Corporate Updates

Central Iron Ore Limited - Project Update

VANCOUVER, BC / ACCESS Newswire / July 21, 2026 / Central Iron Ore Limited (TSX.V:CIO) ("CIO" or

"the Company") is pleased to provide an update on the Development work and studies that are in process

or recently completed.

British King and Endeavour

1. British King Mineral Resource Re-estimate.

This has been recently completed.

2. Endeavour Resource Estimate Review.

The current resource estimate has been reviewed and considered suitable to be used for re-

optimisation.

3. British King and Endeavour Re-optimisation and combined Schedule.

It is intended to commence this work next week.

4. Environmental Permits and Approvals.

Follow-up studies that are currently underway include:

• Fauna, Flora Desktop Review

• Subterranean Fauna

• Surface Water

The need and scope for further groundwater studies is being reviewed.

5. Mining Development and Closure Proposal.

i. A draft document is in preparation and will be updated as the required study information

becomes available ready for submission to the Department of Mines, Petroleum and Exploration

(DMPE). Work continued through June and July identifying and collecting the required data for

each section of this document.

ii. A small soil sampling campaign was designed to provide data for the Mine Closure Plan relating

to the pre-existing evaporation ponds and old vat leach area. Further samples have been collected

from the Endeavour project area. Currently analyses are pending.

6. Mining Lease M37/30 Renewal.

The Renewal application was lodged on March 24, 2026 and has been advertised. CIO have been

notified that the "negotiation in good faith period" with the Native Title Party commenced July 1,

2026.

7. Operating Licence L8891/2015/1 - Under the Environmental Protection Act 1986.

The new license L8891/2015/2 was issued on July 3, 2026.

8. British King Preliminary Geotechnical Assessment.

This work has been completed.

9. Waste Characterisation for Endeavour.

Waste rock samples have been collected from drill holes and are now in Kalgoorlie for cutting and

sampling.

About Central Iron Ore Limited

The Company's South Darlot Gold Project is located approximately 320km northwest of Kalgoorlie in

Western Australia and includes:

 The British King Mine Area which is 100% beneficially owned by the Company and the British King

Extensions, which is 100% owned by the South Darlot Joint Venture in which the Company holds a

70% interest, which together are National Instrument 43-101 - Standards of Disclosure for Mineral

Projects ("NI43-101") compliant.

The British King Mine is 5km southwest of Vault Minerals Darlot Mine.

 South Darlot Gold Project which comprises a number of tenements which are subject to a joint

venture with a subsidiary of Vault Minerals, details of which are set out below, in which CIO has

earned a 70% interest. The Endeavour Resource is included on these tenements.

British King Mine Area

The British King lease M37/30 is 100% beneficially owned by the Company and is National Instrument 43-

101 - Standards of Disclosure for Mineral Projects ("NI43-101") compliant. The British King Mine Area is

5km southwest of Vault Minerals' Darlot Mine includes the British King Mine which is currently in care and

maintenance.

Project Tenement Status Area (km2)

British King M37/30 Granted 0.1

British King L37/162 Granted 0.1

British King L37/191 Granted 0.1

South Darlot Joint Venture (Formerly Barrick Joint Venture Project)

The tenements set out in the table below ("South Darlot JV Tenements") are the subject of a joint venture

between the Company and subsidiaries of Vault Minerals. They are situated southwest of Vault Minerals'

Darlot Gold Mine and are contiguous with CIO's current holding in the area. The South Darlot JV

Tenements are detailed below.

Project Tenement Status Area (ha)

South Darlot JV M37/421 Granted 381

South Darlot JV M37/552 Granted 200

South Darlot JV M37/631 Granted 776

South Darlot JV M37/632 Granted 595

South Darlot JV M37/709 Granted 98

South Darlot JV M37/1045 Granted 90

South Darlot Mines Pty Ltd has a 70% interest in M37/1045, M37/709, M37/631 and M37/552 while Darlot

Mining Company Pty Ltd has a 30% interest. Darlot Mining Company Pty Ltd is holding a 70% interest in a

portion of two additional tenements, M37/421 and M37/632, on trust for South Darlot Mines Pty Ltd.

On behalf of the Board of Directors

CENTRAL IRON ORE LIMITED

"David Deitz"

David Deitz, Director/CEO

For further information, please contact:

www.centralironorelimited.com

Investor and Media Inquiries:

Direct: +61 2 9397 7521

Email: [email protected]

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this

release.

This news release is not for distribution to United States Services or for dissemination in the United

States.

Cautionary Note Regarding Forward-Looking Statements

This news release contains forward-looking information within the meaning of Canadian securities laws.

Although the Company believes that such information is reasonable, it can give no assurance that such

expectations will prove to be correct. Forward-looking information is typically identified by words such as:

believe, expect, anticipate, intend, estimate, postulate and similar expressions, or are those, which, by

their nature, refer to future events. The Company cautions investors that any forward-looking information

provided by the Company is not a guarantee of future results or performance, and that actual results may

diƯer materially from those in forward looking information as a result of various factors, including, but not

limited to, the state of the financial markets for the Company's equity securities, the state of the market

for iron ore or other minerals that may be produced generally, recent market volatility; variations in the

nature, quality and quantity of any mineral deposits that may be located, the Company's ability to obtain

any necessary permits, consents or authorizations required for its activities, to raise the necessary capital

or to be fully able to implement its business strategies and other risks associated with the exploration and

development of mineral properties. The reader is referred to the Company's disclosure documents for a

more complete discussion of such risk factors and their potential eƯects, copies of which may be

accessed through the Company's page on SEDAR at www.sedar.com.

SOURCE: Central Iron Ore Limited