Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

CERT.V ·

Cerrado GOLD Reports Q3 Operating Results

Production Results

-1-

November 29, 2023 www.cerradogold.com

CERRADO GOLD REPORTS Q3 OPERATING RESULTS

• Q3 Production of 10,082 Gold Equivalent Ounces (“GEO”)

• Q3 results impacted by severe weather conditions

• Operations back on track in October and November with shipments of approximately 5,600 and

5,470 GEO, respectively

• Minera Don Nicolas (“MDN”) Expansion Capital Expenditure program now largely complete

(All numbers reported in US dollars)

TORONTO, ONTARIO - Cerrado Gold Inc. (TSX.V: CERT) (OTCQX: CRDOF) (“Cerrado” or the

“Company”) announces the operational and financial results for the third quarter 2023 (“Q3/23”) at

its Minera Don Nicolas (“MDN”) gold project in Santa Cruz Province, Argentina and report s on its

ongoing activities at the Monte Do Carmo gold project (“MDC”) in Brazil. Production results at MDN

were previously released on October 24, 2023. The Company’s quarterly financial results are

reported and available on SEDAR as well as on the Company’s website (www.cerradogold.com).

Q3 2023 Minera Don Nicolas (“MDN”) Financial Highlights:

• Gold production of 10,082 GEO in Q3/23, an 11% decrease year-on-year (“yoy”).

• AISC of $1,703 per ounce during Q3/23 due to difficult operating conditions seen in the

quarter resulting in lower production rates.

• Operating performance has returned to normal in October and November, with sales of

approximately 5,600 and 5,470 GEO, respectively.

• MDN capital program now largely complete, $34.3m invested in Expansion Capital year to

date to develop heap leach facility (US$23.9m), pre-stripping of Calandrias Norte (US$5.0m)

and exploration (US$5.4m).

o Expansion program largely funded via short term notes in Argentina to be rolled over to

longer maturity.

• Production expected to ramp up into 2024, generating significant cash flows to rapidly reduce

debt levels.

• Significant opportunity to see a reduction in operating costs and increased cashflow in US

dollar terms going forward should depreciation in applicable exchange rate continue post-

election.

-2-

Mark Brennan, CEO and Chairman, stated: “While these results reflect very severe winter weather

conditions resulting in lower production in Argentina, the team at MDN has rapidly enabled us to

ramp up production while completing our capital projects and expansion plans from October. With

our initial heap leach project operating and Calandrias Norte now in production, we now look to reap

the benefits of these capital investment programs moving into 2024 through increased production

and significant operating cashflow .” He added “Post-election, we remain optimistic for a more

accommodative fiscal regime providing for significant accretion to cashflow allowing us to

restructure our debt and develop a healthy balance sheet at Cerrado.”

MDN Outlook

Going forward into Q4/2023 and 2024 , Cerrado’s MDN operations are now positioned to benefit

from the completion of its recent expansionary capital expenditure program to grow production

with its new heap leach operations, while sustaining high -grade CIL production. The Company has

invested approximately US$ 23.9m to complete the Heap Leach facilities at Las Calandrias in 2023

and US$5.0m to pre -strip Calandrias Norte to access high -grade ore for the CIL plant. Exploration

spending has totaled US$5.4m and will continue into 2024 as we continue to grow the life of mine

at MDN.

Results in October and November are already demonstrating more normalized operations as a result

of these investments, with shipments for the two months totaling approximately 11,070 GEOs. With

operations returning to normal , the Company anticipates a significant improvement in cash

generation, which should be significantly enhanced with an improved fiscal policy and a more

normalized foreign exchange regime in Argentina supporting lower operating costs in US dollar

terms. While the near -term cash generati ng profile continues to improve, the Company is also

actively working to term out the maturity of its current short term debt profile and roll a significant

amount of these obligations as is customary in Argentina.

Argentinian Currency Controls

Starting October 11, 2023, by means of Joint Resolution No. 1/23 of the certain Ministries of the

Argentinian Government, exporters of gold, silver and their concentrates were allowed to settle

their exports at a preferential exchange rate resulting from settling 75% of such exports through the

Local Exchange Market and the remaining 25% through blue chip transactions ("Mining Dollar"). The

effect of the Mining Dollar allowed for an approximate 30% depreciation of local costs in dollar terms

at MDN during the month of October. While there is an attractive Mining Dollar in place currently,

there is no certainty that such preferential rates will continue . The Company is optimistic that the

election of Javier Milei as President of Argentina, will result in positive changes to the fiscal regime

in Argentina and a reduction in or eventual removal of currency controls, which could result in a

significant improvement in company cashflows in the short to medium term.

-3-

Third Quarter 2023 Operational and Financial Performance

Q3/23 and Full Year Operational Highlights Minera Don Nicolas

The Company produced 1 0,082 GEO (“Gold Equivalent Ounces”) during the three months ended

September 30, 2023, as compared to 11, 284 GEO in the three months ended September 30, 2022.

Production was 11% lower in the three months ended September 30, 2023, due to poor weather

conditions; with flooding resulting in wet feed which then froze, impacting on throughput and lower

than expected overall head grade values.

The average quarterly gold head grade of 3.19 g/t recorded in the third quarter of 2023 represents a

Key Operating Information Unit 2023 2022 2023 2022

Operating Data

Ore Mined ktonnes 55.90 84.79 204.05 265.69

Waste Mined ktonnes 1,349.28 1,265.08 3,884.21 3,273.97

Total Mined ktonnes 1,405.18 1,349.86 4,088.26 3,539.66

Strip Ratio waste/ore 24.14 14.92 19.04 12.32

Mining rate ktpd 15.27 14.67 14.98 12.97

Ore Milled ktonnes 83.37 98.92 273.93 300.47

Head Grade Au g/t 3.19 4.40 4.25 4.16

Head Grade Ag g/t 5.16 11.58 5.29 12.10

Recovery Au % 93% 91% 89% 90%

Recovery Ag % 65% 66% 65% 64%

Mill Throughput tpd 906 1,075 1,003 1,101

Gold Ounces Produced oz 9,972 11,015 36,101 35,317

Silver Ounces Produced oz 8,809 22,418 31,665 80,841

Gold Equivalent Ounces Produced oz 10,082 11,284 36,486 36,312

Gold Ounces Sold oz 11,263 10,522 38,175 36,124

Silver Ounces Sold oz 9,071 22,355 33,662 82,995

Gold Equivalent Ounces Sold oz 11,374 10,788 38,582 37,135

Average realized price and Average realized margin

Metal Sales $ 000's 21,574 17,819 70,225 65,536

Cost of Sales $ 000's 20,270 17,721 57,712 53,633

Gross Margin from Mining Operations $ 000's 1,304 98 12,513 11,903

Average realized price per gold ounce sold (1) $/oz 1,897 1,652 1,819 1,763

Total cash costs per gold ounce sold (1) $/oz 1,689 1,461 1,349 1,268

Average realized margin per gold ounce sold (1) $/oz 207 191 470 495

Total Direct Operating Costs (1) $ 000's 17,336 13,476 44,458 38,878

Royalties and production taxes (1) $ 000's 1,691 1,897 7,037 6,938

Total Cash Costs (1) $ 000's $19,027 $15,373 $51,495 $45,816

Total direct operating costs per gold ounce sold (1) $/oz 1,539 1,281 1,165 1,076

Royalties and production taxes per gold ounce sold (1) $/oz 150 180 184 192

Total cash costs per gold ounce sold (1) $/oz $1,689 $1,461 $1,349 $1,268

AISC - Minera Don Nicolas (1) $/oz $1,703 $1,494 $1,359 $1,318

(1) This is a non-IFRS performance measure, see non-IFRS Performance Measures

Three Months Ended September Nine months ended September

Corporate Financial Highlights Unit 2023 2022 2023 2022

Financial Data

Total revenue $ 000's 21,574 17,819 70,225 65,536

Mine operating expenses $ 000's 20,270 17,721 57,712 53,633

Income from mining operations $ 000's 1,304 98 12,513 11,903

Net income (loss) $ 000's (404) (6,622) (8,270) (4,762)

Adjusted EBITDA (1) $ 000's 30 746 13,064 13,365

Operating cash flow before movements in working capital (1) $ 000's 2,314 (704) 19,349 7,280

Operating cash flow $ 000's 10,268 (600) 37,543 5,729

Cash and cash equivalents $ 000's 11,565 9,469 11,565 9,469

Working capital (deficiency) $ 000's (58,338) (6,874) (58,338) (6,874)

Capital Expenditures $ 000's 13,583 2,922 34,822 6,996

(1) This is a non-IFRS performance measure, see non-IFRS Performance Measures

Three Months Ended September Nine months ended September

-4-

28% decrease as compared to the average head grade of 4.40 g/t in the third quarter of 2022. Ore

feed to the mill was impacted by poor operating conditions during the quarter, most notably

extremely poor wet winter weather conditions followed by freezing temperatures, resulting in lower

than planned mined ore production rates and lower than planned ore grades processed through the

mill. Wet ore also reduced plant throughput . Gold recovery of 93% represents a 2% increase in

recovery as compared to 91% recorded in the third quarter of 2022. Silver recovery of 65% was 2%

lower than the silver recovery achieved in the third quarter of 2022.

Stripping at Calandrias Norte commenced during the quarter with over 1.6MM tonnes of material

moved. A further 2.7MM tonnes is to be stripped in October and November and fresh ore is set to

feed the mill from December onwards. Results in Q4 are expected to show significant improvement

and benefit from access and limited future stripping required for the Calandrias Norte material and

the further ramp up of the heap leach operations. This new pit is planned to be the primary source

of ore in 2024.

During Q 3/2023, the team continued exploration efforts to advance several greenfield and

brownfield targets with the aim of increasing mine life and expanding the overall resource

endowment, while continuing to support the move to underground mining at Paloma.

Las Calandrias Heap Leach Project

At the new Calandrias heap leach project, work continued as the operation remained in the

commissioning phase during the quarter. Initial ramp up was impacted by freezing conditions

reducing initial irrigation rates which has now been addressed. Finalization of the crushing plant has

now been completed, which should also see more consistent feed to the pad and improve overall

performance going forward. Approximately 538 ozs were produced in the quarter. Production is set

to achieve nameplate production rates from January thereafter.

Given weather production disruption in Q3/23 full production is now targeted for January 2024. The

Calandrias Heap Leach is the first step in Cerrado’s plans for growing production capacity at MDC.

All Argentinian projects continue to be funded by operating cash flow and local debt facilities.

Monte Do Carmo Project, Brazil

During Q 3/2023, the Company, together with its numerous advisors, completed the bankable

feasibility study (“FS”) announced on November 7, 2023 showing MDC to be an extremely high

quality, low-cost robust economic project. A summary of the key highlights is presented below:

Highlights

• After-Tax NPV of US$369 million and IRR of 32%

• Average annual gold production of 94,797 ounces per annum over 9 year Life of Mine

("LOM")

• Average AISC of US$711 per ounce over LOM

• Initial Capex of US$186.6 million (including US$15.8 million contingency)

• 2:1 ratio of NPV over Initial Capex

• Annual average free cash flow of $85 million over the LOM, with total cumulative after-tax

free cash flow of $562 million over LOM

-5-

• Initial Proven and Probable Reserves of 895 koz of Gold (16.8 Mt at 1.66 g/t Au)

• Updated Measured and Indicated Resources of 1,012 koz of Gold (18.4 Mt at 1.72 g/t Au) and

Inferred Resources of 66 koz of Gold (1.1 Mt at 1.95 g/t Au)

In addition, regional exploration continues on the greater project area aimed at growing the known

resources and extending the potential mine life. During the quarter, the exploration focus has been

on the Northern extension of the Serra Alta deposit, to the East of the south pit and to the north of

Gogo, as well as on testing more greenfield targets such as Divisa and Bit-3 for ongoing development.

The Preliminary License (“LP”) was issued from the Instituto Natureza do Tocantins (“NATURATINS”)

on May 29, 2023 and the License of Installation/Construction (“LI”) is expected to follow within 90 -

120 days of the LP issuance.

The Company also continues to pursue project funding from the UK Export Credit Agency (“UKEF”),

which is progressing well, and subject to successful due diligence and other review, is expected to

be completed approximately during Q3 2024.

Q3/2023 Financial Highlights

The Company generated revenue of $21.6 million for the three months ended September 30, 2023,

from the sale of 11,374 GEO at an average realized price per gold ounce sold of $1,897 and price per

silver ounce sold of $23.48. For the three months ended September 30, 2022, the Company

generated revenue of $ 17.8 million from the sale of 1 0,788 GEO. Revenue from sales of gold and

silver for the current period was higher than the three months ended September 30, 2022, due to

the higher realized price in the current period.

Cash costs per ounce sold were $1, 689 per ounce in the three months ended September 30, 2023,

as compared to cash costs per ounce sold of $1, 461 per ounce in the three months September 30,

2022, a 16% increase. The 16% increase is a result of higher consumables and material costs compared

to the third quarter of 2022, due to lower tonnage milled and processed.

Cash provided by operating activities during the third quarter ended September 30, 2023, was $10.3

million compared to cash used in operating activities of $0.6 million for the third quarter ended

September 30, 2022. Cash provided by operating activities before working capital changes in 2023

consisted of $2.3 million as compared to $ 0.7 million of cash used in operating activities before

working capital changes in 2022.

Adjusted EBITDA was $ 0.1 million in the third quarter of 2023 as compared to $ 0.7 million in the

third quarter of 2022. Current year adjusted EBITDA was lower due to higher expenses, offset by a

lower tax expense in Q3/2023.

Net loss for the three months ended September 30, 2023 was $0.4 million, as compared to a $ 6.6

million net loss for the three months ended September 30, 2022, a difference of $6.2 million. The

decrease in net loss is primarily a result of an increase in mine operating margin of $1.2 million, a

decrease in finance expense of $0.5 million, a decrease in non-cash remeasurement loss on the

secured notes and stream of $1.6 million, and an increase in general and administrative expenses of

$0.4 million recorded in the third quarter of 2023 as compared to the third quarter of 2022.

-6-

Basic and diluted loss per share for the three months ended September 30, 2023, was $0.00,

compared to the basic and diluted loss per share of $0.08 for the three months ended September 30,

2022, a $0.08 per share decrease as a result of higher mine operating margin and lower other

expenses.

Review of Technical Information

The scientific and technical information in this press release has been reviewed and approved by

Sergio Gelcich, P.Geo., Vice President, Exploration for Cerrado Gold Inc., who is a Qualified Person

as defined in National Instrument 43-101

About Cerrado

Cerrado Gold is a Toronto-based gold production, development, and exploration company focused

on gold projects in South America. The Company is the 100% owner of both the producing Minera

Don Nicolás and Las Calandrias mine in Santa Cruz province, Argentina, and the highly prospective

Monte Do Carmo development project, located in Tocantins State, Brazil. In Canada, Cerrado Gold

is developing it’s 100% owned Mont Sorcier Iron Ore and Vanadium project located outside of

Chibougamou, Quebec.

In Argentina, Cerrado is maximizing asset value at its Minera Don Nicolas operation through

continued operational optimization and is growing production through its operations at the Las

Calandrias Heap Leach project. An extensive campaign of exploration i s ongoing to further unlock

potential resources in our highly prospective land package in the heart of the Deseado Massif.

In Brazil, Cerrado is rapidly advancing the Serra Alta deposit at its Monte Do Carmo Project, through

feasibility and into production. Serra Alta is expected to be a high -margin and high -return project

with significant exploration potential on an extensive and highly prospective 82,542 hectare land

package.

In Canada, Cerrado holds a 100% interest in the Mont Sorcier Iron Ore and Vanadium Project, which

has the potential to produce a premium iron ore concentrate over a long mine life at low operating

costs and low capital intensity. Furthermore, its high grade and high purity product facilitates the

migration of steel producers from blast furnaces to electric arc furnaces contributing to the

decarbonization of the industry and the achievement of SDG goals.

For more information about Cerrado please visit our website at: www.cerradogold.com.

Mark Brennan Mike McAllister

CEO and Chairman Vice President, Investor Relations

Tel: +1-647-805-5662

[email protected]

Disclaimer

NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN POLICIES

OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.

This press release contains statements that constitute “forward -looking information” (collectively, “forward -looking

statements”) within the meaning of the applicable Canadian securities legislation, all statements, other than statements

-7-

of historical fact, are forward -looking statements and are based on expectations, estimates and projections as at the

date of this news release. Any statement that discusses predictions, expectations, beliefs, plans, projections, objectives,

assumptions, future events or performance (often but not always using phrases such as “expects”, or “does not expect”,

“is expected”, “anticipates” or “does not anticipate”, “plans”, “budget”, “scheduled”, “forecasts”, “estimates”, “believes”

or “intends” or variations of such words and phrases or stating that certain actions, events or results “may” or “could”,

“would”, “might” or “will” be taken to occur or be achieved) are not statements of historical fact and may be forward -

looking statements.

Forward-looking statements contained in this press release include, without limitation, statements regarding the

business and operations of Cerrado. In making the forward- looking statements contained in this press release, Cerrado

has made certain assumptions, including, but not limited to the expectation of production ramp up in 2024, the political

situation in Argentina, including the likelihood of changes to the fiscal and currency regimes and the potential benefits

to the Company resulting from politic al changes, the ability of MDN to fund its operations through cash flow and local

debt facilities, anticipated timing for licensing at Monte Do Carm o, time required to reach production capacity at Las

Calandrias, the future operating costs in Argentina, as well the timing of the feasibility study at Monte Do Carmo.

Although Cerrado believes that the expectations reflected in forward-looking statements are reasonable, it can give no

assurance that the expectations of any forward-looking statements will prove to be correct. Known and unknown risks,

uncertainties, and other factors which may cause the actual results and future events to differ materially from those

expressed or implied by such forward-looking statements. Such factors include, but are not limited to general business,

economic, competitive, political and social uncertainties. Accordingly, readers should not place undue reliance on the

forward-looking statements and information contained in this press release. Except as required by law, Cerrado disclaims

any intention and assumes no oblig ation to update or revise any forward -looking statements to reflect actual results,

whether as a result of new information, future events, changes in assumptions, changes in factors affecting such

forward- looking statements or otherwise.