CERRADO GOLD REPORTS STRONG DRILL RESULTS FROM THE SERRA ALTA

DEPOSIT AT ITS MONTE DO CARMO PROJECT IN BRAZIL: HOLE FSA - 164

RETURNS 129.0 M AT 1.68 G/T.

• Concurrent ongoing programs include exploration at satellite deposits and an

infill drill program within the Serra Alta deposit (subject of this press release)

• Infill drilling focused on shallow, early mining phase zones aimed to refine

geometry of wide mineralized areas

• FSA-164 is the second-best hole received to date in terms of metal content (grade

times thickness) drilled by Cerrado at the property

TORONTO, ONTARIO - Cerrado Gold Inc. ("Cerrado" or the "Company”) (TSX.V: CERT) (OTCQX:

CRDOF) is pleased to announce further assay results from its exploratory and infill drill program

at the Serra Alta deposit at its Monte do Carmo Project (“MDC”) located in Tocantins State, Brazil.

The infill/exploratory phase started in Q2/2021 targeting further extensional areas to the known

resource for the current Serra Alta deposit and specific infill zones within the current resource.

Drill Hole Highlights by target area (all composites are reported as true thickness):

FSA-164

• 129.00 m at 1.68 g/t Au, from 15.00 m

▪ Including 2.03 m at 13.54 g/t Au from 26.02 m

▪ Including 11.06 m at 5.22 m g/t from 120.05 m

FSA-158

• 4.89 m at 1.82 g/t Au, from 422.29 m

FSA-160

• 17.70 m at 1.33 g/t Au, from 50.30 m; and

• 5.20 m at 7.29 g/t Au, from 81.27m

▪ Including 1.04 m at 34.11 g/t Au from 82.31 m

-2-

FSA-162

• 7.42 m at 1.47 g/t Au, from 71.73 m

▪ Including 1.03 m at 9.69 g/t Au from 71.73 m

FSA-167

• 4.17 m at 1.63 g/t Au, from 33.54 m

The exploration and infill phase is a continuous and ongoing program initiated immediately

after the completion of phase 1 drilling in Q2. Th at program was the bas is of the updated

resource update for Serra Alta, that currently includes 541,000 Oz’s Au of Indicated resources

and 780,000 Oz’s Au of inferred resources; and the subsequent PEA (see Press Releases from

August 4 and August 23, 2021).

Drilling in H2 2021 has focused both on the Serra Alta Deposit (the focus of this press release

and the reported results herein ) and other satellite deposits, including Capitão, Bit 3, Baru,

Fartura, Ferradura, Eldorado, Magalhaes and Sucuri where the presence of gold has been

significantly confirmed in all targets and will be the subject of an upcoming press release.

The assay results reported in this press release are exclusive to Serra Alta and immediat ely

adjacent extensional areas and were received up until December 10th, 2021, representing the

full extent of eleven diamond drill holes, totaling 2,368 m completed in Serra Alta by late

October. Further drilling into the Serra Alta deposit (pending assays) extended into December

2021.

Mark Brennan, CEO and Co-Chairman commented “We are pleased with the ongoing drill results

at Serra Alta, with results to-date supporting our view of the exceptional characteristics of the deposit.

At Serra Alta, the results once again confirm the wide continuous mineralized zones proximal to the

granitic contact. The remarkable results of hole FSA-164, in Pit Norte block, are relatively shallow and

could represent additional early high-grade material to feed into the mine plan”

Cerrado’s exploration approach at the Monte Do Carmo district continues to be a parallel

process. First to define as accurately as possible the geology and mineralization continuity and

controls of Serra Alta, the most advanced target and conceptual anchor deposit; and secondly

to use this knowledge to test the full strike of the permissive contact zone to understand the

overall district potential. Drilling on the satellite targets is ongoing.

The company is planning an extensive infill drill program for H1 2022 that aims to convert

inferred resources and f urther increase confidence on early phases of the mine plan. Results

of the drilling will be incorporated into next year’s Feasibility study.

Serra Alta Assays Results

The holes reported in this press release include six infill and five extensional holes in and

around the Serra Alta deposit. Infill holes were collared in three sectors of the deposit: Pit Sul:

FSA-160, FSA-162; Pit Norte: FSA -161, FSA 164 and FSA -167; and the Eastern zone: FSA-158.

-3-

Extensional holes were collared west of the pits that constrain the current resource (see Figure

1). Relevant results and locations are included in Tables 1 and 2 and Figure 1.

Figure 1. Location of reported holes from Serra Alta

-4-

Drill hole FSA-158 was collared at the eastern edge of the East Zone, a fault bounded block, and

successfully expanded the boundaries of the gold mineralization to a lateral extent , including

beyond the current pit margins. Additional results, including 4.89 m at 1.82 g/t Au, from 422.29

m could contribute to the potential for an underground resource.

Frequency of visible gold, wide alteration zones and high-grade zones in the proximity of the

intrusive contact confirm the exploration model that assigns special relevance to the contact

zone between the granites and the felsic volcanic.

Drill Hole FSA -161 targeted the previously undrilled north zone within the Pit Norte block, the

hole did not provide any significant strike extension within this block.

Drill holes FSA-160 and FSA -162 confirmed the shape and extent of the high-grade domains

within the pit constrained resource in the Pit Sul sector and some of the mineralized zones

further east that were constrained as potential underground resources in the recent Micon

Resource Update. Notable results include 17.70 m at 1.33 g/t Au, from 50.30 and 5.20 m at 7.29

g/t Au, from 81.27 (FSA-160); and 7.42 m at 1.47 g/t Au, from 71.73 m (FSA-162).

Drill hole FSA-164, is an exceptional hole that was collared in the central p art of the Pit Norte

block. Hole FSA -164 is Cerrado ’s second best hole (after FSA -94, reported on December 16,

2020) in terms of metal endowment , estimated by the product of the true thickness and the

grade. This hole includes 129.00 m at 1.68 g/t Au from 15 m (vertical depth of less than 10 m)

and confirms Cerrado’s exploration model that considers higher structural levels within the

granite (possible copula) in the proximity to either Quartzite or Volcanics as the most permissive

zones for wider and richer quartz/gold veining. Hole FS-164 is remarkable in terms the density

of visible gold within the sheeted veins and is especially encouraging for the conceptual mining

sequencing as it re-affirms the low strip of high-grade zones in the early years of the operation.

Cerrado believes the refinement of the geometry and increase in grade in the area around hole

FSA-164 will likely add ounces locally into the constraining updated wireframe.

Drill hole FSA-167, was also collared in Pit Norte, at the south edge of the block. Results show

several relevant intercepts starting at 2.80 m. This hole will likely contribute to additional

ounces, as it is in close proximity to the contact zone previously not fully outlined in the resource

model. Notably FSA-167 intercepted 1.05 m at 11.18 g/t Au at 65.65 m.

Cross sections for the highlighted drill holes can be found through the following link:

https://www.cerradogold.com/mdc-crosssection-152.

The remaining step out holes drilled outside the current resource pit outline , failed to provide

relevant extension of the sheeted vei n domains. Cerrado targeted mainly extensions to the

west of the current resource following structural mapping and targeting the projection of some

small artisanal mined areas.

-5-

Table 2. Serra Alta Deposit Relevant Intercepts

Target DDH From To LENGTH (m) True Width (m) Au (g/t)

FSA-158 422.29 428.70 6.41 4.89 1.82

FSA-158 includes 422.29 424.38 2.09 1.60 3.93

FSA-158 and 465.42 466.38 0.96 0.73 1.22

FSA-158 and 480.62 484.62 4.00 3.05 0.81

FSA-158 and 499.55 500.63 1.08 0.82 1.71

FSA-158 and 503.87 506.00 2.13 1.63 2.47

FSA-158 and 583.24 584.25 1.01 0.77 0.55

FSA-158 and 589.28 591.28 2.00 1.53 2.91

FSA-158 and 598.61 599.71 1.10 0.84 0.71

FSA-160 - 14.70 14.70 14.70 1.69

FSA-160 includes 11.60 14.70 3.10 3.10 6.56

FSA-160 and 25.08 32.10 7.02 7.02 1.98

FSA-160 and 39.20 40.21 1.01 1.01 1.60

FSA-160 and 46.23 47.26 1.03 1.03 0.55

FSA-160 and 50.30 68.00 17.70 17.70 1.33

FSA-160 includes 56.55 60.66 4.11 4.11 3.35

FSA-160 and 81.27 86.47 5.20 5.20 7.29

FSA-160 includes 82.31 83.35 1.04 1.04 34.11

FSA-160 and 91.59 92.64 1.05 1.05 1.03

FSA-160 and 101.05 102.14 1.09 1.09 0.40

FSA-160 and 128.44 129.48 1.04 1.04 1.78

FSA-160 and 173.48 174.52 1.04 1.04 0.85

FSA-160 and 262.09 263.20 1.11 1.11 3.31

FSA-160 and 272.61 274.66 2.05 2.05 0.33

FSA-160 and 277.70 278.75 1.05 1.05 0.34

FSA-161 124.12 130.11 5.99 5.99 0.42

FSA-162 0 4.14 4.14 4.14 0.74

FSA-162 includes 0 1.58 1.58 1.58 1.37

FSA-162 and 30.88 36.13 5.25 5.25 1.13

FSA-162 includes 32.98 35.00 2.02 2.02 2.49

FSA-162 and 71.73 79.15 7.42 7.42 1.47

FSA-162 includes 71.73 72.76 1.03 1.03 9.69

FSA-164 15.00 144.00 129.00 129.00 1.68

FSA-164 includes 17.84 19.79 1.95 1.95 4.37

FSA-164 includes 26.02 28.05 2.03 2.03 13.54

FSA-164 includes 44.61 45.61 1.00 1.00 3.73

FSA-164 includes 54.85 58.85 4.00 4.00 4.66

FSA-164 includes 62.00 65.05 3.05 3.05 2.57

FSA-164 includes 69.36 70.45 1.09 1.09 4.13

FSA-164 includes 96.00 97.02 1.02 1.02 6.56

FSA-164 includes 103.57 105.90 2.33 2.33 7.02

FSA-164 includes 120.05 131.11 11.06 11.06 5.22

FSA-164 includes 137.00 139.00 2.00 2.00 12.27

FSA-164 includes 142.00 144.00 2.00 2.00 3.80

FSA-167 2.80 3.80 1.00 1.00 0.44

FSA-167 and 10.90 12.00 1.10 1.10 1.87

FSA-167 and 17.20 20.06 2.86 2.86 1.35

FSA-167 and 30.46 31.50 1.04 1.04 0.86

FSA-167 and 33.54 37.71 4.17 4.17 1.63

FSA-167 and 40.75 48.12 7.37 7.37 0.58

FSA-167 and 51.11 53.15 2.04 2.04 2.27

FSA-167 and 65.65 66.70 1.05 1.05 11.18

FSA-167 and 73.90 74.95 1.05 1.05 0.69

FSA-167 and 80.24 84.40 4.16 4.16 0.88

FSA-167 and 104.65 110.00 5.35 5.35 0.46

FSA-167 and 112.08 119.80 7.72 7.72 1.11

FSA-167 and 123.02 124.02 1.00 1.00 2.89

FSA-165 131.13 132.15 1.02 1.02 0.32

FSA-165 215.42 216.50 1.08 1.08 0.67

FSA-168 18.78 21.87 3.09 3.09 0.83

FSA-171 No significant values

FSA-172 No significant values

FSA-177 No significant values

Step Out Infill

-6-

Composited Cut off grade: 0.3 g/t Au

Table 1. Drill Hole Collars

Hole Id Northing Easting Elevation Depth (m)

FSA-158 8810509 820732 662 644.9

FSA-160 8809593 820351 468 371.8

FSA-161 8810142 820453 468 212.3

FSA-162 8809483 820354 503 210.8

FSA-164 8809992 820426 460 236.2

FSA-165 8810489 820323 525 220.6

FSA-167 8809954 820388 459 143.8

FSA-168 8809789 820074 407 100.3

FSA-171 8809779 820251 448 51.1

FSA-172 8809780 820248 447 45.9

FSA-177 8810492 819992 401 130.4

UTM -Central Meridian -54 / Datum SAD-69

Quality Assurance and Quality Control

Analytical work was carried out by SGS Geosol International Lab (SGS). MDC sends half core samples

for sample preparation to the lab. SGS prepares samples at Goiânia (Goiás State) and Belo Horizonte

(Minas Gerais State) and at the same facility performs gold assays by fire assay (FAA505) or metallic

screen (FAASCR_150_Au-Grav), the coarse fraction of metallic screen is assayed at Belo Horizonte

and alternatively in Lima, Peru.

SGS has routine quality control procedures which ensure that every batch of samples includes three

sample repeats and at least two commercial standards and two blanks. Cerrado uses standard

QA/QC procedures, inserting Certified Reference Material (CRM) and blanks, for the drilling

program. The Reference material used are from CDN Resource Laboratories Ltd. and ITAK (Instituto

de Tecnologia August Kekulé Ltda.).

Review of Technical Information

The scientific and technical information in this press relea se has been reviewed and approved by

Sergio Gelcich ., Vice President, Exploration for Cerrado Gold Inc., who is a Qualified Person as

defined in National Instrument 43-101.

For further information please contact

Mark Brennan Nicholas Campbell, CFA

CEO and Co Chairman Director, Corporate Development

Tel: +1-647-796-0023 Tel.: +1-905-630-0148

[email protected] [email protected]

-7-

About Cerrado Gold

Cerrado Gold is a gold production and exploration company with gold production derived from its 100%

owned Minera Don Nicolas mine in Santa Cruz province, Argentina. The company is also undertaking

exploration at its 100% owned Monte Do Carmo project located in Tocantins, Brazil. For more

information about Cerrado Gold please visit our website at www.ceradogold.com

Disclaimer

NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS

DEFINED IN POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIB ILITY FOR THE

ADEQUACY OR ACCURACY OF THIS RELEASE.

This press release contains statements that constitute “forward-looking information” (collectively,

“forward-looking statements”) within the meaning of the applicable Canadian securities legislation,

All statements, other than statements of historical fact, are forward -looking statements and are

based on expectations, estimates and projections as at the date of this news release. Any statement

that discusses predictions, expectations, beliefs, plans, projections, objectives, assumptions, future

events or performance (often but not always using phrases such as “expects”, or “does not expect”,

“is expected”, “anticipates” or “does not anticipate”, “plans”, “budget”, “scheduled”, “forecasts”,

“estimates”, “believes” or “intends” or variations of such words and phrases or stating that certain

actions, events or results “may” or “could”, “would”, “might” or “will” be taken to occur or be

achieved) are not statements of historical fact and may be forward-looking statements.

Forward-looking statements contained in this press release include, without limitation, statements

regarding the business and operations of Cerrado Gold. In making the forward - looking statements

contained in this press release , Cerrado Gold has made certain assumptions, including, but not limited

to ability of Cerrado to expand its drilling program at its Minera Don Nicolás Project and

increase its resources. Although Cerrado Gold believes that the expectations reflected in forwardlooking

statements are reasonable, it can give no assurance that the expectations of any forwardlooking

statements will prove to be correct. Known and unknown risks, uncertainties, and other

factors which may cause the actual results and future events to differ materially from those

expressed or implied by such forward-looking statements. Such factors include, but are not limited

to general business, economic, competitive, political and social uncertainties. Accordingly, readers

should not place undue reliance on the forward-looking statements and information contained in

this press release. Except as required by law, Cerrado Gold disclaims any intention and assumes no

obligation to update or revise any forward-looking statements to reflect actual results, whether as a

result of new information, future events, changes in assumptions, changes in factors affecting such

forward-looking statements or otherwise.