Centerra Gold Announces Strategic Plan Including Thompson Creek Prefeasibility Study Highlights All figures are in United States dollars. All production figures reflect payable metal quantities and are on a 100%-basis, unless otherwise

Economic Studies Shareholder Letters & Outlook

1

NEWS RELEASE

Centerra Gold Announces Strategic Plan Including

Thompson Creek Prefeasibility Study Highlights

All figures are in United States dollars. All production figures reflect payable metal quantities and are on a 100%-basis, unless otherwise

stated. For references denoted with NG, refer to the “Non -GAAP and Other Financial Measures” disclosure at the end of this news

release for a description of these measures.

Toronto, Canada, September 18, 2023: Centerra Gold Inc. (“Centerra” or the “Company” ) (TSX: CG)

(NYSE: CGAU) is pleased to announce its strategic plan for each asset in the Company’s portfolio along with

the Company’s approach to capital allocation.

President and CEO, Paul Tomory, commented, “ We are excited to roll -out our strategic plan that focuses on

maximizing the value for each asset in our portfolio. The plan identifies the opportunities at each asset that will

drive future value and growth for the Company. Specifically, at Mount Milligan, we expect strong operational

performance in the next few years, and we will work to optimize operations and maximize the value of the large

deposit. At Öksüt, our life of mine plan demonstrates particularly strong production and cost performance over

the next two years with a steady gold production profile continuing throughout the life of mine . Our

prefeasibility study on the Thompson Creek molybdenum mine supports a disciplined path to restarting

operations and realizing significant vertical integration synergies with the Langeloth Metallurgical Facility.

And finally, at the Goldfield Project, we have decided to re -evaluate the project scope of work to achieve a

lower capital flowsheet and to maximize the returns on the project. Our exploration focus will now be on oxide

and transition material , with the timing of an initial resource estimate contin gent on exploration success and

metallurgical testwork.”

“In conjunction with execution of the strategic plan, we have also developed a capital allocation strategy which

focuses on returning capital to shareholders through dividends and share buybacks, investing in internal projects

and exploration within our current portfolio and evaluating external opportunities for growth. We believe that

Centerra’s exposure to gold and base metals is a differentiating factor , however, our strategic plan has us

remaining a gold -focused company . Today’s announcement provides a clear path to delivering safe and

sustainable operations and creating value for our shareholders and local stakeholders in the future.”

Mount Milligan Mine (“Mount Milligan”)

Mount Milligan’s production in the first half of 2023 was impacted by mine sequencing and lower than planned

gold grades as a result of mining in an ore-waste transition zone , which caused lower metal recoveries and

throughput challenges in the processing plant in the first quarter. The Company has completed mining in the

ore-waste transition zone in Phase 9 and is currently mining the higher-grade copper and gold zones from Phase

7 and Phase 9 in the second half of 2023.

Centerra view s Mount Milligan’s substantial resource base as a strategic asset and is advancing work on

productivity and cost efficiencies in concert with mine plan optimization to offset some of the recent inflationary

pressures that have impacted the industry. In parallel, Centerra is working to explore ways to maximize the

value of the very large mineral endowment.

2

Öksüt Mine (“Öksüt”)

As previously disclosed, Öksüt resumed full operations on June 5, 2023. In June 2023, the mine started ramping

up its crushing, stacking , and processing activities and produced 20,503 ounces during the month. Öksüt

continues to process gold-in-carbon inventory , and on July 31, 2023 Centerra issued 2023 gold production

guidance of 180,000 to 190,000 ounces.

The Company expects elevated production at Öksüt through mid -2024, as the inventory and stockpiles are

processed through the adsorption, desorption, and recovery (“ADR”) plant, at which point, the production levels

are expected to return to steady state. The life of mine (“LOM”) plan, in the table below, has been updated to

reflect the restart of operation s and other optimizations. The updated Ö ksüt LOM will generate positive free

cash flow, and the mine remains a strategic asset in Centerra’s portfolio.

Öksüt LOM Plan

Gold

Production

(Koz)

Gold

Production Costs

($/oz)

AISC on a by-

product basisNG

($/oz)

Additions to PP&E /

Total Capital

ExpendituresNG(2) ($M)

Q2 YTD 2023 20.5 $404 $1,484 $11

2023(1) 180 – 190 $450 – $500 $650 – $700 $35 – $45

2024 190 – 210 $600 – $700 $800 – $900 $30 – $40

2025 125 – 145 $725 – $825 $875 – $975 $10 – $15

2026 110 – 130 $800 – $900 $925 – $1,025 $5 – $10

2027 110 – 130 $800 – $900 $925 – $1,025 $5 – $10

2028 100 – 120 $900 – $1,000 $975 – $1,075 $0 – $5

2029 40 – 50 $1,500 – $1,600 $1,600 – $1,700 -

(1) As a result of restarting activities at Öksüt, Centerra published Öksüt guidance on July 31, 2023 in conjunction with the Company’s

second quarter 2023 results. (2) Additions to Property, Plant, and Equipment (“PP&E”) is the same as Total Capital ExpendituresNG for

full year estimates in 2023-2029.

Molybdenum Business Unit

The Molybdenum Business Unit (“MBU”) is a fully integrated business in North America with a long operating

history. The MBU consists of the Thompson Creek Mine (“Thompson Creek”) in Idaho, the Endako Mine

(“Endako”) in northern British Columbia , a joint venture in which Centerra owns a 75% in terest and the

remaining 25% is held by Sojitz Moly Resources, Inc., and the Langeloth Metallurgical Facility (“Langeloth”)

near Pittsburgh, Pennsylvania. The two mines have been in care and maintenance since late 2014 and mid-2015,

respectively, with significant infrastructure in place that is in excellent condition, while Langeloth has continued

to operate at reduced capacity processing third party concentrates and selling finished molybdenum products.

The Company has completed a prefeasibility stud y (“PFS”) on the restart of mining at Thompson Creek, with

the objective of realizing value for the MBU. A restart of Thompson Creek, vertically integrated with operations

at Langeloth, would result in a combined $373 million after-tax net present value (5%) (“NPV 5%”) and 16%

after-tax internal rate of return (“IRR”), based on a flat molybdenum price of $20 per pound.

Langeloth is among the largest molybdenum conversion plants in North America and is a unique and strategic

asset given its proximity to the North American steel market. Significant synergies and margin improvements

that will enhance future cash flow generation and profitability from the MBU will result from: (1) increased

capacity utilization at Langeloth from the current level of 30-35% to leverage fixed costs; (2) ability to blend

the high-quality Thompson Creek concentrate with lower quality third-party concentrates; and (3) ability to

produce an increased volume of higher margin final molybdenum products. Overall, the restart and integration

of Thompson Creek with Langeloth presents a n opportunity to establish a fully integrated business that can

3

leverage existing infrastructure and create long -term value through profitable operations and significant

optionality.

The Thompson Creek PFS includes an optimized mine plan with an 11-year mine life. A summary of the PFS

production profile is included in the table below.

Thompson Creek PFS Production Profile

Ore Mined

(M tonnes)

Grade

(% Mo)

Molybdenum Production

(Mlbs)

Year 1 5 0.03% 3

Year 2 – Year 3(1) 10 0.05% 11

Year 4 – Year 8(1) 9 0.07% 13

Year 9 – Year 11(1) 8 0.08% 14

Total LOM 95 0.07% 134

(1) Ore mined, grade, and molybdenum production are annual weighted averages for the stated period. NOTE: Numbers may not add

due to rounding.

The cost profile associated with the Thompson Creek PFS, shown in the table below, is split into three phases,

largely driven by the grade profile in the production table above. The average production cost breakdown over

the LOM is approximately 50% mining, 35% processing, and 15% general and administration.

Thompson Creek PFS Cost Profile

Production Costs

($/lb Mo)

AISC on a by-product basisNG

($/lb Mo)

Year 2 – Year 3 $13 – $16 $15 – $18

Year 4 – Year 8 $10 – $13 $12 – $15

Year 9 – Year 11 $7 – $10 $8 – $11

In line with the Company’s disciplined approach to capital allocation, Centerra expects to phase the operations

restart at Thompson Creek. The PFS , requiring between $350 and $400 million of pre-production capital

expenditures, includes an optimized mine design, which leads to a longer mine life and provides for greater

exposure to molybdenum price cycles. As previously disclosed with the Company’s outlook on February 23,

2023, capital spending at Thompson Creek in 2023 is expected to be $9 to $10 million associated with

advancement of project studies includi ng project de-risking activities such as geotechnical drilling, additional

engineering costs and site early works.

The Company has commenced a feasibility study (“FS”) for Thompson Creek , which is expected to be

completed by mid -2024. Upon completion of the FS, the Company expects to authorize a limited notice to

proceed, requiring $100 to $125 million of capital for pre -stripping within current authorizations and to

purchase long lead items. While the current authorizations support early works and certain activities defined in

the limited notice to proceed stage, the Company has initiated discussions with the appropriate authorities to

obtain a modified permit for the full scope of the optimized mine plan. The Company expects to authorize full

notice to proceed in mid -2025, linked to sufficient progress toward permit modification approvals for the

optimized mine plan, at which time the remaining $250 to $275 million of capital will be released to complete

the project. First production is expected in the second half of 2027. A breakdown of th e PFS capital spending

profile is included in the table below.

4

Thompson Creek PFS Capital Expenditures

Stage Expected Timeframe Additions to PP&E / Capital

ExpendituresNG(1) ($M)

Limited notice to proceed Mid-2024 to Mid-2025 $100 – $125

Full notice to proceed Mid-2025 to Mid-2027 $250 – $275

Total Pre-Production Non-Sustaining Capital ExpendituresNG $350 – $400

(1) Additions to Property, Plant, and Equipment (“PP&E”) is the same as Total Capital ExpendituresNG.

The Thompson Creek PFS and synergies at Langeloth demonstrate solid economics at flat molybdenum prices

of $20 per pound. The sensitivity of project economics due to changes in molybdenum prices is illustrated in

the table below.

Project Economics Sensitivity to Molybdenum Prices

Project

Economics

Molybdenum Price ($/pound)

$17.50 $20 (PFS price) $22.50 $25

NPV5% $153M $373M $569M $761M

IRR 10% 16% 20% 25%

Endako is expected to remain in care and maintenance as the Company focuses on the Thompson Creek restart.

Endako is an important molybdenum asset with a large defined resource in a top-tier jurisdiction, with valuable

modern plant infrastructure, providing longer-term optionality. Should Endako be restarted in the future, it

could support many years of continuous mining from Centerra’s MBU.

While Centerra remains primarily a gold mining business, the Company sees value from its exposure to base

metals. As part of the value maximizing plan for the MBU, the Company will evaluate all strategic options for

the assets.

Goldfield Project

As previously disclosed with the Company’s second quarter results on July 31, 2023, after a review of the

Goldfield Project (“Goldfield”), the Company has made the decision to re -evaluate the project scope of work

to achieve a lower capital flowsheet and to maximize returns on the project. As a result, it will now focus

exploration activities only on oxide and transition material, principally in the Gemfield and nearby deposit

areas. Due to this strategic pivot, Centerra will take additional time to perform exploration activities in

Goldfield’s large, underexplored land position before releasing an initial resource estimate. The timing for

Goldfield’s initial resource estimate will be contingent on exploration success and metallurgical testwork.

Centerra will provide an update on exploration progress at Goldfield with the Company’s third quarter 2023

results. The Company continues to believe that Goldfield presents an attractive opportunity in a top mining

jurisdiction.

Kemess

Kemess is a past producing mine located in the Toodoggone district within British Columbia’s prolific Golden

Horseshoe, a highly prospective area with multiple gold and copper discoveries. Kemess benefits from

infrastructure already on-site, including a process plant, water treatment plant, air strip, and an open pit available

for waste storage. In addition, Kemess has several permits in place and an impact benefit agreement with its

First Nation partner. Centerra’s strategic approach at Kemess is to leverage the existing infrastructure to unlock

regional potential and continue to evaluate the underground prospect of Kemess which could be a future source

of gold and copper production.

5

Capital Allocation

Centerra expects to generate significan t free cash flow in the short- and medium-term and has developed a

capital allocation strategy that focuses on three key areas: (1) returning capital to shareholders th rough

continued dividends and share buybacks ; (2) investing in internal growth projects and exploration within the

Company’s current portfolio, including the Thompson Creek restart , the Goldfield project and greenfield

exploration; and (3) evaluating external opportunities for growth. Even after accounting for these three areas of

priority, the Company expects to maintain a significant cash balance through the end of 2024 and beyond.

Exploration

Total exploration expenditures estimated for 2023 are expected to be $40 to $50 million. This includes

exploration spending at Goldfield of $16 to $20 million, $16 to $19 million on greenfield and generative

exploration projects, and $8 to $11 million on brownfield exploration. In 2023, brownfield exploration at Mount

Milligan is focused on resource expansion drilling programs within the open-pit and to the west and southwest

of the ultimate pit margins, while exploration at Öksüt will continue to test oxide gold potential at peripheral

prospects and assess potential for deeper porphyry -style copper-gold mineralization . In the next few years,

Centerra will continue to invest in exploration spending with roughly 50% of annual exploration spending

allocated to brownfield and 50% allocated to greenfield activities.

About Centerra Gold

Centerra Gold Inc. is a Canadian-based gold mining company focused on operating, developing, exploring and

acquiring gold and copper properties in North America, Türkiye, and other markets worldwide. Centerra

operates two mines: the Mount Milligan Mine in British Columbia, Canada, and the Öksüt Mine in Türkiye.

The Company also owns the Goldfield District Project in Nevada, United States, the Kemess Underground

Project in British Columbia, Canada, and owns and operates the Molybdenum Business Unit in the Un ited

States and Canada. Centerra’s shares trade on the Toronto Stock Exchange (“TSX”) under the symbol CG and

on the New York Stock Exchange (“NYSE”) under the symbol CGAU. The Company is based in Toronto,

Ontario, Canada.

For more information:

Lisa Wilkinson

Vice President, Investor Relations & Corporate Communications

(416) 204-3780

[email protected]

Shae Frosst

Manager, Investor Relations

(416) 204-2159

[email protected]

Additional information on Centerra is available on the Company’s website at www.centerragold.com

and at SEDAR at www.sedar.com and EDGAR at www.sec.gov/edgar.

Qualified Persons

Andrey Shabunin, Professional Engineer, member of Professional Engineers of Ontario and General Manager

of Öksüt Mine at Öksüt Madencilik Sanayi Ticaret A.Ş., a wholly owned subsidiary of Centerra, has reviewed

and approved the scientific and technical information under t he heading “Öksüt Mine (“Öksüt”)” in this news

6

release. Mr. Shabunin is a Qualified Person within the meaning of National Instrument 43 -101 – Standards of

Disclosure for Mineral Projects of the Canadian Securities Administrators (“NI 43-101”).

Jean-Francois St -Onge, Professional Engineer, member of the Professional Engineer of Ontario (PEO) and

Centerra’s Senior Director, Technical Services, has reviewed and approved the scientific and technical

information in this news release related to mining. Mr. St-Onge is a Qualified Person within the meaning of NI

43-101.

Lars Weiershäuser, PhD, P.Geo, and Centerra’s Director, Geology, has reviewed and approved the scientific

and technical information included in this news release related to geology and mineral reso urces. Dr.

Weiershäuser is a Qualified Person within the meaning of NI 43-101.

Anna Malevich, Professional Engineer, member of the Professional Engineers of Ontario (PEO) and Centerra’s

Senior Director, Projects has reviewed and approved the scientific an d technical information included in this

news release related to processing and metallurgy . Ms. Malevich is a Qualified Person within the meaning of

43-101.

All other scientific and technical information presented in this document was reviewed and approv ed by

Centerra’s geological and mining staff under the supervision of W. Paul Chawrun, Professional Engineer,

member of the Professional Engineers of Ontario (PEO) and Centerra’s Executive Vice President and Chief

Operating Officer. Mr. Chawrun is a Qualified Person within the meaning of NI 43-101.

Caution Regarding Forward-Looking Information:

Information contained in this document which is not a statement of historical fact, and the documents

incorporated by reference herein, may be “forward -looking information” for the purposes of Canadian

securities laws and within the meaning of the United S tates Private Securities Litigation Reform Act of 1995.

Such forward-looking information involves risks, uncertainties and other factors that could cause actual results,

performance, prospects and opportunities to differ materially from those expressed or implied by such forward-

looking information. The words "achieve", “advance”, “assume”, “anticipate”, “approach”, “believe”,

“budget”, “contemplate”, “contingent”, “continue”, “could”, “deliver”, “de-risk”, “develop”, “enhance”,

“estimate”, “evaluate”, “expand”, “expect”, “explore”, “focus”, “forecast”, “future”, “generate”,

“growth”, “in line”, “improve”, “intend”, “may”, “maximize”, “modify”, “obtain”, “offset”, “on track”,

“optimize”, “path”, “plan”, "potential", “re-evaluate”, “realize”, “remaining”, “restart”, “result”,

“schedule”, “sees”, “seek”, “strategy”, “subject to”, “target”, “test”, “understand”, “update”, “will”, and

similar expressions identify forward -looking information. These forward -looking statements relate to, among

other things: statements regarding the Company’s strategic plan for each asset in its portfolio and maximizing

the value thereof, 2023 Guidance, including production, costs, capital expenditures and cash flows; the

expected profile of the Company’s future production and costs ; expectations that the Mount Milligan Mine is

on track to access higher grades in the second half of 2023 and Mount Milligan Mine’s production will be

weighted to the back end of 2023 ; expectations of gold processing at the Öksüt Mine, including processing

Öksüt Mine’s gold in carbon inventory and gold in ore stockpiles and on the heap leach pad; strategic options

for the entire Molybdenum Business Unit ; re-evaluating the Goldfield Project including achieving a lower

capital flow sheet and maximizing returns on the project; the Company’s capital allocation strategy regarding

dividends and share buybacks; investing in internal projects and exploration within the Company’s current

portfolio; evaluating external opportunities for growth; and ongoing evaluations of a restart of the Thompson

Creek Mine, including synergies created at Langeloth its operating capacities and the use of the concentrate

from the Thompson Creek Mine, projected net present value and internal rates of return on such a restart and

receiving required permitting and authorization from the relevant authorities concerning a restart; the future

of Endako if restarted; exploration activities and metallurgical test work at the Goldfield Project; the regional

potential and underground prospects at Kemess; and the future exploration plans for the Company.

7

Forward-looking information is necessarily based upon a number of estimates and assumptions that, while

considered reasonable by Centerra, are inherently subject to significant technical, political, business, economic

and competitive uncertainties and contingencies. Known and unknown factors could cause actual results to

differ materially from those projected in the forward- looking information. Factors and assumptions that could

cause actual results or events to differ materially from current expectations include, among other things: (A)

strategic, legal, planning and other risks, including: political risks associated with the Company’s operations

in Türkiye, the USA and Canada; resource nationalism including the management of external stakeholder

expectations; the Company receiving approval for the renewal of its normal course issuer bid ; the impact of

changes in, or to the more aggressive enforcement of, laws, regulations and government practices, including

unjustified civil or criminal action against the Company, its affiliates, or its current or former employees; risks

that community activism may result in increased contributory demands or business interruptions; the risks

related to outstanding l itigation affecting the Company; the impact of any sanctions imposed by Canada, the

United States or other jurisdictions against various Russian and Turkish individuals and entities; potential

defects of title in the Company’s properties that are not known as of the date hereof; the inability of the

Company and its subsidiaries to enforce their legal rights in certain circumstances; risks related to anti -

corruption legislation; Centerra not being able to replace mineral reserves; Indigenous claims and consultative

issues relating to the Company’s properties which are in proximity to Indigenous communities; and potential

risks related to kidnapping or acts of terrorism; (B) risks relating to financial matters, including: sensitivity of

the Company’s business to the volatility of gold, copper and other mineral prices; the use of provisionally -

priced sales contracts for production at the Mount Milligan Mine; reliance on a few key customers for the gold-

copper concentrate at the Mount Milligan Mine; use of commod ity derivatives; the imprecision of the

Company’s mineral reserves and resources estimates and the assumptions they rely on; the accuracy of the

Company’s production and cost estimates; the impact of restrictive covenants in the Company’s credit facilities

which may, among other things, restrict the Company from pursuing certain business activities or making

distributions from its subsidiaries; changes to tax regimes; the Company’s ability to obtain future financing;

the impact of global financial condition s; the impact of currency fluctuations; the effect of market conditions

on the Company’s short-term investments; the Company’s ability to make payments, including any payments of

principal and interest on the Company’s debt facilities, which depends on the cash flow of its subsidiaries; and

(C) risks related to operational matters and geotechnical issues and the Company’s continued ability to

successfully manage such matters, including : the Company receiving the required authorizations and permits

for the restart of Thompson Creek; the ability of the Company to blend concentrate from Thompson Creek at

Langeloth; the stability of the pit walls at the Company’s operations; the integrity of tailings storage facilities

and the management thereof, including as to stability, compliance with laws, regulations, licenses and permits,

controlling seepages and storage of water, where applicable; the risk of having sufficient water to continue

operations at the Mount Milligan Mine and achieve expected mill throughput; ch anges to, or delays in the

Company’s supply chain and transportation routes, including cessation or disruption in rail and shipping

networks, whether caused by decisions of third -party providers or force majeure events (including, but not

limited to: labou r action, flooding, wildfires, earthquakes, COVID -19, or other global events such as wars);

the success of the Company’s future exploration and development activities, including the financial and

political risks inherent in carrying out exploration activit ies; inherent risks associated with the use of sodium

cyanide in the mining operations; the adequacy of the Company’s insurance to mitigate operational and

corporate risks; mechanical breakdowns; the occurrence of any labour unrest or disturbance and the ability of

the Company to successfully renegotiate collective agreements when required; the risk that Centerra’s

workforce and operations may be exposed to widespread epidemic or pandemic; seismic activity, including

earthquakes; wildfires; long lead-times required for equipment and supplies given the remote location of some

of the Company’s operating properties and disruptions caused by global events; reliance on a limited number

of suppliers for certain consumables, equipment and components; the ability of the Company to address

physical and transition risks from climate change and sufficiently manage stakeholder expectations on climate-

related issues; the Company’s ability to accurately predict decommissioning and reclamation costs and the

assumptions they rely upon; the Company’s ability to attract and retain qualified personnel; competition for

mineral acquisition opportunities; risks associated with the conduct of joint ventures/partnerships; and, the

8

Company’s ability to manage its projects effectively and to mitigate the potential lack of availability of

contractors, budget and timing overruns, and project resources. For additional risk factors, please see section

titled “Risks Factors” in the Company’s most recently filed Annual Information Form (“AIF” ) available on

SEDAR at www.sedar.com and EDGAR at www.sec.gov/edgar.

There can be no assurances that forward -looking information and statements will prove to be accurate, as

many factors and future events, both known and unknown could cause actual result s, performance or

achievements to vary or differ materially from the results, performance or achievements that are or may be

expressed or implied by such forward -looking statements contained herein or incorporated by reference.

Accordingly, all such factors should be considered carefully when making decisions with respect to Centerra,

and prospective investors should not place undue reliance on forward -looking information. Forward-looking

information is as of September 18, 2023. Centerra assumes no obligation to update or revise forward-looking

information to reflect changes in assumptions, changes in circumstances or any other events affecting such

forward-looking information, except as required by applicable law.

Non-GAAP and Other Financial Measures

This document contains “specified financial measures” within the meaning of NI 52-112, specifically the non-

GAAP financial measures, non -GAAP ratios and supplementary financial measures described below.

Management believes that the use of these measures assis ts analysts, investors and other stakeholders of the

Company in understanding the costs associated with producing gold and copper, understanding the economics

of gold and copper mining, assessing operating performance, the Company’s ability to generate free cash flow

from current operations and on an overall Company basis, and for planning and forecasting of future periods.

However, the measures have limitations as analytical tools as they may be influenced by the point in the life

cycle of a specific mine and the level of additional exploration or other expenditures a company has to make to

fully develop its properties. The specified financial measures used in this document do not have any

standardized meaning prescribed by IFRS and may not be comparable to similar measures presented by other

issuers, even as compared to other issuers who may be applying the World Gold Council (“WGC”) guidelines.

Accordingly, these specified financial measures should not be considered in isolation, or as a substitute for,

analysis of the Company’s recognized measures presented in accordance with IFRS.

Definitions

The following is a description of the non -GAAP financial measures, non -GAAP ratios and supplementary

financial measures used in this document:

• All-in sustaining costs on a by -product basis per ounce is a non -GAAP ratio calculated as all -in

sustaining costs on a by-product basis divided by ounces of gold sold. All -in sustaining costs on a by-

product basis is a non -GAAP financial measure calculated as the aggregate of production costs as

recorded in the condensed consolidated statements of (loss) earnings, refining and transport costs, the

cash component of capitalized stripping and sustaining capital expenditures, lease payments related to

sustaining assets, corporate general and administrative expenses, accretion expenses, asset retirement

depletion expenses, copper and silver revenue and the associated impact of hedges of by-product sales

revenue. When calculating all-in sustaining costs on a by-product basis, all revenue received from the

sale of copper from the Mount Milligan Mine, as reduced by the effect of the copper stream, is treated

as a reduction of costs incurred. A reconciliation of all-in sustaining costs on a by-product basis to the

nearest I FRS measure is set out below. Management uses these measures to monitor the cost

management effectiveness of each of its operating mines.

• Sustaining capital expenditures and Non-sustaining capital expenditures are non -GAAP financial

measures. Sustaining capital expenditures are defined as those expenditures required to sustain current

operations and exclude all expenditures incurred at new operations or major projects at existing