Centerra Gold Announces Thompson Creek Feasibility Study Results and Strategic Plan for US Molybdenum Operations, Including a Restart of the Thompson Creek Mine and Ramp-Up of Langeloth Integrated value of Thompson Creek and Langeloth is expected to have
Centerra Gold Announces Thompson Creek Feasibility Study Results and
Strategic Plan for US Molybdenum Operations, Including a Restart of the
Thompson Creek Mine and Ramp-Up of Langeloth
Integrated value of Thompson Creek and Langeloth is expected to have
after-tax NPV8% of $472M and IRR of 22%
Langeloth, at full capacity and integrated with Thompson Creek, is expected to generate
approximately $45M earnings from operations and $50M EBITDANG per year
All figures are in United States dollars. All production figures reflect payable metal quantities and are on a 100% basis, unless
otherwise stated. For references denoted with NG, refer to the “Non-GAAP Financial Measures” disclosure at the end of this
news release for a description of these measures.
TORONTO, Sept. 12, 2024 -- Centerra Gold Inc. (“Centerra” or the “Company”) (TSX: CG) (NYSE: CGAU) announces the
results from its Thompson Creek feasibility study, including a strategic, integrated business plan for its Molybdenum Business
Unit (“MBU”) consisting of a restart of the Thompson Creek Mine (“Thompson Creek”) and a commercially optimized plan for
the Langeloth Metallurgical Facility (“Langeloth”), collectively the US Molybdenum Operations (“US Moly”). Centerra will host a
conference call and webcast to discuss the strategic plan for US Moly on Friday, September 13, 2024, at 9:00 am Eastern
Time. Details for the conference call and webcast are included at the end of the news release.
President and CEO, Paul Tomory, commented, “Over the last year, we have developed a value-enhancing strategy for
Centerra’s US molybdenum operations, centered around the vertical integration of Thompson Creek and Langeloth, and
supported by strong molybdenum market fundamentals. The combined US Moly business is expected to produce an after-tax
net present value (8%) (“NPV8%”) of $472 million. A key contributor to this value is Langeloth, which at full capacity, integrated
with Thompson Creek, has the potential to generate robust annual EBITDA. Today, we announce the decision to unlock
significant value through the restart of operations at Thompson Creek and a progressive ramp-up of production at Langeloth.
When Thompson Creek begins production, currently targeted for the second half of 2027, it will provide additional high-grade,
high-quality feed to Langeloth, enabling a ramp-up of production towards Langeloth’s full annual capacity of 40 million pounds
while improving operational flexibility to meet market demand.”
Paul Tomory continued, “We completed a feasibility study at Thompson Creek that has confirmed the capital estimate from
the pre-feasibility study, while adding another year of production. Following significant progress on permitting efforts in the
second quarter 2024, we have pivoted from a two-phased approval to a single-phase capital investment of $397 million over
three years, from now through mid-2027. Our total project costs guidance at Thompson Creek for the second half of 2024 is
expected to be $55 to $65 million. We will provide 2025 guidance for Thompson Creek with our annual guidance that is
expected to be published early next year.”
Paul Tomory concluded, “We are continuing to explore strategic options to unlock the full potential of our molybdenum
business, in line with Centerra’s strategy to maximize the value of each asset in our portfolio. While Centerra expects to
remain a gold-focused company, we acknowledge the significant value of our base metal assets.”
Integrated US Moly Highlights
• Robust integrated economics of Thompson Creek and Langeloth: Strong project economics due to synergies
with the high-quality concentrate blend that could be achieved when Thompson Creek is vertically integrated with
Langeloth. Once Thompson Creek resumes full production, the US Moly business is expected to generate sustainable
strong annual cash flows.
US Moly(1)
(Thompson Creek +
Langeloth)
Thompson Creek
Only(3)
Langeloth
Only
NPV8% $472M $185M $258M
Internal Rate of Return (“IRR”) 22% 15% n.m.
Additions to PP&E / Non-sustaining capital
expendituresNG(2) $397M $397M -
(1) US Moly includes an additional $29M of unattributed tax synergies.
(2) Additions to Property, Plant, and Equipment (“PP&E”) are the same as Capital ExpendituresNG.
(3) The economic assessment for Thompson Creek in the FS (as defined below) has been prepared on a stand-alone basis
and does not include integration with Langeloth. The economics for integrating Thompson Creek and Langeloth are
extrapolated from the Thompson Creek feasibility study.
NOTE: See “Assumptions” at the end of this news release. “n.m.” stand for not meaningful.
• Improved integrated economics compared to the pre-feasibility study (“PFS”) in September 2023: Integrated
economics based on the FS have improved as compared to the PFS, specifically the Thompson Creek updated life of
mine (“LOM”) plan has an additional 12 million pounds of molybdenum being produced, one year of additional mine life,
more concentrate produced in the first four years, and a de-risked capital estimate.
US Moly: Thompson Creek + Langeloth
FS(1) PFS
NPV8% $472M $218M
NPV5% $692M $373M
IRR 22% 16%
LOM 12 years 11 years
Thompson Creek Molybdenum Production 146M lbs 134M lbs
Additions to PP&E / Non-sustaining capital expenditures NG(2,3) $397M $350M - $400M
(1) The economics for integrating Thompson Creek and Langeloth are extrapolated from the Thompson Creek feasibility
study.
(2) Additions to PP&E are the same as Capital Expenditures NG.
(3) Thompson Creek only; Langeloth additions to PP&E are in the range of $3 to $4 million per year and are considered
sustaining capital.
Langeloth Highlights
• Phased ramp-up to full capacity: Langeloth plans to ramp up production progressively over the next few years to
increase production towards its full capacity of 40 million pounds per annum by 2028, which aligns with Thompson
Creek’s first full year of production. At full capacity, the molybdenum feed to Langeloth is expected to consist of
approximately one third supplied by Thompson Creek and two thirds purchased from third parties.
• At full capacity, Langeloth is expected to generate approximately $45 million in earnings from operations
and $50 million of earnings before interest, taxes, depreciation and amortization (“EBITDA”) NG annually.
Significant synergies and margin improvements are expected to result from increased capacity utilization at Langeloth,
including improved blending flexibility and more higher margin molybdenum products enabled by the high-quality feed
from Thompson Creek.
• Strategic geographic location: Langeloth is strategically connected to the North American steel supply and sales
markets via efficient transportation networks and reliable infrastructure. Being close to several major US east coast
ports, Langeloth is also well located for importing molybdenum concentrates and exporting molybdenum products.
• Flexible and agile operations: With six roasters, the ability to produce a variety of finished molybdenum products
and a potential total capacity of approximately 40 million pounds, Langeloth has flexibility to adapt to changing market
and commercial conditions. Langeloth has value-added production capabilities, namely for ferromolybdenum and pure
molybdenum oxide, positioning the business for opportunities and growth.
• Strong leadership and people: The Langeloth management team and staff are highly experienced, dedicated and
committed to a strong culture of operational excellence and innovation. With 100 years of experience in processing
molybdenum, the team at Langeloth has developed a strong commercial network and constructive engagement with
local regulators.
Thompson Creek FS Highlights
• Robust project economics: NPV8% of $185 million and after-tax IRR of 15% using an assumed flat molybdenum price
of $20 per pound for the LOM. The economic assessment for Thompson Creek in the FS has been prepared on a stand-
alone basis and does not include the benefits of integration with Langeloth.
• De-risked capital costs: Initial capital investment of approximately $397 million. The capital expenditures needed to
restart Thompson Creek are significantly de-risked due to an existing pit, significantly advanced equipment rebuilds and
purchases and an existing process plant that requires minimal upgrades and refurbishment. A majority of the
anticipated capital expenditures are focused on capitalized stripping, plant refurbishment and mine mobile fleet
upgrades.
• Initial mine life of 12 years: Average annual molybdenum production is estimated to be approximately 13 million
pounds after initial ramp-up. The average LOM operating costs are $9.66 per molybdenum pound sold and LOM all-in
sustaining costs (“AISC”)NG are $12.46 per molybdenum pound sold.
• Strong Reserve Base: The FS includes proven and probable molybdenum reserves of 161 million pounds, measured
and indicated molybdenum resources of 63 million pounds and inferred molybdenum resources of 17 million pounds, as
of September 1, 2024. The average reserve grade is 0.065% molybdenum.
The Company expects to file a technical report for Thompson Creek on its website at www.centerragold.com, on SEDAR+ at
www.sedarplus.ca and EDGAR at www.sec.gov/edgar.
US Moly Overview
US Moly, consisting of the Langeloth metallurgical facility near Pittsburgh, Pennsylvania, and the Thompson Creek mine in
Idaho, is part of Centerra’s MBU. The molybdenum assets were acquired by Centerra in 2016, along with the Mount Milligan
gold-copper mine.
Langeloth
Langeloth is one of three molybdenum conversion facilities in the United States. Its facility and existing permits make it a
unique and strategic asset, given its proximity to the North American steel market. Langeloth began commercial molybdenum
conversion operations in 1924 and has historically operated at levels significantly higher than today. Over a two-year period
prior to the suspension of the Thompson Creek mine in December 2014, the volume of molybdenum roasted at Langeloth was
around 37 million pounds per year.
Langeloth operates as a conversion facility of molybdenum concentrate into metallurgical and chemical grade products. These
products are sold to steel, other metallurgical, and chemical producers globally. Technical oxide is the main product
manufactured by Langeloth due to its role as a key input in the manufacturing of high-performance steels. It can potentially be
further processed into value-added products that command a higher margin. Langeloth can also produce ferromolybdenum and
pure molybdenum oxide, and it has the capability to produce byproducts such as rhenium, with flexibility to adjust the product
mix depending on market demand and the quality of concentrates sourced. The availability of high-quality Thompson Creek
concentrate provides significant commercial flexibility to the MBU.
Commercial Optimization of Langeloth
Centerra has completed a commercial optimization plan at Langeloth, geared at increasing profitability and maximizing its
future potential by increasing production levels, achieved by a ramp-up in the purchase of third-party concentrates and the
restart of the Thompson Creek primary molybdenum mine.
Langeloth is well-positioned to capitalize on the current supply deficit in the molybdenum market and grow the business to
meet the market demand. In the recent past Langeloth has operated slightly below its annual breakeven capacity of
approximately 14 million pounds. The operation can be ramped up to full capacity to enable production of approximately 40
million pounds per year in a straightforward manner.
At full capacity, significant synergies and margin improvements that will enhance future cash flow generation and profitability
from US Moly are expected to result from: (1) ability to leverage fixed costs, related to increased capacity utilization at
Langeloth from the current level of approximately one third; (2) ability to blend the high-quality Thompson Creek concentrate
with lower quality third-party concentrates; and (3) the ability, enabled by the quality of the Thompson Creek concentrate, to
produce an increased volume of higher margin final molybdenum products.
At full production capacity, integrated with Thompson Creek, the molybdenum conversion facility at Langeloth has the potential
to generate annually approximately $50 million of EBITDA NG, $40 million in cash flow from operations and free cash flow NG of
$35 million.
As a result of the compelling value opportunity, Centerra is initiating a progressive ramp-up at Langeloth to allow for
commercial optimization. Langeloth is expected to ramp up production progressively towards its full capacity of 40 million
pounds per annum by 2028, which aligns with Thompson Creek’s expected first full year of production. At full capacity, the
molybdenum feed processed at the Langeloth facility is expected to consist of approximately one third supplied by Thompson
Creek and approximately two thirds purchased from third-party providers. Further details on the restart of Thompson Creek are
provided below.
Based on an assumed flat price of $20 per pound molybdenum, a working capital investment will be required over the period
from 2025 to 2028 to support the ramp-up to full capacity. On a cash flow basis, this increase in working capital is expected to
be largely offset by cash flow generated by Langeloth during the same period. The structure of commercial contracts at
Langeloth helps to mitigate molybdenum price volatility. Concentrates are purchased at a discount to the prevailing market
molybdenum price, while final products are generally sold at prices at or above this benchmark. As a result, the integrated
operations of US Moly will be better positioned to withstand future fluctuations in molybdenum prices.
Reaching higher capacity utilization will depend on several factors which are not fully in Centerra’s control, including the ability
to acquire third-party concentrates on favourable commercial terms over a significant period of time.
Thompson Creek
The Thompson Creek mine is a large open-pit primary molybdenum mine. It was a producing mine until it was placed on care
and maintenance in December 2014. It has an existing open pit, as well as established site infrastructure, processing facilities
and equipment fleet.
Feasibility Study
The Company has completed a FS on the restart of mining at Thompson Creek, with the objective of realizing value for the US
Moly business. A restart of Thompson Creek, on a stand-alone basis, is expected to result in NPV 8% of $185 million and IRR
of 15%, based on an assumed flat molybdenum price of $20 per pound. The FS includes an optimized mine plan with a 12-
year mine life. A summary of the FS production profile is included in the table below.
Thompson Creek FS Production Profile
Total Mined
(M tons)
Grade of Ore Processed
(% Mo)
Molybdenum Production (3)
(Mlb)
2024(1) 4.9 - -
2025 50.0 - -
2026 48.0 - -
2027(2) 52.0 0.05 4.7
2028 56.9 0.07 12.4
2029 51.0 0.08 14.5
2030 45.0 0.08 14.7
2031 37.0 0.07 13.7
2032 57.0 0.05 9.7
2033 40.0 0.04 7.8
2034 36.7 0.08 15.9
2035 24.2 0.10 19.3
2036 8.0 0.06 12.2
2037 - 0.05 9.1
2038 - 0.05 9.1
2039(2) - 0.03 2.4
Total LOM 510.7 0.06 145.6
(1) 2024 figures for the period from September 1, 2024 to December 31, 2024.
(2) Production is expected for a part of this year.
(3) It is estimated that approximately 4.7% of the recovered molybdenum pounds will be further refined at Thompson Creek
and sold as high-performance molybdenum.
NOTE: “Mo” stands for molybdenum, “M tons” stands for millions of short (US) tons, “Mlb” stands for millions of molybdenum
pounds. Totals may not sum precisely due to rounding.
The cost profile associated with the FS is largely driven by the grade profile. AISC NG per pound from 2028 to 2031 are
expected to be lower than the LOM average due to higher grades and more ore tons mined, which is expected to result in
stronger cash flows in these years. The average operating costs over the LOM are detailed in the table below. These operating
costs exclude capitalized pre-production costs, which are included in capital costs. Processing costs cover mill, tailings and
water management costs.
LOM average operating costs
Mining $2.03 per ton mined
Processing $4.85 per ton processed
General and administrative (“G&A”) $1.67 per ton processed
Capital ExpendituresNG
Centerra is proceeding with a restart of Thompson Creek, which is expected to require an investment of approximately $397
million in total initial, non-sustaining capital expenditures NG over three years, from September 2024 through mid-2027. In the
second quarter of 2024, following environmental studies and regulatory reviews, Centerra obtained mine permit authorizations
for additional lands at Thompson Creek, which will enable the proposed pit highwall layback included in the FS. As a result of
receiving these mine permit authorizations, a key first step in the overall permitting process, the Company is moving away
from a two-phased capital approval previously disclosed to a single-phase capital investment over three years. Thompson
Creek is proactively advancing environmental studies which should support future permitting, which will not be required until
several years after first production.
Centerra’s capital investment at the Thompson Creek mine is significantly de-risked due to an existing pit, significantly
advanced equipment rebuilds and purchases, and an existing process plant that requires some refurbishment. Early works to
support the restart of operations at Thompson Creek are underway, progressing on budget and on schedule. The majority of
the capital expenditures going forward are expected to be focused on pre-stripping activities and mill refurbishment. Over the
first six months of 2024, capital spending at Thompson Creek was primarily related to refurbishment of existing mining mobile
equipment and the purchase of additional mobile equipment, stripping activities and technical studies.
Updated 2024 Guidance at Thompson Creek
For the second half of 2024, total project costs at Thompson Creek are expected to be $55 to $65 million, primarily related to
pre-production stripping and mine mobile fleet upgrades. Approximately $10 million of these costs will be expensed for
accounting purposes, with the remainder treated as capital expenditures. Including the actual amounts spent in the first six
months of 2024 of $20.9 million, full year 2024 project development costs guidance at Thompson Creek is $75 to $85 million.
Sensitivity to Molybdenum Prices
The Thompson Creek FS and integration of Langeloth demonstrate strong economics at assumed flat molybdenum prices of
$20 per pound. Langeloth provides resilience to low molybdenum prices in the cycle. The sensitivity to changes in
molybdenum prices is illustrated in the table below.
FS Economics (Thompson Creek only)
Molybdenum Price ($/pound)
$17.50 $20.00 (FS price) $22.50 $25.00
NPV8% ($7M) $185M $370M $542M
NPV5% $70M $307M $535M $744M
IRR 8% 15% 21% 26%
US Moly Integrated Economics (Thompson Creek plus Langeloth)
Molybdenum Price ($/pound)
$17.50 $20.00 (FS price) $22.50 $25.00
NPV8% $313M $472M $628M $782M
NPV5% $496M $692M $885M $1,076M
IRR 18% 22% 26% 29%
Mineral Reserve and Mineral Resource Estimates
Thompson Creek is an open pit operation that was active until 2014 when management made the decision to cease operations
due to falling molybdenum prices. After approximately 10 years on care and maintenance, the historical mineral resource
model needed to be updated. The tables below outline the mineral reserve and resources at Thompson Creek as of September
1, 2024.
Thompson Creek Mineral Molybdenum Reserve and Resource Estimate (September 1, 2024)
Tons
(M)
Molybdenum
Grade
(%)
Contained Molybdenum
(Mlbs)
Proven 49 0.076 75
Probable 75 0.057 86
Proven and Probable 125 0.065 161
Measured 6 0.059 7
Indicated 50 0.057 57
Measured and Indicated 55 0.057 63
Inferred 12 0.072 17
NOTE: See “Reserve and Resource Notes” at the end of this news release. Totals may not sum precisely due to rounding.
Endako Project
Centerra has a 75% interest in the Endako mine in northern British Columbia, Canada, which is part of the MBU. The
remaining 25% interest is held by Moon River Capital Ltd. Endako is expected to remain in care and maintenance while the
Company focuses on the Thompson Creek restart. Endako is an important primary molybdenum asset with a large defined
resource in a top-tier jurisdiction, with a modern processing plant, providing longer-term optionality. Should Endako be
restarted in the future, it has the potential to provide approximately one third of the molybdenum feed supplied to Langeloth,
which could either complement or replace the Thompson Creek feed.
Molybdenum Market
Molybdenum is an industrial metal principally used for metallurgical applications such as a ferro-alloy in engineered, stainless,
and other speciality steels where high strength, temperature-resistant or corrosion-resistant properties are sought. The
addition of molybdenum enhances the strength, toughness and wear and corrosion-resistance in steels. Molybdenum is used
in major industries including chemical and petrochemical processing, oil and gas for drilling and pipelines, power generation,
automotive and aerospace. It is also required for several green energy applications, especially wind, geothermal and nuclear.
Higher purity molybdenum is also widely used in non-metallurgical applications such as petroleum refining catalysts,
lubricants, flame-retardants in plastics, water treatment and as a pigment.
According to the World Bank report “Minerals for Climate Action: The Mineral Intensity of the Clean Energy Transition ” (2020),
molybdenum is named one of the cross-cutting minerals, like copper, needed across a range of low-carbon technologies,
especially wind and geothermal. The report estimates that the cumulative molybdenum demand under the renewable energy
roadmap scenario from the International Renewable Energy Agency may grow by 119% through 2050 from green technologies
only. Based on data from the International Molybdenum Association , the world used around 630 million pounds of
molybdenum in 2023, with the most used in engineered steels (38%), stainless steels (25%) and chemicals (13%). A variety
of end uses and limited substitution ensures that molybdenum is not dependent on specific industries, making the demand for
it relatively stable.
Conference Call to Discuss the Strategic Plan for US Moly
Centerra will host a conference call and webcast to discuss the strategic plan for US Moly on Friday, September 13, 2024, at
9:00 am Eastern Time. Details for the conference call and webcast are included below.
Webcast
• Participants can access the webcast at the following link.
• An archive of the webcast will be available for until end of day December 13, 2024.
Conference Call
• Participants can register for the conference call at the following registration link. Upon registering, you will receive the
dial-in details and a unique PIN to access the call. This process will by-pass the live operator and avoid the queue.
Registration will remain open until the end of the live conference call.
• Participants who prefer to dial-in and speak with a live operator, can access the call by dialing 1-844-763-8274 or 647-
484-8814. It is recommended that you call 10 minutes before the scheduled start time.
• After the call, an audio recording will be made available via telephone for one month, until end of day October 13, 2024.
The recording can be accessed by dialing 412-317-0088 or 1-877-344-7529 and using the passcode 1752426. In
addition, the webcast will be archived on Centerra’s website at: www.centerragold.com.
About Centerra Gold
Centerra Gold Inc. is a Canadian-based gold mining company focused on operating, developing, exploring and acquiring gold
and copper properties in North America, Türkiye, and other markets worldwide. Centerra operates two mines: the Mount
Milligan Mine in British Columbia, Canada, and the Öksüt Mine in Türkiye. The Company also owns the Goldfield District
Project in Nevada, United States, the Kemess Project in British Columbia, Canada, and owns and operates the Molybdenum
Business Unit in the United States and Canada. Centerra’s shares trade on the Toronto Stock Exchange (“TSX”) under the
symbol CG and on the New York Stock Exchange (“NYSE”) under the symbol CGAU. The Company is based in Toronto,
Ontario, Canada.
For more information:
Lisa Wilkinson
Vice President, Investor Relations & Corporate Communications
(416) 204-3780
Lana Pisarenko
Senior Manager, Investor Relations
(416) 204-1957
Additional information on Centerra is available on the Company’s website at www.centerragold.com, on SEDAR+ at
www.sedarplus.ca and EDGAR at www.sec.gov/edgar.
Reserve and Resource Notes
1. Mineral Reserves stated in the table above are the economic portion of the Measured and Indicated Mineral Resource
contained within the engineered pit design following the selected ultimate Pseudoflow pit shell.
2. Mineral Reserves are stated in terms of in situ tons and grade before process recovery is applied.
3. Modifying factors such as dilution and mining loss have been accounted for.
4. The economic assumptions used for the Mineral Reserve estimate include: ore mining cost of $2.17/ton; waste mining
cost of $1.77/ton; mining sustaining cost of $0.06/ton; G&A, processing, and sustaining costs of $7.33/ton ore; and
selling cost of $1,460/ton metal in concentrate.
5. Mineral Reserves are based upon a 0.030% Mo internal cut-off grade with some marginal material included, using a
$16.00/lb Mo price with a variable molybdenum recovery.
6. Mineral Resources are reported exclusive of Mineral Reserves; Mineral Resources that are not Mineral Reserves do not
have demonstrated economic viability.
7. Mineral Resources are considered for open pit extraction.
8. Resources are reported using a 0.025% Mo cut-off grade within a conceptual pit shell and are exclusive of Mineral
Reserves. Economic parameters for the determination of the resource cut-off grade include: (i) Molybdenum price of
US$18.50/lb; (ii) Mining cost of $1.77-$2.17/ton and G&A and processing cost of $6.75/ton processed. Sustaining
costs were not included in the resource cut-off grade calculation; (iii) At the cut-off grade an 82% recovery was
assumed.
9. Mineral Resources are classified and have been estimated in accordance with CIM Definition Standards.
10. As required by reporting guidelines, rounding may result in apparent summation differences between tons, grade, and
metal content.
11. Refer to the full technical report for the Thompson Creek mine at www.centerragold.com, on SEDAR+ at
www.sedarplus.ca and EDGAR at www.sec.gov/edgar.
Feasibility Study Qualified Persons (“QPs”)
Lars Weiershäuser, PhD, P.Geo, and Centerra’s Director, Geology, has reviewed and approved the scientific and technical
information included in this news release related to mineral resource estimates. Dr. Weiershäuser is a Qualified Person within
the meaning of the Canadian Securities Administrators’ National Instrument 43-101, Standards of Disclosure for Mineral
Projects (“NI 43-101”).
Jean-Francois St-Onge, Professional Engineer, member of the Professional Engineers of Ontario (PEO), has reviewed and
approved the scientific and technical information in this news release related to mineral reserve estimates, operating and
capital costs. Mr. St-Onge is a Qualified Person within the meaning of NI 43-101. Mr. St-Onge was Centerra’s Senior Director,
Technical Services until May 31, 2024, and is now providing services to the Company as an external consultant.
All other scientific and technical information presented in this news release was reviewed and approved by Centerra’s
geological and mining staff under the supervision of W. Paul Chawrun, Professional Engineer, member of the Professional
Engineers of Ontario (PEO) and Centerra’s Executive Vice President and Chief Operating Officer. Mr. Chawrun is a Qualified
Person within the meaning of NI 43-101.
For more information on the FS and the full list of QPs, please refer to the full technical report for the Thompson Creek mine at
www.centerragold.com, on SEDAR+ at www.sedarplus.ca and EDGAR at www.sec.gov/edgar.
Assumptions
The economic analysis of the project was performed using the following assumptions and basis:
1. Economic assessment for Thompson Creek is prepared on a stand-alone basis and does not include any integration
with Langeloth.
2. Pre-tax net cash flows for Thompson Creek include all operating, transport, treatment, capital and reclamation costs.
3. Economic assessment of the project uses a discounted cash flow approach. Cash flows are taken to occur at the mid-
year of each period. NPV is calculated by applying no discounting to 2024 cash flows and by discounting LOM cash
flows from the year 2025 to the end of mine life to January 1, 2025, using 8% discount rate.
4. Project economics are based on a valuation date of September 1, 2024.
5. A price of $20/lb of molybdenum is assumed throughout the LOM.
6. All costs presented are in constant US dollars as of Q2 2024 with no price inflation or escalation factors applied.
7. Ore production is scheduled to begin in Q3 2027.
8. Mine life is 16 years, including an initial four years of construction and waste stripping from years 2024 to 2027 and 12
years of production activities.
9. Average annual molybdenum production during production years is 12 million pounds per year. All molybdenum
produced by the mine is assumed to be sold in the same year it is produced.
10. Working capital for Thompson Creek is assumed not to change significantly over the LOM and is not modeled in this
economic analysis.
11. No salvage values are assumed for the capital equipment at the end of mine life.
12. Reclamation and closure costs for the site were estimated by an external consultant at a total of $202 million.
Reclamation and closure activities will start progressively after the end of production in 2039, with the bulk of
reclamation work to be completed by 2045, followed by ongoing tailings management costs and monitoring thereafter.
13. Transportation costs for molybdenite concentrate shipments to Langeloth are estimated at $29 million over the LOM.
Treatment costs at Langeloth are estimated at $118 million over the LOM. These costs include all processing and
refining expenses necessary to convert the molybdenite concentrate into molybdenum oxide and other marketable
products. The estimated costs for transportation to and treatment at Langeloth are based on current trucking quotes
and current treatment costs at the facility, respectively.
Caution Regarding Forward-Looking Information
Information contained in this document which is not a statement of historical fact, and the documents incorporated by
reference herein, may be “forward-looking information” for the purposes of Canadian securities laws and within the meaning of
the United States Private Securities Litigation Reform Act of 1995. Such forward-looking information involves risks,
uncertainties and other factors that could cause actual results, performance, prospects and opportunities to differ materially
from those expressed or implied by such forward-looking information. The words "achieve", “advance”, “assume”, “anticipate”,
“approach”, “believe”, “budget”, “could”, “de-risk”, “develop”, “enhance”, “estimate”, “expect”, “explore”, “focus”, “forecast”,
“future”, “generate”, “growth”, “in line”, “improve”, “may”, “maximize”, “offset”, “optimize”, “plan”, "potential", “remaining”,
“restart”, “result”, “schedule”, “strategy”, “subject to”, “target”, “understand”, “update”, “will”, and similar expressions identify
forward-looking information.
These forward-looking statements relate to, among other things: statements regarding the Company’s strategic plan; any
synergies which may arise from, or are expected to arise from, the vertical integration of Thompson Creek and Langeloth
including the Company’s ability to source and blend the concentrate from Thompson Creek or third-parties at Langeloth; the
proposed pit highwall layback included in the Thompson Creek feasibility study; projections regarding earnings, cash flow from
operations, free cash flow, internal rates of return and after-tax net present values for Thompson Creek, Langeloth or US Moly;
the 2024 guidance for project spending at Thompson Creek related to capitalized stripping, plant refurbishment, mine mobile
fleet upgrades and capital expenditure guidance; fluctuation of, sensitivity to, and assumptions of molybdenum prices and the
impact it may have on the future supply and demand of molybdenum and steel; the expected profile of US Moly’s future
production and costs; updates to the life of mine plan for Thompson Creek; the expected filing of a technical report for
Thompson Creek; Langeloth’s ability to capitalize on growing demand in the molybdenum market; strategic options for the
entire MBU and US Moly; future cash flow generation and profitability from Thompson Creek, Langeloth or US Moly; evaluating
external opportunities for growth; ongoing evaluations of a restart of Thompson Creek, including integrating Langeloth, its
operating capacities and the use of the concentrate from Thompson Creek or third-parties, the ability of the Company
successfully advance environmental studies that support future permitting; the Company receiving all necessary permits and
authorizations required during the restart and production at Thompson Creek; mineral reserve and mineral resource estimates
from Thompson Creek; the ability to ramp-up operations at Langeloth and realizing its full annual capacity; the ability of the
Company to obtain the requisite supply to support full capacity at Langeloth from third-parties; future prices of molybdenum
including the ability of the Company to purchase concentrate at a discount to the market and being able to sell final products
at or above this benchmark; the future of Endako, its ability to supply Langeloth with molybdenum feed if restarted and
whether or not this molybdenum feed could complement or replace that feed from Thompson Creek; and the future exploration
plans for the Company.
Forward-looking information is necessarily based upon a number of estimates and assumptions that, while considered
reasonable by Centerra, are inherently subject to significant technical, political, business, economic and competitive
uncertainties and contingencies. Known and unknown factors could cause actual results to differ materially from those
projected in the forward- looking information. Factors and assumptions that could cause actual results or events to differ
materially from current expectations include, among other things: (A) strategic, legal, planning and other risks associated with
the Company’s operations, including; the management of external stakeholder expectations; the impact of changes in, or to
the more aggressive enforcement of, laws, regulations and government practices; risks that community activism may result in
increased contributory demands or business interruptions; potential defects of title in the Company’s properties that are not
known as of the date hereof; the imprecision of the Company’s mineral reserves and resources estimates and the
assumptions they rely on, including environmental, processing permitting, taxation, socioeconomic, infill and exploration
drilling and other factors; key assumptions, parameters and methods used to estimate the mineral reserve and mineral
resource estimate in the Thompson Creek feasibility study; Indigenous claims and consultative issues relating to the
Company’s properties which are in proximity to Indigenous communities; and (B) risks related to operational matters and
geotechnical issues and the Company’s continued ability to successfully manage such matters, including: the ability of the
Company to achieve pit slope design angles at Thompson Creek, particularly in the North Wall, which will be based on future
drilling and may be impacted by stronger/weaker rock characteristics, favorable/unfavorable geologic structure, and/or
variations in pore pressures that could result in an increase or decrease in required depressurization to achieve these slope
design angles; the ability of the Company to achieve historical throughput rates at Thompson Creek; the Company receiving
the required authorizations and permits for the restart of Thompson Creek; the ability of the Company to source and blend
concentrate from Thompson Creek or third-parties at Langeloth; the stability of the pit walls at the Company’s operations,
including Thompson Creek; the integrity of tailings storage facilities and the management thereof, including as to stability,
seismic activity, compliance with laws, regulations, licenses and permits, controlling seepages and storage of water, where
applicable and any future capital expenditures required for active reclamation and tailings storage facilities issues; changes to
current remediation plans due to tailings storage facilities structures; the ability of the Company to achieve its commercial
optimization plan at Langeloth; changes to, or delays in the Company’s supply chain and transportation routes, including
cessation or disruption in rail and shipping networks, whether caused by decisions of third-party providers or force majeure