Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

CERT.V ·

Cerrado Gold Announces Q1 2026 Production Results at Its Minera Don Nicolas Mine in Argentina

Production Results

Cerrado Gold Announces Q1 2026 Production Results at Its Minera Don

Nicolas Mine in Argentina

• Strong Production of 12,842 Gold Equivalent Ounces ("GEO") for the 1 st Quarter 2026

• Improved realized gold prices with close-out of hedges in January

• 2026 Production Guidance of 50,000 to 60,000 GEO maintained

• Underground development ramping up to support increased production in Q2/Q3

• Exploration Program advancing rapidly to support resource growth at MDN with four drill rigs operating on

site

• Development activities continue to progress at both the Lagoa Salgada and Mont Sorcier projects

TORONTO, April 20, 2026 -- Cerrado Gold Inc. [TSX.V: CERT] [OTCQX: CRDOF] ("Cerrado" or the "Company") announces

production results for the first quarter ended March 2026 ("Q1 2026") from the Minera Don Nicolas Mine in Santa Cruz

Province, Argentina ("MDN"). Full quarterly financial results are expected to be released prior to May 31, 2026.

Q1 Operating Highlights

• Q1 Production of 12,842 vs 11,163 GEO in Q1 2025

• Heap leach production of 8,787 GEO continues to increase as water availability improves

• Underground development work continued at an accelerated pace, with record development meters during

the period

• Access to new underground ore zones expected in Q2 2026, delivering high-grade ore to the CIL, improving

head feed grade, and increasing production

• CIL plant continues to process a blend of stockpile material and additional ore from underground

development, resulting in total production of 4,055 GEO in Q1 through the CIL plant

Operational results for Q1 2026 showed production remained consistent relative to the previous quarter. Production rates

increased at the heap leach versus the previous quarter; however, irrigation issues continued to limit production. Water

availability continues to improve as we move into the wetter months and remains supported by ongoing purchases and

additional water from expanded borehole water production. As more water for irrigation becomes available, the gold inventory

on the pad that has not been fully irrigated will be recovered over time. Average recovery rates remained lower than planned

due to the mix of primary ore placed on the leach pads as per the mine sequence, as well as reduced irrigation. This was

offset by steady production from the CIL plant, maintaining overall production rates.

The focus on underground development continued during the quarter, which reduced the ore available for immediate

processing, but the increased development (See Figure 1 below) will allow access to more material amounts of ore during the

coming quarters and is expected to lift production and improve head grades to the plant during Q2/Q3. During 2026,

underground ore operations are expected to follow a cycle of development and then ore extraction, as the underground

workings follow the ore zone deeper under the current pit.  

Table 1. Key Operating Information

Key Operating Information                

    2024 2025       2025 2026

Operating Data Unit FY Q1 2025 Q2 2025 Q3 2025 Q4 2025 FY Q1 2026

Heap Leach Operations                

Ore Mined ktonnes 1,280  659  550  759  816  2,784  785 

Waste Mined ktonnes 3,215  1,024  998  1,001  1,131  4,155  984 

Total Mined ktonnes 4,494  1,683  1,549  1,760  1,947  6,939  1,769 

Strip ratio waste/ore 2.51  1.56  1.81  1.32  1.39  1.49  1.25 

Mining rate tpd 12,313  18,699  17,207  19,133  21,166  19,063  19,656 

Ore PAD Feed Ktonnes 1,538  693  724  793  863  3,073  801 

Head Grade Au g/t 0.73  0.80  0.86  0.81  0.79  0.81  0.85 

Head Grade Ag g/t 10.41  15.95  12.13  11.68  13.59  13.29  12.22 

Recovery Au % 34% 39% 37% 47% 32% 39% 33%

Recovery Ag % 10% 8% 15% 24% 16% 16% 26%

PAD Throughput tpd 4,214  7,700  7,953  8,621  9,380  7,700  8,904 

Gold ounces produced oz 12,277  6,897  7,442  9,605  6,982  30,926  7,257 

Silver equivalent ounces produced oz 633  331  422  824  856  2,432  1,531 

Gold Geo Produced oz 12,911  7,228  7,864  10,429  7,838  33,358  8,787 

High Grade CIL Operations                

Ore Mined ktonnes 218  11  -  7  28  46  16 

Waste Mined ktonnes 5,027  60  -  14  28  102  22 

Total Mined ktonnes 5,245  71  -  21  56  148  39 

Strip ratio waste/ore 23.08  5.23  -  2.09  1.00  2.20  1.36 

Mining rate tpd 14,369  788  -  231  611  410  430 

Ore Milled Ktonnes 348  92  97  93  93  374  102 

Head Grade Au g/t 3.99  1.51  1.18  1.31  2.15  1.53  1.34 

Head Grade Ag g/t 9.49  6.44  9.71  7.98  16.66  10.21  8.38 

Recovery Au % 90% 92% 84% 86% 86% 88% 89%

Recovery Ag % 59% 54% 62% 55% 52% 58% 52%

Mill Throughput tpd 952  1,017  1,076  1,006  1,009  1,027  1,131 

Gold ounces produced oz 40,861  3,821  3,378  3,253  5,626  16,078  3,740 

Silver equivalent ounces produced oz 722  115  195  150  342  802  315 

Gold Geo Produced oz 41,583  3,936  3,573  3,403  5,968  16,880  4,055 

Consolidated Gold Produciton                

Gold Geo Produced oz 54,494  11,163  11,437  13,832  13,806  50,238  12,842 

Gold Geo Sold oz 52,058  11,468  10,886  12,896  13,627  48,877  12,185 

Average realized price per gold ounce sold $/oz 2,226  2,520  2,684  3,182  3,401  2,970  4,418 

Figure 1. Paloma Underground Development – meters/quarter

Minera Don Nicolas Exploration Update

The Company continues to advance its exploration program at MDN, focused on near-mine targets with the potential to

materially extend resources and extend mine life. This includes supporting medium-term operational sustainability through

high-grade underground feed to the CIL plant, as well as increasing resources available for heap supporting medium-term

operational sustainability through high-grade underground feed to the CIL plant, as well as increasing resources available for

heap leach processing.

Current drilling is aimed at defining the depth and lateral extent of mineralization in the Sulfuro vein, which was historically

exploited as the Paloma Open Pit and is now exploited as an Underground operation (see Figure 2). The second front of

exploration is currently the Baritina vein (Paula Andrea area), where results to date have been encouraging, demonstrating

continuity of the vein below surface (see Figure 3). During the second half of the year, exploration is expected to shift toward

the Calandrias heap leach and the Martinetas plant areas.

To accelerate progress and enable simultaneous testing of multiple high-priority targets, the Company has expanded its

drilling capacity to include four rigs and associated logistical support. Exploration efforts in 2026 will include both surface and

underground drilling, targeting several high-value zones to further grow the resource base.

At present, assay turnaround times remain a constraint; however, the Company is addressing this through engagement with

external laboratories and by certifying its internal laboratory, which is expected to be completed in Q3 of 2026. The Company

plans to report exploration results in batches to better demonstrate overall resource potential.  

Figure 2. Paloma System

Figure 3. Baritina Vein

Mark Brennan, CEO and Chairman, commented, “The First Quarter represents another strong and steady production quarter

at MDN with our two production fronts of heap leach and CIL continuing to provide production stability during development

cycles in the underground, while water issues existed at the heap leach. The exploration program is now progressing at the

expected rate, and while assays continue to be delayed, we are working on both internal and external resolutions to these

challenges.

He continued, “Cerrado also continued to make good progress to advance the Mont Sorcier project with completion of the

feasibility study on track for late Q2 2026. At Lagoa Salgada, the Company continues to work closely with the relevant

authorities and agencies regarding permitting.”

Review of Technical Information

The scientific and technical information in this press release has been reviewed and approved by Andrew Croal, P.Eng., Chief

Technical Officer for Cerrado Gold, who is a Qualified Person as defined in National Instrument 43-101.

About Cerrado 

Cerrado Gold is a Toronto-based gold production, development, and exploration company. The Company is the 100% owner of

the producing Minera Don Nicolás and Las Calandrias mine in Santa Cruz province, Argentina. In Portugal, the Company holds

an 80% interest in the highly prospective Lagoa Salgada VMS project through its position in Redcorp - Empreendimentos

Mineiros, Lda. In Canada, Cerrado Gold is developing its 100% owned Mont Sorcier Iron project located outside of

Chibougamau, Quebec.

In Argentina, Cerrado is maximizing asset value at its Minera Don Nicolas ("MDN") operation through continued operational

optimization and is growing production through its operations at the Las Calandrias heap leach project. An extensive campaign

of exploration is ongoing to further unlock potential resources in our highly prospective land package in the heart of the

Deseado Masiff.

In Portugal, Cerrado is focused on the development and exploration of the highly prospective Lagoa Salgada VMS project

located on the prolific Iberian Pyrite Belt in Portugal. The Lagoa Salgada project is a high-grade polymetallic project,

demonstrating a typical mineralization endowment of zinc, copper, lead, tin, silver, and gold. Extensive exploration upside

potential lies both near the deposit and at prospective step-out targets across the large 7,209-hectare property concession.

Located just 80km from Lisbon and surrounded by existing infrastructure, Lagoa Salgada offers a low-cost entry point to a

significant development and exploration opportunity, already demonstrating its mineable scale and cash flow generation

potential.

In Canada, Cerrado is developing its 100% owned Mont Sorcier high-purity, high-grade, Direct Reduced Iron project, located on

the traditional Cree territory of Eeyou Istchee James Bay in the municipality of Chibougamau. The Mont Sorcier project has

the potential to produce a premium iron concentrate over a long mine life at low operating costs and low capital intensity.

Furthermore, its high-grade and high-purity product facilitates the migration of steel producers from blast furnaces to electric

arc furnaces, contributing to the decarbonization of the industry and the achievement of sustainable development goals.

For more information about Cerrado, please visit our website at www.cerradogold.com. 

Mark Brennan                        

CEO and Chairman        

Mike McAllister

Vice President, Investor Relations

Tel: +1-647-805-5662

[email protected]                                

Disclaimer

NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE

POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF

THIS RELEASE.

This press release contains statements that constitute "forward-looking information" (collectively, "forward-looking

statements") within the meaning of the applicable Canadian securities legislation. All statements, other than statements of

historical fact, are forward-looking statements and are based on expectations, estimates and projections as at the date of this

news release. Any statement that discusses predictions, expectations, beliefs, plans, projections, objectives, assumptions,

future events or performance (often but not always using phrases such as "expects", or "does not expect", “is expected”,

“anticipates” or “does not anticipate”, “plans”, “budget”, “scheduled”, “forecasts”, “estimates”, “believes” or “intends” or

variations of such words and phrases or stating that certain actions, events or results “may” or “could”, “would”, “might” or “will”

be taken to occur or be achieved) are not statements of historical fact and may be forward-looking statements.

Forward-looking statements contained in this press release include, without limitation, statements regarding the business and

operations of Cerrado, production forecasts for 2026, progress and potential of underground development at MDN, exploration

potential at MDN and the ability of prospective targets to materially add to mine life and discovery of ore capable of feeding

the heap leach and CIL operations, the anticipated outcome and time to complete the feasibility study on the Mont Sorcier

project, the outcome of permitting matters relating to the Lagoa Salgada Project, and the risks and uncertainties described

under the heading “Risks & Uncertainties” in the Company’s Management Discussion and Analysis and other filings made with

the securities commissions in Canada. In making the forward-looking statements contained in this press release, Cerrado has

made certain assumptions. Although Cerrado believes that the expectations reflected in forward-looking statements are

reasonable, it can give no assurance that the expectations of any forward-looking statements will prove to be correct. Known

and unknown risks, uncertainties, and other factors which may cause the actual results and future events to differ materially

from those expressed or implied by such forward-looking statements. Except as required by law, Cerrado disclaims any

intention and assumes no obligation to update or revise any forward-looking statements to reflect actual results, whether as a

result of new information, future events, changes in assumptions, changes in factors affecting such forward-looking

statements or otherwise.

Photos accompanying this announcement are available at:

https://www.globenewswire.com/NewsRoom/AttachmentNg/c2fa366c-1bb4-4dcb-9de8-7825c29399db 

https://www.globenewswire.com/NewsRoom/AttachmentNg/e35ffe02-f466-44af-be56-f8f1afc78c83 

https://www.globenewswire.com/NewsRoom/AttachmentNg/8a23fc2c-ab12-44a2-b01e-d66172d0dc91