Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

CERT.V ·

Cerrado GOLD Announces Q4 and Annual 2023 GOLD Production Results FOR Its Minera Don Nicolas MINE IN Argentina

Production Results

2

January 24, 2024 www.cerradogold.com

CERRADO GOLD ANNOUNCES Q4 AND ANNUAL 2023 GOLD PRODUCTION RESULTS FOR

ITS MINERA DON NICOLAS MINE IN ARGENTINA

TORONTO, ONTARIO - Cerrado Gold Inc. [TSX.V: CERT][OTCQX: CRDOF] "Cerrado" or the

"Company") announces production results for the fourth quarter of 2023 ("Q4 2023") from the

Minera Don Nicolas Mine in Santa Cruz Province, Argentina ("MDN"). Full financial results are

expected to be released in late April 2024.

Q4 Operating Highlights

• Q4 2023 GEO production of 15,202 ounces and annual GEO production of 51,688 ounces

for 2023.

• Ramp-up of production from the Las Calandrias heap leap project continues; commercial

production delayed to end of Q1 2024.

• Pre-strip at Calandrias Norte largely complete and higher-grade ore beginning to feed the

mill.

• Major capital programs at MDN complete, with current focus on delivering cashflow,

rebuilding the balance sheet and longer-term exploration and mine life extension.

Operational results presented for Q4 2023 continued to be impacted by the slower than expected

ramp-up of the Calandrias Heap Leach project during the quarter while a new crushing system was

installed. The crushing unit is now operational, and mining rates are reaching planned capacity.

Production is set to ramp-up over the first quarter of 2024 and achieve nameplate production

rates from April thereafter. At Calandrias Norte, stripping activities were largely completed during

the quarter and the pit is now beginning to deliver ore to the CIL plant at Martinetas. Ore is

expected to fill the mill by mid-February onward. Head grades from Calandrias Norte are

reconciling well with the model and grades are expected to increase as early benches are mined

and deeper, higher grade levels accessed.

While production levels have begun to improve, the delay in the ramp up of the heap leach

operations, the costs associated with stripping at Calandrias Norte and debt repayment associated

with capital projects have had an impact on the financial performance at MDN. Newly introduced

fiscal policies that have resulted in hyper-inflation have also had a significant impact on the

operations of the business particularly as suppliers react to the new fiscal regime in Argentina.

-2-

Mark Brennan, CEO and Chairman commented, "While the second half of the year has been

challenging starting with unusually harsh winter conditions in August resulting in a slower ramp up

at the heap leach, we see operations at MDN positioned to turn the corner in February as we

access higher grade ore from Calandrias Norte and the leach cycle at Las Calandrias normalizes.

That said, recent changes to fiscal policies in Argentina have resulted in a highly inflationary

environment, impacting operations as costs have increased and suppliers have reduced payment

terms. The focus at MDN will move to generating cashflow from our capital investments in 2023

that allow us to rebuild the balance sheet and refocus our efforts on exploration and increasing the

overall life of mine at MDN."

Stripping at Calandrias Norte continued during the quarter. The Pre-Strip is now largely complete

allowing for fresh ore to fully feed the mill.

Ore milled increased during the fourth quarter as operations normalized. Production rates

improved in Q4 as the operating environment returned to normal. However, additional gold

production expected from the heap leach has been limited in the 4th quarter as irrigation was

paused to allow for the completion of the installation of the new crushing circuit. Total production

from the heap leach in the 4th quarter was 531 ounces. Please see Table 1. for a summary of key

highlights for the fourth quarter and full year 2023. Sales for the quarter were slightly higher than

production due to timing differences.

Ongoing work to optimize mine sequencing and exploration work to upgrade and define new

sources of resources remains the key focus of development at MDN. The operations team is

focused on numerous new growth projects aside from expanding current open pit resources,

including the completion of the ramp up of Las Calandrias Heap Leach operation and the review of

a potential new Heap Leach operation at Martinetas.

Table 1. Key Operating Information

-3-

Monte Do Carmo Update

At the Company's Monte Do Carmo ("MDC") project in Brazil, as announced on December 15th,

Cerrado filed its 43-101 Updated Feasibility Study Technical Report for MDC ("FS") with an

updated After-Tax NPV5% of US$390 Million and IRR of 34%. A Summary of the results of the FS are

summarized in Table 1. Below. The License of Installation/Construction ("LI") is expected to be

granted during the Q1 2024.

Table 1.

Summary of Key Results and Overall Project

Economics Production Units Value

Steady State Throughput Mtpa 1.92

Average Annual Production K oz per annum 95,212

Life of Mine Years 9.0

Life of Mine Au Recovery % 95.64

Total Ore Mined - Open Pit Mt 14.3

LOM Average Stripping Ratio x 7.84

Total Ore Mined - Underground Mt 2.5

Total Recovered Gold (Payable) Ounces 856,905

Operating Costs Units Value

Mining US$/tonne 17.01

Processing US$/tonne 9.11

Water and Tailings Management US$/tonne 1.45

G&A US$/tonne 2.21

Total Cash Costs US$/oz 583.7

AISC US$/oz 686.6

Capital Expenditure Units Value

Initial Capital US$ M 165.6

Contingency US$ M 15.8

Total Upfront Capital US$ M 181.4

Sustaining Capital US$ M 66.0

Closure Costs US$ M 15

Total Capital US$ M 262.4

Financial Results Units Value

Pre-Tax NPV US$ M 466

Pre-Tax IRR % 37

Pre-Tax Payback Period Years 2.0

After Tax NPV US$ M 390

After Tax IRR % 34

-4-

After Tax Payback Period Years 2.1

Assumptions Units Value

Gold Price US$/oz 1,750

Discount Rate % 5.0

Review of Technical Information

The scientific and technical information in this press release has been reviewed and approved by

Sergio Gelcich, P.Geo., Vice President, Exploration for Cerrado Gold Inc., who is a Qualified Person

as defined in National Instrument 43-101.

About Cerrado

Cerrado Gold is a Toronto-based gold production, development, and exploration company focused

on gold projects in South America. The Company is the 100% owner of both the producing Minera

Don Nicolás and Las Calandrias mine in Santa Cruz province, Argentina, and the highly prospective

Monte Do Carmo development project, located in Tocantins State, Brazil. In Canada, Cerrado Gold

is developing it's 100% owned Mont Sorcier Iron Ore and Vanadium project located outside of

Chibougamou, Quebec.

In Argentina, Cerrado is maximizing asset value at its Minera Don Nicolas operation through

continued operational optimization and is growing production through its operations at the Las

Calandrias Heap Leach project. An extensive campaign of exploration is ongoing to further unlock

potential resources in our highly prospective land package in the heart of the Deseado Masiff.

In Brazil, Cerrado is rapidly advancing the Serra Alta deposit at its Monte Do Carmo Project,

through feasibility and into production. Serra Alta is expected to be a high-margin and high-return

project with significant exploration potential on an extensive and highly prospective 82,542

hectare land package.

In Canada, Cerrado holds a 100% interest in the Mont Sorcier Iron Ore and Vanadium Project,

which has the potential to produce a premium iron ore concentrate over a long mine life at low

operating costs and low capital intensity. Furthermore, its high grade and high purity product

facilitates the migration of steel producers from blast furnaces to electric arc furnaces contributing

to the decarbonisation of the industry and the achievement of SDG goals.

For more information about Cerrado please visit our website at: www.cerradogold.com.

Mark Brennan Mike McAllister

CEO and Chairman Vice President, Investor Relations

Tel: +1-647-805-5662

[email protected]

Disclaimer

-5-

NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS

DEFINED IN POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE

ADEQUACY OR ACCURACY OF THIS RELEASE.

This press release contains statements that constitute "forward-looking information" (collectively,

"forward-looking statements") within the meaning of the applicable Canadian securities

legislation, all statements, other than statements of historical fact, are forward-looking statements

and are based on expectations, estimates and projections as at the date of this news release. Any

statement that discusses predictions, expectations, beliefs, plans, projections, objectives,

assumptions, future events or performance (often but not always using phrases such as "expects",

or "does not expect", "is expected", "anticipates" or "does not anticipate", "plans", "budget",

"scheduled", "forecasts", "estimates", "believes" or "intends" or variations of such words and

phrases or stating that certain actions, events or results "may" or "could", "would", "might" or

"will" be taken to occur or be achieved) are not statements of historical fact and may be forward-

looking statements.

Forward-looking statements contained in this press release include, without limitation, statements

regarding the business and operations of Cerrado. In making the forward- looking statements

contained in this press release, Cerrado has made certain assumptions, including, but not limited to

the ramp-up of the Calandrias Heal Leach project, stripping activities and head grades at

Calandrias Norte, expectations regarding MDN operations and financial performance generally,

and expectations regarding permitting at Monte Do Carmo including granting of the LI. Although

Cerrado believes that the expectations reflected in forward-looking statements are reasonable, it

can give no assurance that the expectations of any forward-looking statements will prove to be

correct. Known and unknown risks, uncertainties, and other factors which may cause the actual

results and future events to differ materially from those expressed or implied by such forward-

looking statements. Such factors include, but are not limited to general business, economic,

competitive, political and social uncertainties. Accordingly, readers should not place undue reliance

on the forward-looking statements and information contained in this press release. Except as

required by law, Cerrado disclaims any intention and assumes no obligation to update or revise any

forward-looking statements to reflect actual results, whether as a result of new information, future

events, changes in assumptions, changes in factors affecting such forward-looking statements or

otherwise.