Cerrado Gold Provides Update on Its Mont Sorcier High Grade Direct Reduction Iron (DRI) Project in Quebec
Cerrado Gold Provides Update on Its Mont Sorcier High Grade Direct
Reduction Iron (DRI) Project in Quebec
• Feasibility Study completion targeted for Q2 2026
• Targeting Increased Production rate of 8 MM tpa of 67% iron concentrate in a 2-stage phased development
approach
TORONTO, Nov. 10, 2025 -- CERRADO GOLD ("Cerrado" or the "Company”) is pleased to provide an update on the progress
and anticipated changes to the development proposal for its Mont Sorcier high purity magnetite iron project located on the
traditional Cree territory of Eeyou Istchee James Bay in the municipality of Chibougamau, Quebec. Mont Sorcier is currently in
the later stages of a Feasibility Study targeted for completion in Q2 2026.
As previously announced and based on updated metallurgical testwork, the Mont Sorcier project can produce a premium 67%
iron concentrate over a long mine life. The high grade and high purity nature of the iron concentrate product deems it as a
Critical Mineral Project as outlined by the Canadian and Quebec governments. The magnetite iron mineralization allows for it
to be concentrated into high-grade low impurity material, making the product suitable for direct reduction iron (“DRI”) or pellet
feed, contributing to the decarbonization of the steel industry and the achievement of sustainable development goals.
Currently, the growth in demand for high grade DRI material is approximately 10% pa; well above the growth for the broader
iron ore market, resulting in significant price premiums relative to more standard and lower grade iron ore concentrates.
Due to its location, low strip ratio, and innate infrastructure advantages, namely availability of existing rail and Port of
Saguenay, the feasibility study is expected to demonstrate a long life mine with high margins, low operating costs, and low
capital intensity.
Mark Brennan, CEO & Co-Chairman commented: “As we progress through the different elements of the Feasibility Study, we
continue to be impressed by the significant potential of this asset to be developed into a long life, robust operation. With the
revised scope now being incorporated into the Feasibility Study, we expect the forthcoming Feasibility Study to clearly
demonstrate the project’s strong value proposition. As the results become evident to the market, we believe the inherent value
will be recognized — reflecting the project’s exceptional quality, expansion capacity, established infrastructure, competitive
cost position, and strategic role in the future of iron ore and green steel production .”
He continued, “There is a strong initiative for the Quebec and Federal governments to develop critical mineral mines in general
and the Northern Corridor of Quebec in particular. Mont Sorcier has a ready lain railway and port waiting for customers to
increase their utilization. The Mont Sorcier project appears destined to be one of the first projects ready to be developed in
this corridor.”
The Mont Sorcier magnetite iron project is now well advanced, with all technical streams required to complete the feasibility
study. As a result, several optimizations have led to changes to the project scope from the original 43-101 Preliminary
Economic Assessment dated September 8, 2022 (“PEA”). The key scope changes that are currently anticipated to be
included in the feasibility study, which is targeted for completion in Q2 2026, are as follows.
Product Grade : Previously announced test work in early 2025 confirmed the ability to produce a 67% grade iron concentrate
with combined silica and alumina below 2.3%, making the product highly desirable as low impurity and high-grade Direct
Reduction Iron (DRI) or pellet feed product in today’s marketplace. The flowsheet currently contemplates standard magnetic
separation followed by a flotation circuit to reduce the silica content to desired levels while increasing iron grade in
concentrate.
Expanded Production Rate: Based on strong market demand for high grade iron concentrates, while aiming to keep initial
capital costs low, the project is now being designed as an expanded 8 MM tpa project as compared to a 5MM tpa project in
the PEA. The revised development plan will propose the project be developed in two phases, each delivering 4 MM tpa of
concentrate production. Phase one is currently being designed to deliver an initial 4 MM tpa of concentrate production with a
further 4 MM tpa of concentrate coming online in approximately the third year of operation to bring the total annual production
rate to 8 MM tpa of high grade, 67% iron concentrates. The phased approach to development has been contemplated in the
context of rising capital costs in the market and strong product demand from the steel industry. The final schedule will be
determined in the Feasibility Study to optimize overall project value.
Optimized Capital Costs: Phase 1 capital costs are expected to increase by approximately 30-40% relative to the PEA.
Higher costs relative to the PEA can be attributed to revised flow sheet design, the staged development plan, as certain
infrastructure will be built to accommodate the 8 MM tpa expanded production rate in the initial phase, and overall industry
wide inflation. Phase 2 would then be expected to be significantly lower as key infrastructure such as the tailing facilities,
railway, offices and other core facilities would already be in place.
Resource Definition: Over the past several months, the Company has completed 17,890 metres of resource definition with
core logging completed and some assays still pending. The results are expected to support an updated Mineral Resource
Estimate, which will then be used to support the definition of Mineral Reserves to be incorporated into the mine plan as part of
the overall feasibility study. Despite the increase in production rates, the Company still anticipates the mine life of the
expanded operation to be approximately 20 years, although no assurance can be provided before the updated mineral resource
estimate is completed. The Mont Sorcier ore body remains large and homogenous, and significant additional resources remain
available for future upgrading to extend the mine life or for future expansion potential if desired.
Optimized Low Impact Site Layout – In response to the planned scope changes and feedback from Indigenous land users
and local stakeholders, the location of key infrastructure is being optimized to minimize the impact on wetlands, fish habitats
and reduce overall visual impacts from the surrounding areas.
Environmental Permitting Progress – Progress on collecting all required information to complete the Environmental and
Social Impact Assessment remains ongoing, with the governmental environmental review process now underway. Considering
the revised footprint, the completion and submission of the ESIA is now expected in Q4 2026. The Company is encouraged
by the efforts being undertaken by the governments of Quebec and Canada to streamline the review and approval of this type of
submission, while ensuring that environmental standards are fully respected. The Company remains confident that the overall
timeline to potential construction commencing in mid-2028 remains on track, subject to receipt of necessary permitting and
availability of project financing.
Review of Technical Information
The scientific and technical information in this press release has been reviewed and approved by Andrew Croal, P.Eng., Chief
Technical Officer for Cerrado Gold, who is a Qualified Person as defined in National Instrument 43-101.
About Cerrado
Cerrado Gold is a Toronto-based gold production, development, and exploration company. The Company is the 100% owner of
the producing Minera Don Nicolás and Las Calandrias mine in Santa Cruz province, Argentina. In Portugal, the Company holds
an 80% interest in the highly prospective Lagoa Salgada VMS project through its position in Redcorp - Empreendimentos
Mineiros, Lda. In Canada, Cerrado Gold is developing its 100% owned Mont Sorcier Iron project located in the city of
Chibougamau, Quebec.
In Argentina, Cerrado is maximizing asset value at its Minera Don Nicolas ("MDN") operation through continued operational
optimization and is growing production through its operations at the Las Calandrias heap leach project. An extensive campaign
of exploration is ongoing to further unlock potential resources in our highly prospective land package in the heart of the
Deseado Masiff.
In Portugal, Cerrado is focused on the development and exploration of the highly prospective Lagoa Salgada VMS project
located on the prolific Iberian Pyrite Belt in Portugal. The Lagoa Salgada project is a high-grade polymetallic project,
demonstrating a typical mineralization endowment of zinc, copper, lead, tin, silver, and gold. Extensive exploration upside
potential lies both near deposit and at prospective step-out targets across the large 7,209-hectare property concession.
Located just 80km from Lisbon and surrounded by exceptional infrastructure, Lagoa Salgada offers a low-cost entry to a
significant development and exploration opportunity, already showing its mineable scale and cashflow generation potential.
In Canada, Cerrado is developing its 100% owned Mont Sorcier high-purity, high-grade, Direct Reduced Iron project, located on
the traditional Cree territory of Eeyou Istchee James Bay in the municipality of Chibougamau. The Mont Sorcier high purity
high grade DRI Iron project, which has the potential to produce a premium iron concentrate over a long mine life at low
operating costs and low capital intensity. Furthermore, its high grade and high purity product facilitates the migration of steel
producers from blast furnaces to electric arc furnaces, contributing to the decarbonization of the industry and the achievement
of sustainable development goals.
For more information about Cerrado please visit our website at: www.cerradogold.com.
Mark Brennan
CEO and Chairman
Mike McAllister
Vice President, Investor Relations
Tel: +1-647-805-5662
Disclaimer
NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN
POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF
THIS RELEASE.
This press release contains statements that constitute “forward-looking information” (collectively, “forward-looking
Mont Sorcier Project, Quebec, Canada
Image of Mont Sorcier in Quebec, Canada
statements”) within the meaning of the applicable Canadian securities legislation. All statements, other than statements of
historical fact, are forward-looking statements and are based on expectations, estimates and projections as at the date of this
news release. Any statement that discusses predictions, expectations, beliefs, plans, projections, objectives, assumptions,
future events or performance (often but not always using phrases such as “expects”, or “does not expect”, “is expected”,
“anticipates” or “does not anticipate”, “plans”, “budget”, “scheduled”, “forecasts”, “estimates”, “believes” or “intends” or
variations of such words and phrases or stating that certain actions, events or results “may” or “could”, “would”, “might” or “will”
be taken to occur or be achieved) are not statements of historical fact and may be forward-looking statements.
Forward-looking statements contained in this press release include, without limitation, statements regarding the business and
operations of Cerrado and the Company’s assessment and expectations regarding the Mont Sorcier Project (the “Project”),
including but not limited to the anticipated grade of iron concentrate and low impurity of material derived from the Project, the
expectation of a long mine life of the Project of approximately 20 years with high margins, low operating cost and low capital
intensity resulting in an attractive overall value proposition, initiatives being undertaken by the provincial government of
Quebec and the federal government of Canada to develop critical mineral mines, the anticipated initial and expanded
throughput rates, the anticipated capital cost of the Project, the expectation of an updated mineral reserve and life of mine,
the expectation of an optimized low impact site layout to minimize impact on wetlands fish habitats and overall visual impact,
the anticipated date of completion of a the feasibility study and commencement of construction. In making the forward-
looking statements contained in this press release, Cerrado has made certain assumptions. Although Cerrado believes that
the expectations reflected in forward-looking statements are reasonable, it can give no assurance that the expectations of any
forward-looking statements will prove to be correct. Known and unknown risks, uncertainties, and other factors which may
cause the actual results and future events to differ materially from those expressed or implied by such forward-looking
statements. Such factors include, but are not limited to general business, economic, competitive, political and social
uncertainties. Accordingly, readers should not place undue reliance on the forward-looking statements and information
contained in this press release. Except as required by law, Cerrado disclaims any intention and assumes no obligation to
update or revise any forward-looking statements to reflect actual results, whether as a result of new information, future events,
changes in assumptions, changes in factors affecting such forward-looking statements or otherwise.
A photo accompanying this announcement is available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/eb843015-e8a6-41a3-bbc9-77a991c7b51e