CERRADO GOLD RECEIVES PERMITS FOR THE LAS CALANDRIAS HEAP LEACH

PROJECT IN ARGENTINA

• First gold pour scheduled for end of May 2023

• Primary resource recoveries confirmed; Life of Mine extended

• Feasibility study progressing extremely well at Monte do Carmo (Brazil)

with completion targeted for May 2023; robust economics expected to

follow strong PEA

TORONTO, ONTARIO – Cerrado Gold Inc. [TSX.V: CERT][OTCQX:CRDOF] (“Cerrado” or the “Company”) is

pleased to provide an update on the progress of its development of the gold heap leach project at the

Las Calandrias deposit in Santa Cruz, Argentina (“MDN”).

As of March 3 rd, 2023 Cerrado has secured all the required environmental permits relating to the

development and operation of the Las Calandrias heap leach project. Construction work remains ongoing

with first ore expected to be stacked on the heap leach pad during April and first gold pour is scheduled

before the end of May. Please see photographs below of construction activities to date.

Additionally, metallurgical testing has confirmed gold recoveries with greater than 80% confidence from

Oxide materials with at least 70% recovery, Transition ores have at least 50% confidence and the Primary

ore has at least 36% recoveries. As a result, mine planning has been redesigned to add material from the

primary ore zone which will expand resources for production and extend the mine life. The benefits of

the higher grade in the Primary Zone will offset lower recoveries . This is i n addition , to ongoing

production from the CIL plant and the planned development of a n underground operation at Paloma

and a second heap leach operation at Martinetas later this year.

As outlined in a press release dated October 18 2022, the heap leach operation is targeted as part of the

strategic growth to increase aggregate production rates at Cerrado’s Argentina operations to 90,000 oz

per annum from the 2022 production rate of 5 3,672 oz at MDN with reductions in AISC. Production

growth and cost reductions are planned from the development of two heap leach operations ; firstly at

Las Calandrias and secondly at the Martinetas area. MDN is also expected to develop high -grade

underground Resources that are currently known and available by directly accessing the resources from

the base of the existing high-grade pits such as at Paloma.

Mark Brennan, CEO and Chairman commented “We are pleased to have been granted all the necessary

approvals to commence operations at our initial heap leach facility at Las Calandrias which reflects the high

quality of the work completed by the team on the ground at MDN. Construction is progressing extremely well

and we are now one step clos er to delivering on our production growth strategy at MDN to exploit the all

available resources more fully.”

-2-

He continued, “Development is proceeding exceptionally well at both MDN and at MDC (Brazil); we believe that

the intrinsic value creation to shareholders will be strongly evidenced by the production growth at MDN by year

end and the Feasibility Study in Brazil which is expected by the end of May.”

Monte do Carmo (“MDC”) Feasibility Study Progress

As previously released (see Press Release of February 27, 2023), all the infill drilling completed at the

Serra Alta deposit has been completed with the objective of upgrading a significant component of the

resources to the Measured and Indicated categories. Work is now focused on mine engineering, process

plant design, tailing facilities and associated infrastructure. Completion of the Feasibility Study is

expected by May 2023.

The quotational process for key operational contracts and capital equipment is well underway. Early

indications suggest both capital and operating costs are expected to be in -line with the 43 -101

Preliminary Economic Assessment, confirming expectations that Serra Alta is set to be a low capital cost

project combined with low operating cost s set to deliver robust economics as demonstrated in the

Preliminary Economic Assessment completed in 2021.

All required works for the approval of the preliminary license are progressing according to schedule and

we expect to receive said preliminary license imminently. The construction license is expected to follow

in the following months. Additionally, the Company has also initiated discussions with various financial

groups regarding Project Financing.

Photos: Las Calandrias Heap Leach pad preparation

-3-

Review of Technical Information

The scientific and technical information in this press release has been reviewed and approved by

Clinton Swemmer, P.Eng., Vice President, Technical Services for Cerrado Gold Inc., who is a Qualified

Person as defined in National Instrument 43-101.

Mark Brennan David Ball

CEO and Co Chairman Vice President, Corporate Development

Tel: +1-647-796-0023 Tel: +1-647-796-0068

[email protected] [email protected]

About Cerrado

Cerrado is a Toronto based gold production, development and exploration company focused on gold

projects in the Americas. The Company is the 100% owner of both the producing Minera Don Nicolás

-4-

mine in Santa Cruz province, Argentina, and the highly prospect ive development project, Monte Do

Carmo located in Tocantins State, Brazil.

At Minera Don Nicolas, Cerrado is maximising asset value through further operation optimization and

continued production growth. An extensive campaign of exploration is ongoing to further unlock

potential resources in our highly prospective land package.

At Monte Do Carmo, Cerrado is rapidly advancing the Serra Alta deposit through Feasibility and

production. The Serra Alta deposit Indicated Resources of 541 k . Oz of contained gold and Inferred

Resources of 780 k. ozs of contained gold. The Preliminary Eco nomic Assessment demonstrates robust

economics as well as the potential to be one of the industry’s lowest cost producers. Cerrado also holds

an extensive and highly prospective 82,542 ha land package at Monte Do Carmo.

For more information about Cerrado please visit our website at: www.cerradogold.com.

Disclaimer

This press release contains statements that constitute “forward -looking information” (collectively, “forward -

looking statements”) within the meaning of the applicable Canadian securities legislation, all statements, other

than statements of historical fact, are forward -looking statements and are based on expectations, estimates

and projections as at the date of this news release. Any statement that discusses predictions, expectations,

beliefs, plans, projections, objectives, assumptions, future events or performance (often but not always using

phrases such as “expects”, or “does not expect”, “is expected”, “anticipates” o r “does not anticipate”, “plans”,

“budget”, “scheduled”, “forecasts”, “estimates”, “believes” or “intends” or variations of such words and phrases

or stating that certain actions, events or results “may” or “could”, “would”, “might” or “will” be taken to occur or

be achieved) are not statements of historical fact and may be forward-looking statements.

Forward-looking statements contained in this press release include, without limitation, statements regarding

the business and operations of Cerrado. In making the forward - looking statements contained in this press

release, Cerrado has made certain assumptions, including, but not limited to the timing of production, rates of

production, operating costs and capital costs of the Las Calandrias project , and expectations and timing of

receipt of the preliminary license and construction license at MDC . Although Cerrado believes that the

expectations reflected in forward -looking statements are reasonable, it can give no assurance that the

expectations of any forward -looking statements will prove to be correct. Known and unknown risks,

uncertainties, and other factors which may cause the actual results and future events to differ materially from

those expressed or implied by such forward -looking statements. Such factors include, but are not limited to

general business, economic, competitive, political and social unc ertainties. Accordingly, readers should not

place undue reliance on the forward-looking statements and information contained in this press release. Except

as required by law, Cerrado disclaims any intention and assumes no obligation to update or revise any forward-

looking statements to reflect actual results, whether as a result of new information, future events, changes in

assumptions, changes in factors affecting such forward-looking statements or otherwise.