NEWS RELEASE

Centerra Gold Reports Restart of Mill Processing Operations at Mt. Milligan

Toronto, Canada, February 5, 2018: Centerra Gold Inc. (“Centerra”) (TSX: CG) today reported that its

Mount Milligan operation in British Columbia, Canada initia ted restart of mill operations at partial capacity.

At this time, the mill is utilizing one ball mill to mini mize water requirements. During the restart phase, the

Company anticipates a ramp-up period and there may be periodic commissioning downtime. Mill operations

are expected to achieve sustainable mill throughput levels of approximately 30,000 tpd by mid-February.

During the recent shutdown the Company completed a number of steps to increase the flow of water into the

tailings storage facility (TSF) from which the Mount M illigan mill draws all of its water requirements to

supply milling operations. Such steps included adding pumps to existing water wells, increasing pump sizes

to increase the flow rate, and drilling additional wells. Current make-up water sources for the TSF are from

normal surface run-off, groundwater wells internal to the TSF, and from base underd rain towers that access

process water underlying the TSF. The Company expects to restart the second ball mill in April, returning

mill operations to full capacity, when additional fresh wa ter becomes available from surface run-off after the

spring melt. The return of mill operations to sustainable levels, on one or both ball mills, is dependent on the

performance of the make-up water sources noted above and the overall water balance in the TSF. In addition

the availability of water is subject to, among other things, natural forces that can be unpredictable.

As a further longer-term mitigation measure, the Company has now received an amendment to Mount

Milligan’s Environmental Assessment Certificate to allow pumping of water from a nearby lake (Philip

Lake) and has received the additional related permits. The Company expects to commence drawing water

from Philip Lake by the end of February.

The Company expects to issue its 2018 full-year Company-wide guidance on February 23, 2018.

Caution Regarding Forward-Looking Information

Information contained in this document which are not statements of historical facts, and the documents

incorporated by reference herein, may be “forward -looking information” for the purposes of Canadian

securities laws. Such forward-looking information invol ves risks, uncertainties and other factors that could

cause actual results, performance, prospects and opportuni ties to differ materially from those expressed or

implied by such forward looking information. The words “believe”, “expect”, “anticipate”, “contemplate”,

“plan”, “intends”, “continue”, “budget”, “estimate”, “may”, “will”, “schedule”, “understand” and similar

expressions identify forward-looking information. These forward-looking statements relate to, among other

things: the performance of mill operations at the Mount Milligan mill, including the re-start of the mill, the

achievement of sustainable throughput, the return of mill operations to full capacity, the continued

performance of mitigation measures to provide make-up water flows to the TSF, and the timing and outcome

of pumping from Philip Lake to access additional fresh water.

Forward-looking information is necessarily based upon a number of estimates and assumptions that, while

considered reasonable by Centerra , are inherently subject to significant political, business, economic and

competitive uncertainties and contingencies. Know n and unknown factors could cause actual results to

differ materially from those projected in the forward looking information. Factors that could cause actual

1 University Avenue, Suite 1500 2

Toronto, ON

M5J 2P1

tel. 416-204-1953

fax 416-204-1954

www.centerragold.com

results or events to differ materially from current expectations include, among other things: Aboriginal

claims and consultative issues relating to Mount Milligan’s permitting and regulatory matters, risks related to

operational matters and the Company’s ability to successf ully manage such matters, including the ability of

the Company to successfully manage water issues, mechanical breakdowns and maintenance at Mount

Milligan; the availability of water resources at Mount Milligan and the Company’s expectations regarding

the effects and timing of weather and spring melt at Mount Milligan; and the Company’s expectations

regarding the results of drilling to access water from aqui fers near Mount Milligan. See section titled “Risks

that can affect our business” in the 2016 Annual Information Form available on SEDAR at www.sedar.com.

There can be no assurances that forward-looking informa tion and statements will prove to be accurate, as

many factors and future events, both known and unknown could cause actual results, performance or

achievements to vary or differ materially, from the r esults, performance or achievements that are or may be

expressed or implied by such forward-looking statements contained herein or incorporated by reference.

Accordingly, all such factors should be considered carefully when making decisions with respect to Centerra,

and prospective investors should not place undue relian ce on forward looking information. Forward-looking

information is as of February 5, 2018. Centerra a ssumes no obligation to update or revise forward looking

information to reflect changes in assumptions, changes in circumstances or any other events affecting such

forward-looking information, except as required by applicable law.

About Centerra

Centerra Gold Inc. is a Canadian-based gold mining company focused on operating, developing, exploring

and acquiring gold properties in North America, Asia and other markets worldwide. Centerra operates two

flagship assets, the Kumtor Mine in the Kyrgyz Repu blic and the Mount Milligan Mine in British Columbia,

Canada and is the largest Western-based gold producer in Central Asia. Centerra's shares trade on the

Toronto Stock Exchange (TSX) under the symbol CG. The Company is based in Toronto, Ontario, Canada.

For more information:

John W. Pearson

Vice President, Investor Relations

Centerra Gold Inc.

(416) 204-1953

[email protected]

Additional information on Centerra is available on the Company’s web site at www.centerragold.com

and at SEDAR at www.sedar.com.

- end -