Canadian North Resources Announces Updated Mineral Resources for its 100% owned Ferguson Lake Project in Canada; High-grade Open Pit Indicated Mineral Resources of 22.4 million tonnes at 0.84% copper, 0.60% nickel, 0.07% cobalt, 1.37g/t palladium and 0.23g/t platinum

Drill Results Resource Estimates

Canadian North Resources Announces Updated Mineral Resources for its 100% owned Ferguson Lake

Project in Canada;

High-grade Open Pit Indicated Mineral Resources of 22.4 million tonnes at 0.84% copper, 0.60% nickel,

0.07% cobalt, 1.37g/t palladium and 0.23g/t platinum

Toronto, June 13 , 2022 – Canadian North Resources Inc. (“Canadian North” or the “Company”) (TSXV:

CNRI) is pleased to announce an updated Mineral Resource estimate for its 100% owned Ferguson Lake

base metal ( nickel, copper, cobalt ) and platinum group metal (“PGM”, mainly palladium and platinum)

project in Nunavut, Canada.

Highlights:

• Indicated Mineral Resources containing 455 million pounds (Mlb) copper at 0.85% , 32 1Mlb

nickel at 0.60%, 37.5Mlb cobalt at 0.07%, 1.08 million ounces (Moz) palladium at 1.38gpt and

0.18Moz platinum at 0.23gpt;

• Inferred Mineral Resources containing 947Mlb copper at 0.91% , 5 51.5Mlb nickel at 0.53% ,

62.4Mlb cobalt at 0.06%, 2.12Moz palladium at 1.4gpt and 0.38Moz platinum at 0.25gpt;

• Significant potential for resource expansion along strike and at depth over the 15 km long

mineralized belt.

” We are very pleased to announce our updated resource estimation showing substantial high-grade open

pit and underground resources,” said Dr. Kaihui Yang, President and CEO of Canadian North. “We also see

significant potential for resource expansion along strike and at depth over the 15 kilometers long

mineralized belt. Management believes the geology and mineralization of the Ferguson Lake Project may

be comparable with the Norilsk mining area of Russia, one of the world ’s most productive regions for

nickel, copper, palladium and platinum. The Company is carrying out its $11 million exploration program

for 2022 to further expand the potential high -grade large -tonnage economic base metal and PGM

resource.”

“This Mineral Resource estimation incorporates mostly the West Zone, which represents approximately

6km of the presently known 15-kilometer-long mineralized belt. In addition, rhodium and gold are not

included in the resource modeling due to no systematic assaying results , although there are significant

values in several mineralized zones . We are drilling to further define the potential large -tonnage base

metal and PGM resources along the main mineralized zones and expect to incorporate both the West and

East Zones in to an updated resource estimation next year .“ said Dr. Trevor Boyd, Vice Presi dent for

Exploration.

The following Mineral Resource (Table 1) has been estimated for the Ferguson Lake Project, based on a

database that contains 611 historic holes and a total of 186,416 metres of drilling and 36,740 assay

samples.

Table 1: Ferguson Lake Project Mineral Resources

Indicated Mineral Resources

Mining Method Tonnes Copper Nickel Cobalt Palladium Platinum

Grades

(Mt) (%) (%) (%) (gpt) (gpt)

Open Pit 22.40 0.84 0.60 0.07 1.37 0.23

Underground 1.90 1.03 0.60 0.07 1.49 0.32

Total 24.30 0.85 0.60 0.07 1.38 0.23

Contained Metals

(Million Pounds) (Million ounces)

Open Pit

414.82 296.30 34.57 0.99 0.17

Underground

43.14 25.13 2.93 0.09 0.02

Total

455.36 321.43 37.50 1.08 0.18

Inferred Mineral Resources

Method Tonnes Copper Nickel Cobalt Palladium Platinum

Grades

(Mt) (%) (%) (%) (gpt) (gpt)

Open Pit 12.10 0.59 0.40 0.04 0.99 0.22

Underground 35.10 1.02 0.57 0.07 1.54 0.26

Total 47.20 0.91 0.53 0.06 1.40 0.25

Contained Metals

(Million Pounds) (Million ounces)

Open Pit

157.39 106.70 10.67 0.39 0.09

Underground

789.29 441.07 54.17 1.74 0.29

Total

946.92 551.50 62.43 2.12 0.38

Notes:

1. CIM definitions (2014) were followed for Mineral Resources.

2. Mineral Resources were estimated at NSR cutoff values of US$ 49.70 for open pit and US$9 4.50

for underground.

3. NSR values were calculated using long-term metal prices of US$8.00/lb for Nickel, $US3.30/lb for

Copper, US$20.60/lb of Cobalt, US$900/oz Platinum, and US$1,800/oz Palladium.

4. Metallurgical recoveries used in the NSR calculation were 91% for Nickel. 94% for Copper, 90%

for Cobalt, 50% for Platinum and 81% for Palladium.

5. Open pit Mineral Resources are reported at a base case NSR value of US$49.70 within a conceptual

pit.

6. Underground Mineral Resources were estimated using a minimum true width of 2.5 metres and

US$94.50 NSR value.

7. The independent Qualified Persons for the current Mineral Resource estimate is Mr. Jamie

Lavigne, P. Geo. (Francis Minerals Ltd).

8. The Mineral Resource block model was peer -reviewed by Allan Armitage, PhD, P.Geo of SGS

Geological Services Ltd.. Dr. Armitage is a Qualified Person as defined in NI-43-101 Standards.

9. Mineral Resources which are not Mineral Reserves do not have demonstrated economic viability.

10. All figures are rounded to reflect the relative accuracy of the estimate. Numbers may not add due

to rounding.

The Ferguson Lake Project was originally discovered by Inco Limited in 19 50s and has had over $150

million spent with over 180,000 meters drilled and a Preliminary Economic Assessment (PEA) completed

by Starfield Resources in 2011. Canadian North Resources Inc. acquired the Fergusson Lake project in

2013. During the past 9 years, the Company has focused on surface sampling and geological mapping,

ground geophysical surveys , confirmation assaying, assaying of historic holes drilled previously not

assayed, compilation of hundreds of historic reports, metallurgical work to extract the PG M and base

metals economically, completion of NI43-101 Technical Report as well as camp and equipment updates.

The Company has returned to the exploration phase to increase the tonnage of high-grade zones and

expand the entire resource over the 15-km-long major mineralized belts and other targets.

NI 43-101 Technical Report:

A technical report on the resource estimates , which is being prepared in accordance with National

Instrument 43 -101 ("NI 43 -101"), will be available on SEDAR (www.sedar.com) under the Company's

issuer profile within 45 days. The effective date of the current mineral resource estimate is June 13, 2022.

Qualified Person:

The technical contents of this news release have been reviewed by Dr. Trevor Boyd, P.Geo., a qualified

person as defined by Canadian National Instrument 43-101 standards.

About Canadian North Resources Inc.:

Canadian North Resources Inc. is an exploration and development company focusing on the metals for

the clean-energy, electric vehicles, battery and high -tech industries. The company is advancing its 100%

owned Ferguson Lake nickel, copper, cobalt, palladium, and platinum project in Nunavut, Canada.

Further information please visit the website at www.cnresources.com or contact:

Dr. Kaihui Yang, President and CEO

Phone: 905-696-8288 (Canada) 1-888-688-8809 (Toll-Free)

Email: [email protected]

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies

of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Cautionary Note Regarding Forward-Looking Statements

Certain statements contained in this news release, including statements which may contain words such

as “expects”, “anticipates”, “intends ”, “plans”, “believes”, “estimates”, or similar expressions, and

statements related to matters which are not historical facts, are forward -looking information within the

meaning of applicable securities laws. Such forward -looking statements, which reflect management’s

expectations regarding the Company’s future growth, results of operations, performance, business

prospects and opportunities, are based on certain factors and assumptions and involve known and

unknown risks and uncertainties which may cause the actual results, performance, or achievements to be

materially different from future results, performance, or achievements expressed or implied by such

forward-looking statements.

These factors should be considered carefully, and readers should not place undue reliance on the

Company’s forward -looking statements. The Company believes that the expectations reflected in the

forward-looking statements contained in this news release and the documents incorporated by reference

herein are reasonable, but no assurance can be given that these expectations will prove to be correct. In

addition, although the Company has attempted to identify important factors that could cause actual

actions, events or results to differ materially from those described in forward look ing statements, there

may be other factors that cause actions, events or results not to be as anticipated, estimated or intended.

The Company undertakes no obligation to release publicly any future revisions to forward -looking

statements to reflect events or circumstances after the date of this news or to reflect the occurrence of