

governmental regulations and stock exchange rules, reliance on approvals, licences and permits from

governmental authorities and stock exchanges and potential legal challenges to permit applications, impact

of climate change and changes to climatic conditions at our operations and projects, risks relating to

widespread epidemics or pandemic outbreaks, geopolitical events and the effects of global supply chain

disruptions, uncertainties and risks related to the potential development of the Santo Domingo project, risks

related to the MVDP , challenges to title to our mineral properties, environmental risks, maintaining ongoing

social licence to operate, dependence on key management personnel, TSX and ASX listing compliance

requirements and other risks of the mining industry as well as those factors detailed from time to time in the

Company’s and the risks included in our continuous disclosure filings on SEDAR+ at www.sedarplus.ca.

Although the Company has attempted to identify important factors that could cause our actual results,

performance or achievements to differ materially from those described in our forward- looking statements,

there may be other factors that cause our results, performance or achievements not to be as anticipated,

estimated or intended. There can be no assurance that our forward- looking statements will prove to be

accurate, as our actual results, performance or achievements could differ materially from those anticipated in

such statements. Accordingly, readers should not place undue reliance on our forward-looking statements.

Contact Information

Jerrold Annett, SVP, Strategy & Capital Markets

3

647-273-7351

[email protected]

Daniel Sampieri, Director, Investor Relations & Strategic Analysis

437-788-1767

[email protected]