Cerrado GOLD Reports After Tax NPV5% of US$617 Million and After Tax IRR of 94.8% FOR Its Preliminary Economic Assessment at Its Monte Do Carmo GOLD Project IN Brazil
August 23, 2021 www.cerradogold.com
CERRADO GOLD REPORTS AFTER TAX NPV5% OF US$617 MILLION AND AFTER
TAX IRR OF 94.8% FOR ITS PRELIMINARY ECONOMIC ASSESSMENT AT ITS
MONTE DO CARMO GOLD PROJECT IN BRAZIL
• Average annual gold production of 149,000 ozs over first 5 years and 131,000 ozs over LOM 8
years
• Annual Average Free cash flow of US$150 million over the first 5 years at US$1,600 Au
• Total cumulative, after tax, free cash flow estimated US$901 million over 8 years
• Average AISC of US$431/oz over the first 5 years
• Low Initial Capex of US$126 million (including US$25 million contingency)
• Payback of 1.3 years
• Further upside potential from continued exploration drilling & resource expansion
• Development program including Feasibility Study to begin immediately
PEA Summary Results
2021
$ millions $617
% 94.8%
US$/oz Au $1,600
$ millions $126
Life of Mine years 8
years 1.3
LOM average annual production koz 131.0
LOM annual tonned mined MM tonnes 2.600
$/t $33.04
US$/oz Au $583
US$/oz Au $612
Sustaining LOM Capital $ millions 13.5
LOM Stripping Ratio waste:ore 10.9:1
Royalties % 1%
$ millions $16.78
Avg Cash Cost
Avg LOM AISC
Payback time (years)
Mine Closure
PEA Summary Table
All Figures in US$ unless otherwise noted
NPI @ 5% After Tax
IRR After Tax
Long Term Gold Price (US$/troy oz.)
Initial Capex
Opex
-2-
TORONTO, ONTARIO – CERRADO GOLD (TSX.V: CERT) (OTCQX: CRDOF) ("Cerrado" or the "Company”) is
very pleased to announce the results of its new NI 43-101 Preliminary Economic Assessment (“PEA”) based
upon the recently expanded 43 -101 resources defined at the Serra Alta deposit at its Monte do Carmo gold
project in Tocantins State, Brazil. The work has been completed by GE21 Consultoria Mineral Ltda (“GE21”)
and is based upon the NI 43-101 Mineral Resource Estimate produced by MICON International dated July 21,
2021. The final PEA report is expected to be completed and available on SEDAR by the end of September
2021.
Mark Brennan, CEO of Cerrado Gold commented “We are extremely pleased with the results of the PEA. The
results demonstrate the tremendous economic potential offered by the development of the Serra Alta deposit
as the initial cornerstone operation at our Monte do Carmo project . We continue to explore Serra Alta and
regional satellite analogue deposits to determine the full potential of the Monte do Carmo gold district.” He
continued “The robust production and cash flow generation in the initial years allows for a rapid pay back and
generates significant cash flows to continue to grow the resource potential to materially extend the mine life”.
.
Project Summary
The Monte do Carmo (MDC) Gold Project is located in the state of Tocantins, Brazil; 2 kilometres east of the
town of Monte do Carmo which is 40Km from Porto Nacional (50,000 inhab itants) and 100Km from Palmas ,
the Capital of Tocantins State (250,000 inhab itants). The Serra Alta deposit has been the main focus of
exploration at the project until recently where Cerrado has drilled numerous analogue satellite deposits to
expand the existing resource . The project has g ood access to all necessary infrastructure: paved roads,
energy, a 69 kV electric power line, water supply and an international airport, and is well supported by the local
community.
Mining
The mine design is based on standard open pit mining techniques of drill, blast and haul using contract mining
to reduce upfront capital needs. Based upon the newly expanded resource, GE21 has designed a mine plan
which extracts approximately 18.5 millio n tonnes of the current resource base over an 8 -year mine life at an
average strip ratio of 6.64 for the first 5 years and 10.9 to 1 over the life of mine. The Phase I exploratory
drilling program completed earl ier this year, increased the mineral resourc es model mainly to the North and
East, resulting in the extension of the Projected Open Pit in the same direction resulting in a slightly higher
strip ratio than the prior PEA , but significantly increasing recoverable ounces. Mining will reach nominal ore
feed to mill in year 2 of approximately 2.6 million tonnes. Mining costs are estimated at US $1.70/t of material
-3-
moved which is based on current costs at other regional operations. The annual mining costs reflect adjusted
haul distances and waste/ore ratios relative to the previous PEA completed in 2020 and as shown below.
2020 Projected Pit Shell PEA GE21 2021 Projected Pit Shell PEA GE21
Metallurgy and Processing
Cerrado completed additional metallurgical test work to advance previous strong results. The a dditional
metallurgical test work, based on 300 kg samples , once again confirmed the recoverability of gold by gravity
concentration and tailing flotation followed by CIP leaching of float concentrate. The results of the test work
confirmed the metallurgical recovery of up to 98.5% of which approximately 79% is recovered by gravity. The
final leached tailings will be submitted to detox circuit before sending it to final disposal. The high percentage
of gold recovered by gravity allows for a simple design layout with limited CIP leaching capacity required, which
significantly reduces up front capital requirements . Metallurgical te st work also indicates that the waste rock
and detoxed tailings are neutral by nature, which points to very amenable disposal of mineral residues making
it easier to deploy environmentally and more affordable.
Infrastructure
The site is ideally located with access to all -weather roads, water, 69 kV electrical power grid and sufficient
power to support project development with only modest infrastructure capital expenditures to develop the
operations. In addition, the site is close to numerous large population centres to provide skilled workforce and
auxiliary services to the operation. The local municipality of Monte do Carmo , where the mine will be built ,
provides basic health services as well as schooling that can easily be improved. Porto Nacion al and the state
capital Palmas, are within 45km and 100km respectively, and can also provide comprehensive services.
Capital Costs
Upfront capital costs are estimated at US$125.9 million plus US$8.8 million working capital , and US$13.5
million of sustaining capital over the 8 year mine life. Pay back is in the order of 1.3 years with an after-tax IRR
of 94.8%. Capital costs include a 25% contingency for equipment, plant and infrastructure and assumes the
use of contract mining negating the need for the acquisition of a mining fleet given the relatively short mine life
presented with current resources.
Capital Cost
Mine and Infrastructure US$MM 10,687,666
Processing Plant US$MM 90,000,000
Contingency (25%) US$MM 25,171,917
Total 125,859,583
-4-
Operating Costs
The LOM operating costs are estimated at a total of US$ 33.04/t of ore processed (US$25.68/t over the first
five years), benefiting from the free gold in the ore – no refractory ore has been identified. Based on test work
to date, costs will benefit from the outstanding gravity recoveries which indicate a simple processing circuit
lowering overall costs. Due to the amenable characteristics of both waste rock and tailings , dry stacking and
co-disposal of tails is applicable . The overall jurisdiction and good logistics are beneficial for both labor and
consumables.
Production and Cash/ AISC Cost Profile
The chart below highlights the expected production AISC cost profile at Serra Alta as per the PEA. Production
in the early years is expected to benefit from materially higher grades and peak in year three at 193,000 ozs .
Production over the mine life averages 131,00 ozs per year but averages approximately 150,000 ozs per year
over the first five years. Similarly , cash costs are expected to average US$582/oz over the life of mine but
average only US$404/ozs over the first five years while LOM AISC will average US$612 per year and
US$431/oz over the first five years.
Production and AISC Cost Profile
Operating Costs
Mining Cost/tonne rock US$/t $1.70
Mining Costs per tonne milled US$/t $20.11
Milling Costs US$/t $11.23
G&A Costs US$/t $1.70
Total US$/t $33.04
$0.00
$200.00
$400.00
$600.00
$800.00
$1,000.00
$1,200.00
-
50
100
150
200
250
1 2 3 4 5 6 7 8
AISC US$/oz
Gold Production 000's ozs
Annual Production and All In Sustaining Costs/oz
Annual Production (000's ozs) AISC per oz (RHS)
-5-
Overall Project Economics
The Monte do Carmo project shows a potentially extremely robust economic opportunity with an after tax NPV
at 5% discount rate of US$617 million and IRR of 94.8% at a flat gold price of $1, 600/oz. Project economics
are based on a potential 8-year mine life with a 1.3-year payback period, w ith positive after -tax cash flow
commencing in Year 1. Total cumulative, after-tax free cash flow over the life of mine is estimated at US$762
million at a $1,600/oz gold price. The mine is expected to benefit from regional tax incentives in Brazil .
The chart below demonstrates the robust free cash flow generation expected, especially in the first five years
of operation. Cash flows during the first five years of production are estimated to average US$150 MM per
annum.
The chart below highlights the NPV sensitivity to changes in capital costs, various input costs and gold price
assumptions
Project Economic Summary
Average Gold Price US$/oz $1,600
NPV 5% US$MM $617
IRR % 94.8%
Average Cash Cost US$/oz $583
AISC (inlcuing closure costs) US$/oz $612
Payback years 1.3
-$200,000
-$100,000
$0
$100,000
$200,000
$300,000
$400,000
$500,000
$600,000
$700,000
$800,000
$900,000
-$200,000
-$150,000
-$100,000
-$50,000
$0
$50,000
$100,000
$150,000
$200,000
$250,000
0 1 2 3 4 5 6 7 8
Cumulative Free Cash flow
Annual Free Cash Flow
Free Cash Flow Evolution
Annual After Tax Free Cash Flow Cumulative After Tax Free Cash Flow (RHS)
-6-
Mineral Resource Estimate
The PEA is based on the current NI 43 -101 compliant Mineral Resource Estimate completed by MICON
International Limited, with an effective date of July 21, 2021. It should be noted that Mineral resources which
are not mineral reserves do not have demonstrated economic viability. It should also be noted drilling continues
at Serra Alta to further expand and upgrade the resource as the company makes plans to move towards
feasibility. In addition to Serra Alta the company is also undertak ing a more regional exploration program on
the larger Monte Do Carmo property to define potential satellite deposits which could significantly enhance the
mine life of the installed asset base
The significant addition on mineral resources and the rise on confidence l evel represented by the maiden
indicated resources are supported by the total amount of drilling invested and numerous technologies
implemented on site; Oriented cores, structural data collection, low angle rigs , electronical cloud drilling
database allows to extract the maximum information of the cores and makes the drilling program more efficient.
Table 1. Serra Alta Mineral Resource Statement – Effective Date July 21, 2021
Mining Method Cut-off Grade
(g/t Au)
Resource
Category
Tonnage
(kt)
Avg. Au
Grade (g/t)
Metal Content
(koz)
Open Pit 0.30 Indicated 9,063 1.85 539
Inferred 12,128 1.82 708
Underground 1.10 Indicated 45 1.66 2
Inferred 1,069 2.10 72
OP + UG Indicated 9,108 1.85 541
Inferred 13,197 1.84 780
200
300
400
500
600
700
800
900
81% 87% 94% 100% 106% 113% 119%
NPV (US$MM)
Sensitivity Analysis - NPV
WACC Price CAPEX
OPEX Mine OPEX Plant Exchange Rate
-7-
Estimate Notes:
1. Mineral resources were estimated by Mr. B. Terrence Hennessey, P.Geo. and Mr. Alan J. San Martin, MAusIMM (CP) of Micon
International Limited. (“Micon”), a Toronto based consulting company, independent of Cerrado Gold. Both Mr. Hennessey and
Mr. San Martin meet the requirements of a “Qualified Person” as established by the Canadian Institute of Mining, Metallurgy
and Petroleum (CIM) Definition Standards for Mineral Resources and Mineral Reserves (May 2014) (“the CIM Standards”).
2. Mineral resources are not mineral reserves and therefore do not have demonstrated economic viability.
3. The Serra Alta estimate has been completed entirely using Leapfrog Geo – EDGE software.
4. The estimate is based on a long-term gold price of US$ 1,600 per ounce and economic cut-off grades 0.30 g/t Au (Open Pit)
and 1.10 g/t (Underground).
5. Open Pit constrained resources are reported within an optimized pit shell; underground resources are reported within
continuous and contiguous shapes which lie adjacent to and below the ultimate open pit shell and interpreted to be
recoverable utilizing standard underground mining methods.
6. The mineral resource estimate has an effective date of July 21, 2021.
7. The Serra Alta gold deposit was modelled by Cerrado using a wireframe constructed based on a 0.1 g/t Au cut-off grade and a
few vein interpretations.
8. Rock density was assigned to different lithologies based on the geological and mineralization models, using calculated
average values of 2.624 g/cm3 in granite, 2.65 g/cm3 in volcanics and 2.60 g/cm3 inside mineralization wireframes.
9. Grade capping was used to control the influence of outliers in the estimate, raw assays were composited to 1.0 m and then
assessed for capping. Grade capping used throughout the deposit was 45 g/t Au for the main broad envelope and 8.0 g/t Au
for the interpreted veins.
10. The block model gold grades were estimated using the Ordinary Kriging interpolation method with searching parameters
derived from geostatistical analysis performed within the mineralization wireframes. Variogram ranges go from 90 m to 150
m in the major axis.
11. The estimate assumes a metallurgical recovery of 98.5% gold, based on completed test-work to date.
12. The estimate assumes the following costs: Mining (Pit) US$ 2.00/t, Mining (Pit Waste) US$ 1.70/t, Mining (Underground) US$
40.00/t, Processing US$10.78/t, and G&A of US$ 2.00/t.
13. The pit constrained resource is reported within an optimized pit shell that assumed a maximum slope angle of 55 degrees.
Open pit mining recovery was assumed to be 100%. Open pit dilution was assumed to be 0%. Underground mining recovery
was assumed to be 100%. Underground dilution was assumed to be 0%.
14. Micon has not identified any legal, political, environmental, or other risks that could materially affect the potential
development of the mineral resource estimate.
15. The mineral resource estimates are classified according to the CIM Standards which define a Mineral Resource as “a
concentration or occurrence of solid material of economic interest in or on the earth's crust in such form, grade or quality
and quantity that there are reasonable prospects for eventual economic extraction. The location, quantity, grade or quality,
continuity and other characteristics of a mineral resource are known, estimated, or interpreted from specific geological
evidence and knowledge including sampling.
16. The mineral resource was categorized based on the geological confidence of the deposit into inferred and indicated
categories. An inferred mineral resource has the lowest level of confidence. An indicated mineral resource has a higher level
of confidence than an inferred mineral resource. It is reasonably expected that the portions of the inferred mineral resources
could be upgraded to indicated mineral resources with additional infill drilling.
17. All procedures, methodologies and key assumptions supporting this mineral resource estimate are included in a NI 43-101F1
Technical Report which will be available at www.sedar.com.
Technical Disclosure
The reader is advised that the PEA summarized in this press release is intended to provide only an initial, high-
level review of the project potential and design options. The PEA mine plan and economic model include
numerous assumptions and the use of Inferred Mineral Resources. Inferred Mineral Resources are considered
to be too speculative to be used in an economic analysis except as allowed for by Canadian Securities
Administrators’ National Instrument 43 -101 in PEA studies. There is no guarantee the project economics
described herein will be achieved.
Cerrado Gold Inc. will within 45 days, publish a Technical Report prepared in accordance with NI 43 -101 that
documents the PEA study and supports the current disclosure.
-8-
Independent Qualified Persons
Porfírio Cabaleiro Rodriguez, Mining Engineer, BSc (Mine Eng), MAIG , director of GE21 Consultoria Mineral
Ltda and B. Terrence Hennessey , P.Geo., Vice President of MICON International Limited , are the Qualified
Persons as defined in NI 43-101 responsible for the Technical Report and are all independent of the Company.
Quality Assurance Quality Control:
The scientific and technical information in this press release has been reviewed and approved by Porfírio
Cabaleiro Rodriguez, Mining Engineer, BSc (Mine Eng), MAIG, director of GE21 Consultoria Mineral Ltda, and
B. Terrence Hennessey , P.Geo., Vice Preside nt of MICON International Limited , all of whom are Qualified
Persons as defined in NI 43-101.
About GE21
GE21 is a specialized and independent mineral consulting firm based on a multi -disciplinary technical team,
which offers services covering most project development stages in the mining sector.
The senior staff and Board of Directors have extensive technical and operational experience, based on
collaboration with relevant companies in the fields of exploration and mineral consulting in Brazil going back
to the 1980's.
GE21's services cover the entire mining cycle, from business strategies and target generation and investments
to mine closure. GE21 routinely provides services for mineral exploration, project development, geological
valuations, and resource and reserve estimation and certification according to international standards,
including JORC and NI 43- 101. In addition, GE21 also serves the mining industry by working with operators
in connection with mine planning and mine optimization, tech nical and economic studies as well as technical
audits and the application of best market practices advocated by various international codes.
For further information please contact
Mark Brennan Nicholas Campbell, CFA
CEO and Co Chairman Director, Corporate Development
Tel: +1-647-796-0023 Tel.: +1-905-630-0148
[email protected] [email protected]
About Cerrado Gold
Cerrado Gold is a public gold producer and exploration company with gold production derived from its
100% owned Minera Don Nicolás mine in Santa Cruz province, Argentina. It also owns 100% of the assets
of Minera Mariana in Santa Cruz province, Argentina. The company is also undertaking exploration at its
100% owned Monte Do Carmo project located in Tocantins, Brazil. For more information about Cerrado
Gold please visit our website at: www.cerradogold.com.
Disclaimer
NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED
IN POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR
ACCURACY OF THIS RELEASE.
This press release contains statements that constitute “forward -looking information” (collectively, “forward -
looking statements”) within the meaning of the applicable Canadian securities legislation, all statements, other
than statements of historical fact , are forward -looking statements and are based on expectations, estimates
and projections as at the date of this news release. Any statement that discusses predictions, expectations,
beliefs, plans, projections, objectives, assumptions, future events or pe rformance (often but not always using
phrases such as “expects”, or “does not expect”, “is expected”, “anticipates” or “does not anticipate”, “plans”,
“budget”, “scheduled”, “forecasts”, “estimates”, “believes” or “intends” or variations of such words and phrases