Cerrado GOLD Announces Q1 GOLD Production Results FOR Its Minera Don Nicolas MINE IN Argentina

Production Results

2

April 30, 2024 www.cerradogold.com

CERRADO GOLD ANNOUNCES Q1 GOLD PRODUCTION RESULTS FOR ITS MINERA DON

NICOLAS MINE IN ARGENTINA

• Calandrias Norte production in March driving improved production growth.

• Focus for 2024 remains on delivering strong cash flow and rebuilding the balance sheet

with exploration focused on mine life extension.

• Management currently developing a longer-term production plan for Argentina.

TORONTO, ONTARIO - Cerrado Gold Inc. [TSX.V: CERT][OTCQX: CRDOF] (“Cerrado” or the

“Company”) announces production results for the first quarter of 2024 (“Q1 2024”) from the Minera

Don Nicolas Mine in Santa Cruz Province, Argentina (“MDN”). Full first quarter financial results are

expected to be released in May 2024.

Q1 Operating Highlights

• Q1 2024 production of 11,024 Gold Equivalent Ounces (“GEO”).

• Production for March of 5,747 GEO and April expected to be over 6,000 GEO’s for the

month, with Calandria Norte delivering expected production targets.

• Calandrias Norte contributing higher-grade ore feed to the mill, expected to improve

production levels moving forward.

• Production ramp-up from the Las Calandrias heap leap project continues; commercial

production expected in Q2 2024.

Operational results presented for Q1 2024 were below expectations in January and February due to

lower than expected ore grades in the upper benches of Cala ndrias Norte and ongoing ramp up

issues with the crushing circuit at the Calandrias Sur heap leach operations. Production improved

significantly in March with the production of 5,255 GEO from the CIL plant and 4 92 GEO from the

Calandrias Heap leach.

Production returned to expected levels as mining transitioned to lower benches at Calandrias Norte,

which has higher grades and better reconciliation to the anticipated mine plan. Performance of the

crushing circuit at the Calandrias Sur Heap Leach Project continues to improve , allowing the

placement of more ore on the heap leach pad during the latter part of the quarter. Operations in

the quarter were also impacted by the fiscal policy changes implemented in the country following

the November 2023 general election that imposed not only a significant financial burden on the

MDN operation, but also disrupted deliveries of certain supplies and spare parts.

Production is set to ramp-up over the second quarter of 2024 , and the Calandrias Heap Leach is

expected to achieve nameplate production rates in June. At Calandrias Norte, stripping activities

-2-

have been completed, and the pit is now beginning to deliver higher grade ore to the CIL plant at

Martinetas. Head grades from Calandrias Norte are reconciling well with the model, and grades have

increased as the early benches have been mined out and deeper, higher grade levels are accessed.

Mark Brennan, CEO and Chairman commented, "Production in the first quarter was impacted due

to lingering issues with the new heap leach facility , resulting in a slower ramp up than initially

planned. Further, ore grades were lower than expected in the initial benches at Calandrias Norte.

That said, the performance at MDN has begun to show significant improvement in March and April

as we accessed higher grade ore from Calandrias Norte, and the leach cycle at Las Calandrias shows

a consistent increase in production although at lower than expected rates.”

He continued, “ It has been a very difficult period for Cerrado and MDN over the past six months ,

waiting for production at Calandrias Norte and the Heap Leach to ramp up, and we now feel that we

have turned the corner. I n the near term , the focus at MDN continues to be on generating strong

cash flow from our now completed capital investments, which are expected to allow us to rebuild

the balance sheet and refocus our efforts on exploration and increasing the overall life of mine at

MDN. There remains a terrific opportunity to scale up MDN and develop it into a significant operation

much like our neighboring peers."

Ore milled and production rates decreased during the first quarter as operations, while normalized,

experienced lower grades from the initial benches mine d at Las Calandrias Norte and some issues

with the commissioning of the crusher at the heap leach operation . Improved production is

expected into the second quarter as the crushing circuit continues to operate at or near full capacity,

and higher grades from the lower benches at Las Calandrias Norte are now being mined. Total

production for the first quarter from the heap leach operation was 1,103 gold ounces and 2,543

silver ounces, with 43% of the gold production from the heap leach coming in March. Please see

Table 1. for a summary of key highlights for the first quarter. Sales for the quarter were lower than

production due to delays in shipping due to in-country holidays for Easter at the end of March.

-3-

Table 1. Key Operating Information

Hedging

Additionally, the Company announces that on April 26, 2024 it has entered into a limited hedging

program with Ocean Partners UK Ltd. The hedge is constructed as a zero-cost collar with lower and

upper boundaries of US$2,300 and US$2,475 per ounce respectively. The h edging volume is for

2,000 ounces per month for a period of 11 months beginning May 2024 and terminating on March

31th, 2025. The Company is focused on signifigantly reducing the current payables and debt balance

in Argentina over the next year and has entered into this hedge to protect a portion of cashflows

from a possible reduction in Gold prices over this period.

Review of Technical Information

The scientific and technical information in this press release has been reviewed and approved by

Sergio Gelcich, P.Geo., Vice President, Exploration for Cerrado Gold Inc., who is a Qualified Person

as defined in National Instrument 43-101.

Operating Data Unit Q1 2024

Total tons mined for CIL and HL

Ore Mined CIL ktonnes 375 287 85

Ore mined for Calandrias Heapleach 560 189

Waste Mined ktonnes 4,530 5,158 2,618

Total Mined (1) ktonnes 5,223 6,093 2,892

Strip ratio waste/ore 12.08 13.33 30.70

Mining rate tpd 14,311 16,694 32,133

CIL Plant

Ore Milled Ktonnes 395 367 90

Head Grade Au g/t 4.56 4.59 3.65

Head Grade Ag g/t 10.97 5.59 10.21

Recovery Au % 91.6% 90.4% 87.6%

Recovery Ag % 63.3% 62.1% 55.7%

Mill Throughput tpd 1,082 1,006 1,001

Gold Production (CIL & Heapleach)

Gold ounces produced (Dore) oz 52,504 50,659 10,982

Silver equivalent ounces produced oz 1,167 492 222

Gold Geo Produced oz 53,672 51,150 11,204

Gold ounces sold oz 50,743 53,751 10,383

Silver equivalent ounces sold oz 1,180 540 208

Total Gold Ounces sold CIL & Heapleach

Gold Geo Sold 51,923 54,292 10,592

Average realized price per gold ounce sold $/oz 1,742 1,849 1,971

1. Includes low grade stockpiles at Martinetas

Key Operating Information

2024Jan to Dec,

2022

Jan to Dec,

2023

-4-

Mark Brennan

CEO and Co Chairman

Mike McAllister

Vice President, Investor Relations

Tel: +1-647-805-5662

[email protected]

About Cerrado

Cerrado Gold is a Toronto-based gold production, development, and exploration company focused

on gold projects in South America. The Company is the 100% owner of both the producing Minera

Don Nicolás and Las Calandrias mine in Santa Cruz province, Argentin a, and the highly prospective

Monte Do Carmo development project, located in Tocantins State, Brazil. In Canada, Cerrado Gold

is developing it's 100% owned Mont Sorcier Iron Ore and Vanadium project located outside of

Chibougamou, Quebec.

In Argentina, Cerrado is maximizing asset value at its Minera Don Nicolas operation through

continued operational optimization and is growing production through its operations at the Las

Calandrias Heap Leach project. An extensive campaign of exploration i s ongoing to further unlock

potential resources in our highly prospective land package in the heart of the Deseado Masiff.

In Canada, Cerrado holds a 100% interest in the Mont Sorcier Iron Ore and Vanadium Project, which

has the potential to produce a premium iron ore concentrate over a long mine life at low operating

costs and low capital intensity. Furthermore, its high grad e and high purity product facilitates the

migration of steel producers from blast furnaces to electric arc furnaces contributing to the

decarbonisation of the industry and the achievement of SDG goals.

For more information about Cerrado, please visit our website at: www.cerradogold.com.

Disclaimer

NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS

DEFINED IN POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE

ADEQUACY OR ACCURACY OF THIS RELEASE.

This press release contains statements that constitute "forward -looking information" (collectively,

"forward-looking statements") within the meaning of the applicable Canadian securities legislation,

all statements, other than statements of historical fact , are forward -looking statements and are

based on expectations, estimates and projections as at the date of this news release. Any statement

that discusses predictions, expectations, beliefs, plans, projections, objectives, assumptions, future

events or performance (often but not always using phrases such as "expects", or "does not expect",

"is expected", "anticipates" or "does not anticipate", "plans", "budget", "scheduled", "forecasts",

"estimates", "believes" or "intends" or variations of such words and phrases or stating that certain

actions, events or results "may" or "could", "would", "might" or "will" be taken to occur or be

achieved) are not statements of historical fact and may be forward-looking statements.

Forward-looking statements contained in this press release include, without limitation, statements

regarding the business and operations of Cerrado. In making the forward - looking statements

contained in this press release, Cerrado has made certain assumptions, including, but not limited to

-5-

the ramp-up of the Calandrias Heap Leach project, stripping activities and head grades at Calandrias

Norte, expectations regarding MDN operations and financial performance generally. Although

Cerrado believes that the expectations reflected in forward -looking statements are reasonable, it

can give no assurance that the expectations of any forward -looking statements will prove to be

correct. Known and unknown risks, uncertainties, and other factors which may cause the actual

results and future events to diff er materially from those expressed or implied by such forward -

looking statements. Such factors include, but are not limited to general business, economic,

competitive, political and social uncertainties. Accordingly, readers should not place undue reliance

on the forward -looking statements and information contained in this press release. Except as

required by law, Cerrado disclaims any intention and assumes no obligation to update or revise any

forward-looking statements to reflect actual results, whether as a result of new information, future

events, changes in assumptions, changes in factors affecting such forward -looking statements or

otherwise.