Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

CKG.V ·

Chesapeake Announces Strong PEA Results for Phase 1 Heap Leach Mine at Metates with Pre-Tax NPV of US$1.1 Billion (C$1.4 Billion) and 35% IRR

Economic Studies Metallurgy & Processing

Chesapeake Announces Strong PEA Results

for Phase 1 Heap Leach Mine at Metates with

Pre-Tax NPV of US$1.1 Billion (C$1.4 Billion)

and 35% IRR

Vancouver, British Columbia--(Newsfile Corp. - July 26, 2021) - Chesapeake Gold Corp. (TSXV: CKG)

(OTCQX: CHPGF) ("

Chesapeake

" or the "

Company

") is pleased to report the positive results of the

Preliminary Economic Assessment ("

PEA

") for the Phase 1 mine plan ("

Phase 1

") of the Metates gold-

silver project in Durango, Mexico. Phase 1 evaluates the initial development of Metates as a low cost,

scalable heap-leach operation. The PEA demonstrates robust project economics with optionality for

expansion into a significantly larger operation. The PEA was prepared by M3 Engineering & Technology

of Tucson, Arizona ("

M3

") with input from other prominent industry consultants.

HIGHLIGHTS OF PHASE 1 PEA:

(All financial figures are in U.S. dollars unless otherwise noted)

Compelling Project Economics:

Pre-tax NPV of C$1.43 billion (US$1.14 billion) and 35% IRR

at $1,600 per ounce gold and $22 per ounce silver at a 5% discount rate, over a 31-year mine life

("

LOM

").

Production Metrics:

Average annual production of over 110,000 ounces of gold and 2.5 million

ounces of silver during the first 15 years. All-in sustaining cost ("

AISC

") of $748 per gold ounce

with a LOM low stripping ratio of 2.2:1.

Significant Cash Flow:

Average annual pre-tax free cash flow of $113 million in the first 15

years, and cumulatively $2.7 billion LOM.

Initial Capital Cost and Payback:

The PEA contemplates an initial capital cost of $359 million,

including $64 million in contingency costs. Payback 2.5 years.

Scalable Operation:

Phase 1 15,000 tpd mine is expandable to 30,000 tpd, to bring production

forward and reduce the 31-year LOM.

Resource Optionality:

The PEA only focuses on the higher-grade intrusive hosted portion of the

Metates orebody, which represents less than 20% of the total mineral resource.

Highlights Sulphide Heap-Leach Technology Potential:

Management believes there is a

strategic opportunity for Chesapeake across the precious metals industry to enhance the project

economics of sulphide orebodies globally.

The PEA demonstrates strong financial performance and rapid capital payback developing Metates as

a sulphide heap leach operation. The site's simplified process flowsheet, compact footprint and

proximity to key infrastructure contribute to the project's low initial capital cost. The PEA forecasts early

cash flow generation which supports future expansions that can be developed by the Company. Excellent

upside optionality exists to scale up future production to potentially take advantage of the entire

resource.

Alan Pangbourne, CEO said, "The Metates PEA is a key milestone towards Chesapeake's larger

vision of becoming a mid tier gold and silver producer. I'd like to thank our technical team for the

progress to date. We look forward to providing additional updates as we continue to de-risk and

develop Metates."

Randy Reifel, Chairman continued, "This PEA demonstrates Metates as large, scalable Tier 1 project

with excellent economics.

I believe the revised approach to Metates is a potential "game changer" for

Metates and the gold mining industry at large. Alan has the track record to build Chesapeake into an

innovative, successful gold producer in the coming decade."

An updated presentation including the highlights of the Phase 1 PEA has been uploaded to the

Chesapeake website:

https://chesapeakegold.com/wp-content/uploads/2021/07/2021.07.26-Metates-

PEA-Presentation.pdf

.

METATES GOLD-SILVER PROJECT

The Metates project located in Durango State, Mexico, is one of the largest, undeveloped disseminated

gold and silver deposits in Mexico.

The property comprises 12 mineral concessions totalling 14,727

hectares.

The Metates deposit is hosted by Mesozoic sedimentary rocks that have been intruded by a

quartz latite body up to 300 metres thick and 1,500 metres long.

The gold-silver mineralization occurs as

sulphide veinlets and disseminations in both the intrusive and sedimentary host rocks.

Mineral Resource Estimate

The PEA includes a revised mineral resource estimate for the Metates Project and replaces the mineral

reserve estimate contained in the Company's updated preliminary feasibility study dated April 29, 2016

("

2016 PFS

").

The measured and indicated mineral resource is 1.3 billion tonnes at 0.47 g/t gold and

12.9 g/t silver for 19.8 million ounces of contained gold and 542.0 million ounces of contained silver.

Inferred mineral resource is an additional 62.2 million tonnes at 0.32 g/t gold and 9.0 g/t silver for

640,000 ounces contained gold and 18.0 million ounces of contained silver.

Table 1 below shows the

new resource statement for the Metates project.

The mineral resource is broadly divided into intrusive hosted and sediment hosted mineralization. In

terms of measured and indicated mineral resource tonnes, about 80% of the resources are sediment

hosted and 20% intrusive hosted.

The mineral resources are based on a block model developed by

Independent Mining Consultants ("

IMC

") during July 2014.

The results of the recent metallurgical core

drilling program reported in the news release dated June 28, 2021, have not been included in this block

model.

The measured, indicated, and inferred mineral resources reported are contained within a floating cone

pit shell, and are compliant with the "reasonable prospects for economic extraction" requirements of

National Instrument 43-101 Standards of Disclosure for Mineral Projects ("

NI 43-101

").

The mineral

resource cone shell is based on a gold price of US$1,600 per ounce and silver at US$20 per ounce.

Table 1: Metates Mineral Resource Statement

Resource Category

M

tonnes

Gold

Eq.

(g/t)

Gold

(g/t)

Silver

(g/t)

Gold

(moz)

Silver

(moz)

Measured Mineral Resource

395.4

0.79

0.59

15.5

7.44

197.3

Intrusive

103.1

0.98

0.76

16.5

2.52

54.6

Sediment

292.4

0.73

0.52

15.2

4.92

142.7

Indicated Mineral Resource

907.0

0.58

0.42

11.8

12.36

344.7

Intrusive

146.0

0.76

0.60

11.9

2.79

55.9

Sediment

761.1

0.55

0.39

11.8

9.57

288.7

Measured/Indicated Resource

1,302.4

0.65

0.47

12.9

19.80

542.0

Intrusive

249.0

0.85

0.66

13.8

5.32

110.6

Sediment

1,053.4

0.60

0.43

12.7

14.48

431.4

Inferred Mineral Resource

62.2

0.44

0.32

9.0

0.64

18.0

Intrusive

3.4

0.51

0.43

6.0

0.05

0.7

Sediment

58.8

0.44

0.32

9.2

0.60

17.3

Notes:

1

.

The Mineral Resources have an effective date of May 18, 2021 and the estimate was prepared using the definitions in CIM Definition

Standards (May 10, 2014).

2

.

All figures are rounded to reflect the relative accuracy of the estimate and therefore numbers may not appear to add precisely.

3

.

Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

4

.

Mineral Resources are based on prices of US$1600/oz gold and US$20/oz silver.

5

.

Mineral Resources are based on a gold equivalent cut off grade of 0.26 g/t.

6

.

The gold equivalent value is calculated as follows:

Gold Equivalent (g/t) = Gold (g/t) + Silver (g/t) / 74.67, based on gold recovery of 70% and silver recovery of 75%.

Figure 1: Phase 1 Metates Cross Section

To view an enhanced version of Figure 1, please visit:

https://orders.newsfilecorp.com/files/752/91171_bdc26a5944d5e8b9_002full.jpg

The Company cautions that the results of the PEA are preliminary in nature and include inferred mineral

resources that are considered too speculative geologically to have economic considerations applied to

them to be classified as mineral reserves. There is no certainty that the results of the PEA will be

realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

Mining and Processing

The Metates mine will be a conventional open pit mine. The mining is planned to be conducted by

contractors.

Mine operations will consist of conventional drilling blasting, loading and hauling with large

off-road trucks, hydraulic shovels and wheel loaders.

Plant feed will be delivered to the primary crusher

and waste to various waste storage facilities.

The mine plan for this study only considered the higher

grade intrusive hosted mineralization as potential plant feed. There will be a stockpile for sedimentary

hosted resource that is not considered plant feed for this first phase of the operation.

There will also be a

low-grade stockpile facility to store marginal grade intrusive material for processing at the end of

commercial pit operations. There will be a support fleet of track dozers, rubber-tired dozers, motor

graders, and water trucks to maintain the working areas of the pit, waste storage areas, and haul roads.

Figure 2 shows the overall site layout.

The site layout features a very compact layout with all the major infrastructure located at or near site.

A

water diversion tunnel is required upstream of the mine and a water reservoir will be constructed below

the site to supply water for the operations.

Power will come to site via a connection to a nearby

substation and allow power to be supplied from the national grid.

All the major mining, waste dumps,

stockpiles and leach pads are all located in one watershed.

The mine plan consumes significantly less

power and water than a conventional sulphide flow sheet with a very low environmental footprint.

A mine plan was developed to supply plant feed to a conventional three stage crushing plant with the

capacity to process 15,000 tpd.

After crushing to 80% minus ½ inch the material is agglomerated in

alkaline solution and placed on a "on-off" pad to allow it to oxidize for up to 180 days. Oxidation solutions

are continuously regenerated to maintain the alkalinity and remove sulphate build up.

The oxidized material is then transferred to a permanent pad for conventional cyanide leaching in

multiple lifts resulting in gold and silver recoveries of 70% and 75% respectively.

Gold and silver bearing solutions from the permanent pad will be collected and processed in a

conventional Merrill Crowe plant to recover the gold and silver.

Precipitate from the Merrill Crowe plant will be smelted on-site into Dore and shipped off site for final

refining. The barren solution will be recharged with cyanide and returned to the gold and silver permanent

leach pads.

The site is scheduled to operate two 12 hour shifts per day for 365 days per year.

A flowsheet for the mineral processing is shown below in Figure 3.

Figure 2: Overall Site Layout

To view an enhanced version of Figure 2, please visit:

https://orders.newsfilecorp.com/files/752/91171_chesafigure2.jpg

Figure 3: Process Flowsheet

To view an enhanced version of Figure 3, please visit:

https://orders.newsfilecorp.com/files/752/91171_bdc26a5944d5e8b9_006full.jpg

Selected operating and production statistics from the PEA are presented in Table 2.

Table 2: Estimated PEA Operating and Production Parameters

Operating Metrics

Material Mined

Life of Mine ("LOM")

Total Material Mined From Pit (K tonnes)

533,998

Direct Feed To Process (K tonnes)

127,294

Low Grade Stockpile (K tonnes)

38,797

Waste Rock (K tonnes)

367,907

Strip Ratio (Low Grade as Ore)

2.22

Average Stacking Rate

(K tonnes/yr)

5,358

Average Processed Grades

Years

1-10

Years

11-20

Years

21-31

LOM

Avg.

Gold (g/t)

0.859

0.931

0.490

0.756

Silver (g/t)

23.18

11.22

12.75

15.71

Average Annual Production

Years

1-10

Years

11-20

Years

21-31

LOM

Avg.

Gold (K oz.)

104.8

114.7

57.1

91.1

Silver (K oz.)

3,004

1,467

1,598

2,009

Initial Capital Costs Summary

The initial capital costs, including contingency are estimated at $359 million. A significant reduction from

the 2016 PFS and reflects the smaller starter mine and compact site supported by nearby infrastructure

including close proximity to the national grid and water source.

A summary of estimated initial capital costs is presented in Table 3.

Table 3: Summary of PEA Initial Capital Costs

Summary of Initial Capital Costs

Cost

$000

Metates Site

Mining Equipment & Mine Development

$18,713

Crushing & Conveying

$36,104

Ponds & Pads

$28,404

Reagent/Regeneration System

$11,677

Merrill-Crowe & Refinery

$9,124

Subtotal

$104,022

Infrastructure

General Site/Earthworks/Access Roads

$106,069

Electric Power

$7,851

Water Supply

$7,380

Ancillaries & Buildings

$11,121

Subtotal

$132,421

Freight, Taxes & Duties

$4,060

Total Direct Field Cost

$240,503

Indirects-EPCM, Commissioning & Spares

$32,047

Total On Site Constructed Cost

$272,550

Contingency

$63,459

First Fills

$6,000

Owner's Cost

$17,200

Total Initial Capital Cost

$359,209

Operating Costs Summary

Cash costs and AISC per payable gold ounce are non-GAAP financial measures. Please see

"Cautionary Note Regarding Non-GAAP Measures" on page 11 of this press release.

Average LOM operating costs (including mining, processing, and G&A - net of capital development,

royalties and refining) total $686 per payable ounce of gold sold. The AISC, which includes sustaining

capital, capitalized exploration and reclamation, total $748 per payable ounce of gold sold.

Total estimated operating costs in the PEA are presented in Table 4.

Table 4: Summary of PEA Operating Costs

LOM

Average

US$/t

processed

$/Au Oz.

Production

Metates Site

Mining (including rehandle)

$7.51

$441.70

Processing (Crushing, Stacking, Oxidation, Leach, Merrill-Crowe)

$8.05

$473.65

Site Support

$1.41

$82.69

Profit Sharing

$1.32

$77.74

Total Operating Cost

$18.29

$1,075.78

Royalties (0.5% NSR & 7.5% Gov't EBITDA Royalty)

$1.45

$85.35

Doré Treatment Charges

$0.17

$10.15

By-Product Credit (Silver)

($8.25)

($485.31)

Total Cash Cost

$11.66

$685.97

Sustaining Capital, Reclamation & Closure

$1.06

$62.49

AISC

$12.72

$748.46

Financial Analysis

The financial analysis presented in Table 5 with the key financial assumptions.

Table 5: Key PEA Financial Values

Metal Price Assumptions

Low Case

Base Case

Spot

Gold ($/oz.)

$1,360

$1,600

$1,786

Silver ($/oz.)

$19

$22

$26

USD:CDN Exchange Rate $

1:1.25

USD:MEX Exchange Rate $

1:20.05

Unlevered Pre-Tax Economic Indicators

NPV @ 5% (C$M)

$896

$1,427

$1,906

NPV @ 5% (US$M)

$717

$1,142

$1,525

IRR %

25.3

35.4

45.2

Payback (years)

3.4

2.5

2.0

Levered After-Tax Economic Indicators

1

NPV @ 5% (C$M)

$509

$852

$1,162

NPV @ 5% (US$M)

$407

$682

$930

IRR %

26.9

41.2

55.9

Payback (years)

3.4

2.2

1.6

Notes:

1

.

The Company expects to debt finance a significant portion of development costs. The levered economics assume initial capital is 60% debt

financed at an annual interest rate of 7%, an upfront financing fee of 3%, and a seven-year term post commencement of commercial

production with a balloon payment of 30% of the principal at maturity.

Sensitivity Analysis

The Metates heap-leach PEA demonstrates strong economic performance across a range of gold and

silver prices. Estimated NPV sensitivities for key operating and economic metrics are presented in

Tables 7 through 9, as well as Figure 4.

Table 7: C$MM Pre-Tax NPV

(5%)

Sensitivity Analysis: Gold and Silver Prices

Gold Price (US$/oz)

1,400

1,600

1,800

2,000

2,200

Silver Price

(US$/oz)

20

$1,005

$1,345

$1,685

$2,025

$2,365

22

$1,087

$1,427

$1,767

$2,107

$2,447

24

$1,169

$1,509

$1,848

$2,188

$2,528

26

$1,250

$1,590

$1,930

$2,270

$2,610

28

$1,332

$1,672

$2,012

$2,352

$2,691

Table 8: US$MM Pre-Tax NPV

(5%)

Sensitivity Analysis: Gold and Silver Prices

Gold Price (US$/oz)

1,400

1,600

1,800

2,000

2,200

Silver Price

(US$/oz)

20

$804

$1,076

$1,348

$1,620

$1,892

22

$870

$1,142

$1,413

$1,685

$1,957

24

$935

$1,207

$1,479

$1,751

$2,023

26

$1,000

$1,272

$1,544

$1,816

$2,088

28

$1,065

$1,337

$1,609

$1,881

$2,153

Table 9: Pre-Tax IRR Sensitivity Analysis: Gold and Silver Prices

Gold Price (US$/oz)

1,400

1,600

1,800

2,000

2,200

Silver Price

(US$/oz)

20

28%

33%

38%

42%

47%

22

30%

35%

40%

45%

49%

24

33%

38%

43%

47%

52%

26

35%

41%

46%

50%

55%

28

38%

43%

48%

53%

57%