CERRADO GOLD ANNOUNCES Q4 AND ANNUAL 2024 GOLD PRODUCTION RESULTS FOR ITS

MINERA DON NICOLAS MINE IN ARGENTINA

• Annual Gold Equivalent Ounce (“GEO”) Production of 54,494 GEO; in line with

Guidance of 50,000 – 60,000 GEO.

• Q4 Production of 10,431 GEO impacted by lower than planned ore grades from

residual open pits.

• Record Production of 5,956, GEO from Heap Leach operations during the quarter.

• Received Asset Sale and Option payments totaling $34 MM during the quarter,

significantly strengthening the balance sheet.

• 2025 Production Guidance of between 50,000-55,000 GEO.

TORONTO, ONTARIO - Cerrado Gold Inc. [TSX.V: CERT][OTCQX: CRDOF] (“Cerrado” or the

“Company”) announces production results for the fourth quarter ended December, 2024 (“Q4

2024”) from the Minera Don Nicolas Mine in Santa Cruz Province, Argentina (“MDN”). Full fourth

quarter financial results are expected to be released prior to April 30, 2025.

Q4 Operating Highlights

• Q4 Production of 10,431 GEO vs 16,604 GEO in Q3.

• Annual Sales of 51,694 GEO for 2024

• Production impacted by lower than planned feed grade to the CIL plant during the

quarter as mining of high-grade pits nears completion.

• Studies to commence underground operations at Paloma in H2/25 initiated during

the quarter.

• Focus remains on ramping up crushing capacity at Calandrias Sur and bringing heap

leach production up to 4,000- 4,500 GEO per month by March 2025.

While operational results for Q 4 2024 demonstrated a decrease in production over the previous

quarter, this was driven by lower than expected ore grades delivered from the final stages of mining

of the older high grade open pits and stockpiles to feed the CIL plant as the Company’s operations

transition to a primarily heap le ach operation in 2025. The heap leach operation al performance

continued to improve over the quarter, reaching record production leve ls as more ore was added

to the pad. The performance of the heap leach continues to depend on the crushing circuit . A n

additional secondary crushing circuit is currently being installed to ensure excess capacilty is in place

to support the transition to a heap leach only facility . Once fully operational, the crushing capacity

should allow for approximately 300,000 tonnes of ore to be place d on the pad per month. The

-2-

installation of the secondary crusher is expected to reduce fleet and operating costs and is expected

to operate at full capacity by the end of the 1st quarter, at which time the mobile crushers will be

placed on stand by.

In addition, the company is undertaking detailed analysis and preparations for equipment sourcing

with the view to commencing underground operations later this year beneath the Palmoa pit. While

the initial production expectations are relatively modest given the current know n underground

resource, underground access is expected to provide a platform for major exploration activities at

lower costs than drilling from surface with the aim to materially expand the resources available for

underground development . Further details will be released once finalized and a de velopment

decision is made.

The Company provides 2025 annual production guidance of between 5 0,000 – 55,000 GEO at an

ASIC of between $1,300 - $1,500 per GEO. The bulk of this production is expected to be delivered

solely from heap leach operations from Q2/25 onwards .

Mont Sorcier Update

At the Mont Sorcier high purity iron project , detailed metallurginal testwork and flow sheet design

continued during the quarter . As announced in early December 2024 (see press r elease dated

December 4, 2024) testwork has reaffirmed the potential to produce high grade and high purity iron

concentrate grading in excess of 67% iron with silica and alumina below 2.3%. Ongoing testwork is

focused on flotation testing, more detailed variability tests, grind size and reagent optimization

programs as well as equipment sizing.

Current testwork and overall process design are to be at the core of the NI 43 -101 Bankable

Feasibility Study ("BFS") which is targeted to be completed by the end of Q1 2026. The Bankable

Feasibility Study will look to provide greater detail into the potential of the project that was

highlighted in the previous 2022 NI 43-101 Preliminary Economic Assessment ("PEA") that delivered

a project NPV8% of US$1.6 Billion based upon iron concerates grading 65% iron.

Corporate Activities

The Company has also continued to make progress on improving its working capital position during

the quarter with the recepit of a total of US$34 million from asset sales and the sale of an option on

the Michelle properties at MDN. As a result , the company has now significantly strengthened its

balance sheet and expects to continue to deliver further deleveraging during 2025. Future payments

from the Brazilian Monte do Carmo asset sale totalling US$15 million as well as a further US$ 10

million, should the Michelle Option be excersised, would continue to add to the Company’s strong

cash position moving forward.

Mark Brennan, CEO and Chairman commented, "While 2024 was a year with significant challenges,

we are pleased to have achived gold production in line with our guidance for the year, supported by

strong growth in production from the heap leach as the year progressed . With the new crushing

circuit currently being installed , we expect this trend to continue to support production targets for

2025 while we review the potential to add additional production from a potential underground

operation at Paloma. Further testwork at our Mont Sorcier project in Quebec continues to highlight

the significant upside we see in this project as we work to unlock value with the completion of a

feasibility study by Q1/2026 . Cerrado is exiting the year with a signifigantly improved working

capital position, placing Cerrado in a stronger financial position heading into 2025. ”

-3-

Table 1. Key Operating Information

Note : Q1-Q3 2024 Ore mined for Heap Leach Operations has been adjusted to reflect a recalcualation based on

updated information. This has no impact on ounces produced.

Review of Technical Information

The scientific and technical information from Minera do n Nicolas in this press release has been

reviewed and approved by Cid Bonfim, P. Geo., Senior Geologist Cerrado Gold , and Pierre Jean

LaFleur, P. Geo., VP Exploration for Voyager Metals, a 100% owned subsidiary of Cerrado Gold, are

Qualified Persons as defined in National Instrument 43-101.

About Cerrado

Cerrado Gold is a Toronto-based gold production, development, and exploration company focused

on gold projects in South America. The Company is the 100% owner of both the producing Minera

Don Nicolás and Las Calandrias mine in Santa Cruz province, Argentina . In Canada, Cerrado Gold is

developing it's 100% owned Mont Sorcier Iron Ore and Vanadium project located outside of

Chibougamou, Quebec.

In Argentina, Cerrado is maximizing asset value at its Minera Don Nicolas operation through

continued operational optimization and is growing production through its operations at the Las

Operating Data Unit Q1 2024 Q2 2024 Q3 2024 Q4 2024

High Grade CIL Operations

Ore Mined ktonnes 375 303 85 58 43 31 218

Waste Mined ktonnes 4,530 4,043 2,099 1,083 1,235 610 5,027

Total Mined ktonnes 5,223 4,409 2,184 1,142 1,278 641 5,245

Strip ratio waste/ore 12.08 13.33 24.61 18.56 28.44 19.87 23.08

Mining rate tpd 14,311 12,079 24,264 12,546 13,896 6,966 14,369

Ore Milled Ktonnes 395 367 90 66 99 93 348

Head Grade Au g/t 4.56 4.59 3.65 7.08 4.58 1.48 3.99

Head Grade Ag g/t 10.97 5.59 10.21 12.86 7.86 8.13 9.49

Recovery Au % 91.6% 90.4% 87.6% 91.2% 91.9% 89.9% 90.4%

Recovery Ag % 63.3% 62.1% 55.7% 53.8% 62.5% 64.4% 58.8%

Mill Throughput tpd 1,082 1,006 1,001 725 1,072 1,010 952

Gold ounces produced oz 52,504 50,658 9,879 13,648 13,022 4,312 40,861

Silver equivalent ounces produced oz 1,167 492 193 187 179 163 722

Gold Geo Produced oz 53,672 51,150 10,072 13,835 13,201 4,475 41,583

Heap Leach Operations

Ore Mined ktonnes 560 144 207 365 563 1,280

Waste Mined ktonnes 1,115 519 708 885 1,103 3,215

Total Mined ktonnes 1,675 663 915 1,250 1,666 4,494

Strip ratio waste/ore 1.99 3.60 3.42 2.43 1.96 2.51

Mining rate tpd 6,839 7,369 10,058 13,583 18,112 12,313

Ore PAD Feed Ktonnes 446 231 285 434 588 1,538

Head Grade Au g/t 0.52 0.59 0.85 0.75 0.73 0.73

Head Grade Ag g/t 4.54 9.82 12.39 10.04 9.96 10.41

Recovery Au % 13.4% 25.4% 29.4% 31.2% 40.9% 33.8%

Recovery Ag % 2.6% 3.5% 9.1% 9.1% 14.6% 10.3%

PAD Throughput tpd 4,927 2,565 3,134 4,715 6,394 4,214

Gold ounces produced oz 1,057 1,103 2,290 3,253 5,631 12,277

Silver equivalent ounces produced oz 23 29 130 150 325 633

Gold Geo Produced oz 1,080 1,132 2,420 3,403 5,956 12,911

Consolidated Gold Produciton

Gold Geo Produced oz 53,672 52,230 11,204 16,255 16,604 10,431 54,494

Gold Geo Sold oz 51,923 54,100 10,331 15,775 15,844 9,744 51,694

Average realized price per gold ounce sold $/oz 1,742 1,849 1,970 2,199 2,329 2,377 2,226

Key Operating Information

Jan to Dec,

2022

Jan to Dec,

2023

2024 Jan to Dec,

2024

-4-

Calandrias Heap Leach project. An extensive campaign of exploration is ongoing to further unlock

potential resources in our highly prospective land package in the heart of the Deseado Masiff.

In Canada, Cerrado holds a 100% interest in the Mont Sorcier Iron Ore and Vanadium project, which

has the potential to produce a premium iron ore concentrate over a long mine life at low operating

costs and low capital intensity. Furthermore, its high grade and high purity product facilitates the

migration of steel producers from blast furnaces to electric arc furnaces , contributing to the

decarbonization of the industry and the achievement of SDG goals.

For more information about Cerrado please visit our website at: www.cerradogold.com.

Mark Brennan

CEO and Chairman

Mike McAllister

Vice President, Investor Relations

Tel: +1-647-805-5662

[email protected]

Disclaimer

NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS

DEFINED IN POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE

ADEQUACY OR ACCURACY OF THIS RELEASE.

This press release contains statements that constitute “forward -looking information” (collectively,

“forward-looking statements”) within the meaning of the applicable Canadian securities legislation.

All statements, other than statements of historical fact , are forward -looking statements and are

based on expectations, estimates and projections as at the date of this news release. Any statement

that discusses predictions, expectations, beliefs, plans, projections, objectives, assumptions, future

events or performance (often but not always using phrases such as “expects”, or “does not expect”,

“is expected”, “anticipates” or “does not anticipate”, “plans”, “budget”, “scheduled”, “forecasts”,

“estimates”, “believes” or “intends” or variations of such words and phrases or stating that certain

actions, events or results “may” or “could”, “would”, “might” or “will” be taken to occur or be

achieved) are not statements of historical fact and may be forward-looking statements.

Forward-looking statements contained in this press release include, without limitation, statements

regarding the business and operations of Cerrado, production forecasts and estimated ASIC for 2025

and beyond, the potential for additional crushing capacity that may be added and the performance

of the heap leach pad, the possibility of commencing underground mining, the potential to produce

iron concentrate grading in excess of 67% at Mont Sorcier, further deleveraging during 2025, receipt

of the deferred closing payment of US$15 million in connection with the asset sale and the likelihood

of the Michelle option being exercised and the related option payment being received . In making

the forward - looking statements contained in this press release, Cerrado has made certain

assumptions. Although C errado believes that the expectations reflected in forward -looking

statements are reasonable, it can give no assurance that the expectations of any forward -looking

statements will prove to be correct. Known and unknown risks, uncertainties, and other factors which

-5-

may cause the actual results and future events to differ materially from those expressed or implied

by such forward -looking statements. Such factors include, but are not limited to general business,

economic, competitive, political and social uncertainties . Accordingly, readers should not place

undue reliance on the forward -looking statements and information contained in this press release.

Except as required by law, Cerrado disclaims any intention and assumes no obligation to update or

revise any forward -looking statements to reflect actual results, whether as a result of new

information, future events, changes in assumptions, changes in factors affecting such forward -

looking statements or otherwise.

.