Cerro de Pasco Resources Prepares for Next Phase as Technical and Permitting Work Advances at the Quiulacocha Project
PRESS RELEASE
Cerro de Pasco Resources Prepares for Next Phase as Technical and
Permitting Work Advances at the Quiulacocha Project
Montréal, Québec, Canada – December 10, 2025 – Cerro de Pasco Resources Inc.
(TSXV: CDPR) (OTCMKTS: GPPRF) (BVL: CDPR) is pleased to provide a comprehensive update on
the progress achieved at the Quiulacocha Tailings Reprocessing Project. This update reflects the
significant advancement of technical, environmental, geotechnical, and permi tting work
completed under Phase 1 and the transition into Phase 2. The Quiulacocha Project represents
the most strategically important tailings reprocessing and remediation initiatives in Peru, with the
potential to deliver both substantial resource value and long-term environmental benefits.
Phase 1 Achievements to Date
Drilling and Mineral Resource
Completion of a 40 -hole sonic drill program confirming metal grades and continuity across the
drilled area. Tendering and technical assessment of international contractors for Phase 2 drilling
is underway. The combined Phase 1 and Phase 2 datasets will sup port the mineral resource
estimate for the Quiulacocha tailings.
Mineralogy & Metallurgy
Extensive mineralogical and metallurgical test work is progressing across multiple international
laboratories to determine the most effective flowsheet for recovering metals into marketable
products.
Environmental Baseline Studies
Completion of wet season baseline studies and ongoing dry season assessments. These include
drone-based LiDAR, magnetometry, and photogrammetry, as well as water quality, biological,
geochemical, geotechnical, and hydrogeological monitoring.
Hydrogeology and Geotechnics
High resolution LiDAR, photogrammetry, and magnetometry surveys have been incorporated into
hydrogeological models and stability assessments. These results guide mine planning, re mining
method selection, and Phase 2 drilling infrastructure requirements.
Tailings Re-mining and final storage
Initial trade off assessments for long-term storage sites and re -mining methods have been
completed. Rheology and abrasivity testing confirm that Quiulacocha tailings can be efficiently
dredged and pumped at low cost.
Permitting and Approvals
Submission of the Phase 1 Results Report to initiate the regulatory process for Phase 2 drilling
and the formalization of tailings reprocessing rights beyond the El Metalurgista concession.
CDPR is fully funded to complete Phase 2 drilling and all ongoing metallurgical test programs
following its most recent financing.
/3
Upcoming Milestones
Formalization of claim on entire tailings footprint
Completion of integrated metallurgical program in Q1 2026
Submission and approval of DIA or FTA for Phase 2 drilling
Commencement of Phase 2 drilling
Completion of hydrogeological and geotechnical models
Selection of preferred long term tailings storage solution
Advancement into pre-feasibility study
Executive Commentary
Guy Goulet, Chief Executive Officer, commented:
“Our team has made significant progress across the most comprehensive technical and
environmental program ever undertaken on the Quiulacocha Tailings Project. The results provide
strong confirmation of the project’s potential and position us well for the next stages of
engineering and development. With multiple laboratories, technical partners, and specialist
teams contributing to this effort, we are building a robust technical foundation for a long-term
value generating operation.
Few projects globally offer the combination of metal endowment, environmental benefit, and
development potential that we see at Quiulacocha. With the remaining administrative steps
moving forward, CDPR is preparing to advance into the feasibility phase and remains fully
committed to delivering this transformational project for our shareholders and for Peru. ”
Permitting and Approvals
In November 2025 the independent Mining Council, Peru’s highest administrative authority for
mining matters, issued two resolutions that provide a clear and affirmative basis for advancing
the final stages of the permitting process for the Quiulacocha Project. encompassing the entire
tailings footprint to achieve a comprehensive reprocessing and remediation solution. The
Council’s decisions formally set out the requirement for agreement between CDPR, owner of the
core tailings concession, and the State, hol der of legacy environmental responsibilities in the
area. They also clarify the administrative path for the Ministry of Energy and Mines to proceed with
the evaluation and formalization of CDPR’s Tailings Reprocessing Application. This recent
clarification creates alignment among the relevant authorities and supports a timely conclusion
of the remaining administrative steps. CDPR is engaging closely with the Ministry and anticipates
continued momentum as the permitting process advances toward completion.
Technical Program Update
The Quiulacocha Project continues to advance as a large-scale, long-life development supported
by a rigorous technical work program. Metallurgical and mineralogical testing across
international laboratories is defining the most effective multi product processing route. With the
integrated metallurgical program scheduled to conclude in the first quarter of 2026, CDPR is
assembling the technical foundation required for feasibility level engineering and economic
evaluation.
/4
Mineralogical and Geochemical Program
The mineralogy program includes quantitative mineralogy, sequential extractions, electron
microprobe work, laser ICP MS, flotation product mineralogy, and hydro separation for trace
mineral analysis. These tests help determine mineral associations, metal d eportment, and
factors influencing metallurgical recoveries. The work has been conducted across LTU in
Sweden, Montana Tech, Chilean laboratories, and Peruvian facilities.
Metallurgical Test Work Program
The metallurgical program aims to recover silver, zinc, lead, copper, and pyrite into saleable
concentrates, with additional focus on gold and gallium recovery pathways. The initial phase
centers on flotation and selective leaching to maximize metal recoveries.
Representative composite samples were generated based on metallurgical domains defined
through the 40-hole drilling campaign. Bench scale flotation tests have successfully produced
base metal concentrates followed by pyrite, with silver reporting across these products. Cleaner
stage testing is underway to optimize recoveries and concentrate grades.
The fine-grained nature of the tailings requires minimal grinding, offering potential operating cost
advantages. Specialized fine particle flotation technologies are being evaluated to enhance
recovery and grade.
Preliminary leaching tests demonstrate the potential to selectively recover silver and gold into a
distinct product stream. Pyrite concentrate optimization continues to support its potential
saleability or downstream processing into sulphuric acid.
The initial metallurgical phase is expected to conclude in Q1 2026, after which locked cycle tests
and variability testing will begin in Q2 2026.
Collectively, the results to date support the potential for a multi-product flowsheet designed to
maximize metal recovery while significantly reducing final tailings volumes.
Environmental Baseline Program
CDPR has completed its wet season environmental baseline and advanced dry season work,
including water quality monitoring, geochemical sampling, biological surveys, and physical
assessments. These datasets will form the foundation of the project’s Environm ental Impact
Assessment.
Reprocessing the Quiulacocha tailings has the potential to reduce long term environmental
liabilities, improve water and land conditions, and provide lasting remediation benefits to the
region.
In parallel with technical programs, CDPR continues to advance an equally rigorous
environmental workstream.
Hydrogeological and Geotechnical Studies
Drone based surveys across more than 5,000 hectares include high resolution LiDAR, detailed
photogrammetry, and regional magnetometry. These datasets feed into the hydrogeological
model and Digital Elevation Model of the region.
Preliminary stability assessments, including analysis of historical data and new measurements,
have been completed. Plate load testing, geotechnical sampling, and SCPTu measurements
/5
define the requirements for Phase 2 drilling, infrastructure planning, and long-term tailings
management.
This growing geotechnical and hydrogeological foundation is essential for mine planning, re -
mining method selection, and feasibility level design.
Re-mining and Final Tailings Storage Trade Offs
Technical studies continue across re -mining methods, material handling, hydrogeological and
geotechnical interpretation, and overall site layout planning. Laboratory work for rheology,
abrasivity, density, and geotechnical behavior was completed for ten composite samples from
the Phase 1 drilling program. These tests confirmed that the Quiulacocha tailings are pumpable
within an optimal solids concentration range of 65 to 75 percent by weight, supporting the
implementation of low cost dredging based extraction methods and providing meaningful
advantages for operational efficiency and water balance management.
Tailings storage trade off studies have evaluated storage capacity, land suitability, hydrology,
environmental considerations, and long-term operational requirements across several regional
locations. These evaluations will guide the selection of a preferred long term storage solution and
are key inputs for determining the optimal combination of re-mining, processing, and final tailings
placement strategies.
Phase 2 Drilling Program
The next drilling campaign will complete the geological, hydrogeological, and geotechnical
datasets required for feasibility level engineering. The combined Phase 1 and Phase 2 drilling
program includes approximately 116 drillholes across the Quiulacocha TSF , providing one-meter
samples and laboratory assays that will support the first Mineral Resource Estimate.
International drilling contractors have submitted proposals featuring amphibious platforms and
sonic capable rigs. Drilling will commence following approval of the Tailings Reprocessing
Application that grants tailings reprocessing rights beyond the El Metalurgista concession.
This drilling is a critical step toward feasibility level engineering and will complete the technical
dataset required for mine planning.
Technical Information
Mr. Alfonso Palacio Castilla, MIMMM/Chartered Engineer (CEng) and Project Superintendent for
CDPR, has reviewed and approved the scientific and technical information contained in this news
release. Mr. Palacio is a Qualified Person for the purposes of reporting in compliance with NI 43-
101.
About Cerro de Pasco Resources
Cerro de Pasco Resources is focused on the development of its one hundred percent owned El
Metalurgista mining concession in central Peru. The concession hosts silver -rich tailings and
stockpiles accumulated over more than a century of mining. The Company’s strategy is to
reprocess and remediate historic mining waste, unlocking value while supporting sustainable
development.
CDPR is committed to advancing Quiulacocha as a model for responsible tailings reprocessing,
environmental remediation, and sustainable value creation in Peru.
For more information, please visit www.pascoresources.com.
/6
Further Information
Guy Goulet, CEO
Telephone: +1 579 476 7000
Mobile: +1 514 294 7000
Email: [email protected]
Forward-Looking Statements and Disclaimer
Certain information contained herein may constitute “forward -looking information” under
Canadian securities legislation. Generally, forward -looking information can be identified using
forward-looking terminology such as “plans”, “seeks”, “expects”, “estima tes”, “intends”,
“anticipates”, “believes”, “could”, “might”, “likely”, “scheduled” or variations of such words or
statements that certain actions, events or results “may”, “will”, “could”, “would”, “might”, “will
be taken”, “occur”, “be achieved” or othe r similar expressions. Forward- looking statements,
including the expectations of CDPR’s management regarding the advancement, timing, scope
and completion of the Phase 1 and Phase 2 work programs at the Quiulacocha Tailings
Reprocessing Project; the anticipated timing, content and results of metallurgical, mineralogical,
environmental, hydrogeological and geotechnical test work and studies; the expected timing for
completion of the integrated metallurgical program, hydrogeological and geotechnical models,
and other technical datasets required for feasibility ‑level engineering and mine planning; the
preparation, timing and potential results of the first Mineral Resource Estimate for the
Quiulacocha tailings; and the expected benefits of tailings reprocessing; the timing, outcome
and impact of permitting and re gulatory processes, including the formalization of tailings
reprocessing rights beyond the El Metalurgista concession use of proceeds and the use of the
available funds following completion of the Offering, execution of the technical, environmental
and eng ineering programs and timing on when the proceeds will be used to meet the
Corporation’s objectives at the Quiulacocha Tailings Project, are based on CDPR’s estimates and
are subject to known and unknown risks, uncertainties and other factors that may caus e the
actual results, level of activity, performance or achievements of CDPR to be materially different
from those expressed or implied by such forward- looking statements or forward -looking
information. Forward -looking statements are subject to business an d economic factors and
uncertainties and other factors, that could cause actual results to differ materially from these
forward-looking statements, including the relevant assumptions and risk factors set out in
CDPR’s public documents, available on SEDAR+ at www.sedarplus.ca. There can be no
assurance that such statements will prove to be accurate, as actual results and future events
could differ materially from those anticipated in such statements. Although CDPR believes that
the assumptions and factors us ed in preparing the forward- looking statements are reasonable,
undue reliance should not be placed on these statements and forward -looking information.
Except where required by applicable law, CDPR disclaims any intention or obligation to update
or revise any forward-looking statement, whether as a result of new information, future events or
otherwise.
Neither the TSXV nor its Regulation Services Provider (as that term is defined in the policies of the
TSXV) accepts responsibility for the adequacy or accuracy of this news release.