Cordoba Announces Positive Preliminary Economic Assessment for the San Matias Copper-Gold-Silver Project Total Estimated Production: 417,300 Tonnes of Copper, 724,500 Ounces of Gold, 5,930,000 Ounces of Silver Estimated $347.0 million Pre-Tax NPV8% and 26.8% Pre-Tax IRR;
1
Cordoba Announces Positive Preliminary Economic
Assessment for the San Matias Copper-Gold-Silver Project
Total Estimated Production: 417,300 Tonnes of Copper,
724,500 Ounces of Gold, 5,930,000 Ounces of Silver
Estimated $347.0 million Pre-Tax NPV8% and 26.8% Pre-Tax IRR;
$210.7 million After-Tax NPV8% and 20.3% After-Tax IRR
High-Grade Gold and Porphyry Copper Upside at San Matias
VANCOUVER, BRITISH COLUMBIA, July 29, 2019: Cordoba Minerals Corp. (TSX-V:CDB;
OTCQB:CDBMF) (“Cordoba” or the “Company”) today reported results from an independent
Preliminary Economic Assessment (“PEA”) for its San Matias Copper-Gold-Silver Project (“San
Matias” or the “Project”) in Colombia. The PEA was prepared by Nordmin Engineering Ltd.
(“Nordmin”) of Thunder Bay, Ontario, and includes revisions to the June 2019 San Matias Mineral
Resource estimate that was completed by Nordmin (refer to Cordoba’s news release dated July
3, 2019). All amounts are in United States dollars, unless otherwise stated. Summary results of
the PEA are shown below in Table 1.
San Matias PEA Highlights:
• Conceptual 8,000 tonnes per day (“tpd”) conventional open pit mining operation,
increasing to 16,000 tpd after the processing plant expansion is completed in Year 6 –
underpinned by 119.1 million tonnes of modeled mill feed grading 0.45% copper, 0.26 g/t
gold and 2.41 g/t silver, supporting a 23-year life of mine. During the first five years, the
PEA includes copper, gold and silver grades averaging 0.67%, 0.30 g/t and 3.74 g/t
respectively with a low strip ratio of 0.82:1.
• PEA life of mine (“LOM”) production of 417,300 tonnes of copper, 724,500 ounces of gold
and 5,930,000 ounces of silver contained in a clean copper concentrate and precious
metals doré. The copper concentrate is expected to contain very low contents of
deleterious elements, such as arsenic and lead.
• Estimated annual copper production of 15,400 tonnes in concentrate in Years 1 to 5;
increasing to 20,700 tonnes in Years 6 to 16; and averaging 18,100 tonnes per year over
the total 23-year PEA life of mine.
• Average LOM C1 cash costs of $1.32 per pound of copper, net of precious metals by-
product credits.
• Initial capital expenditures of $161.4 million, expansion capital expenditures of $120.6
million and total PEA life of mine capital expenditures, including sustaining capital, Tailings
Management Facility (“TMF”) and reclamation costs, of $527.5 million.
2
• Pre-tax net present value ("NPV") of $347.0 million at an 8% discount rate and a pre-tax
internal rate of return ("IRR") of 26.8%, using metals price assumptions of $3.25 per pound
copper, $1,400 per ounce gold and $17.75 per ounce silver. A USD/COP foreign
exchange rate of 3,125:1 has been applied. Pre-tax values include Colombian mining
royalties of 4% of total precious metals revenue and 5% of total copper revenue.
• After-tax NPV8% of $210.7 million and an after-tax IRR of 20.3%, representing a 5.3-year
payback using the same metals price assumptions.
• Over the PEA life of mine, the San Matias Project is expected to generate $180.7 million
in royalty revenue plus $331.2 million in income tax revenue to the government.
• Cordoba has identified additional opportunities to enhance the overall project economics,
including delineation of the high-grade gold veins contained within the El Alacrán deposit
(“Alacran”) and optimization of mineral processing and metals recovery. Potential also
exists for the discovery of the porphyry sources for the Alacran and Montiel West deposits
and for other deposits within the San Matias Project area.
The San Matias 2019 PEA is preliminary in nature and includes an economic analysis that is
based, in part, on Inferred Mineral Resources. Inferred Mineral Resources are considered too
speculative geologically for the application of economic considerations that would enable them to
be categorized as Mineral Reserves – and there is no certainty that the results will be realized.
Mineral Resources do not have demonstrated economic viability and are not Mineral Reserves.
“We believe we have demonstrated a very robust project at San Matias through the PEA work
completed by Nordmin.” stated Eric Finlayson, President and CEO of Cordoba. “The Alacran
deposit, with its significant copper, gold and silver grades and low strip ratio, remains the
cornerstone of the Project, supplemented by the later addition of mill feed from the Montiel East,
Montiel West and Costa Azul pits. This is only the beginning for San Matias, and we will continue
to explore our highly prospective copper and gold targets within the region.”
San Matias Copper-Gold-Silver Project Overview
The San Matias Copper-Gold-Silver Project is located in the municipality of Puerto Libertador,
Department of Córdoba, Colombia, and is approximately 200 kilometres north of Medellín. The
site is road accessible from the town of Puerto Libertador, approximately 20 kilometres away. The
PEA outlines a conventional open pit mining operation consisting of a main open pit mine at the
Alacran deposit and three smaller open pit mines at the Montiel East, Montiel West and Costa
Azul satellite deposits. The PEA includes a centralized processing plant and TMF located directly
adjacent to the Alacran pit. The site layout is shown below in Figure 1.
The PEA includes employment for 290 personnel during the first 5 years of expected production
and increasing to 355 personnel for the remaining 18 years.
Permitting
Cordoba holds exploration licences covering 149 square kilometres and has an additional 2,491
square kilometres of exploration licenses under application. Cordoba is working to complete the
Mining Technical Work Plan (Programa de Trabajo y Obras or “PTO”) and the Environmental
Impact Assessment (“EIA”) for the Alacran deposit, required prior to receiving approvals to begin
construction.
3
Table 1: San Matias July 2019 PEA highlights completed by Nordmin Engineering Ltd.
Preliminary Economic Assessment Highlights - July 2019
Production Metrics
PEA mine life (years) 23
Total copper production (t) 417,300
Total gold production (oz) 724,500
Total silver production (oz) 5,930,000
Average annual copper production (Years 1 to 5; tpa) 15,400
Average annual copper production (Years 6 to 16; tpa) 20,700
Average annual copper production (LOM average; tpa) 18,100
Total conceptual open pit resources (kt) 119,100
Total waste (kt) 96,200
Total material (kt) 215,300
Strip ratio (waste:conceptual open pit resources) 0.81:1
Years 1 to 5 / average LOM copper grade (%) 0.67% / 0.45%
Years 1 to 5 / average LOM gold grade (g/t) 0.30 / 0.26
Years 1 to 5 / average LOM silver grade (g/t) 3.74 / 2.41
Nameplate mill throughput (Years 1 to 5; tpd) 8,000
Nameplate mill throughput (Years 6+; tpd) 16,000
Operating Costs
Total operating cost ($/t processed; incl. royalties) $15.78
C1 cash cost ($/lb copper; net of by-product credits) $1.32
Capital Costs ($M)
Initial capital expenditures $161.4
Expansion capital expenditures $120.6
Total LOM capital expenditures (incl. TMF expansion, sustaining & closure) $527.5
Economic Analysis
Pre-tax undiscounted free cash flow ($M) $1,076.5
Pre-tax NPV8% ($M) $347.0
Pre-Tax IRR 26.8%
After-tax undiscounted free cash flow ($M) $745.3
After-tax NPV8% ($M) $210.7
After-tax IRR 20.3%
Copper price ($/lb) $3.25
Gold price ($/oz) $1,400
Silver price ($/oz) $17.75
Exchange rate (USD/COP) 3,125
Pre-tax values include Colombian mining royalties of 4% of total precious metals revenue and 5% of total copper revenue.
4
PEA Mining Plan
The PEA envisions that the Alacran and satellite pits will be mined using conventional drill, blast
and shovel/truck open pit mining methods. The PEA assumes mining activities will be performed
by a contractor-owned mining fleet for Years 1 to 5 of operation and switching to an owner-
operated fleet in Year 6 and onward.
Mining at the Alacran pit is planned to initially target the high-grade, low-waste strip blocks located
in the centre of the deposit. Three small pushbacks are planned within the first five years of the
operation to ensure consistent high-grade resources are being fed to the mill and maximizing
NPV. During the first five years, copper, gold and silver grades are expected to average 0.67%,
0.30 g/t and 3.74 g/t respectively with a low strip ratio of 0.82:1 including pushbacks. An additional
three pushbacks are planned in the remaining life of mine for the Alacran pit. The deposit is
situated along a ridgeline, which reduces the overall strip ratio and allows for minimal re-ramping
in the pushbacks. Alacran pit outlines are shown below in Figure 2.
In the PEA, mining activity at the Alacran pit is projected to be reduced in Year 17, at which point
part of the mining fleet is planned to start mining the satellite deposits at the Montiel East, Montiel
West and Costa Azul pits. The PEA assumes that these smaller, satellite open pits will be mined
simultaneously in order to provide a sustainable supply of mill feed and increase operational
flexibility. During Years 17 to 23, 8,000 tpd of mill feed is expected from the Alacran pit
complemented by 8,000 tpd from the satellite pits.
The PEA calls for saprolite rock to be mined and a portion of this material to be stockpiled in order
to maintain a set rate of blending with fresh rock prior to being processed through the mill.
5
Figure 1: San Matias site layout showing the Alacran pit, the Montiel East, Montiel West and Costa Azul satellite pits, the mill location
and the TMF.
18220-01 -10-1010
MINE SITE LAYOUT
GENERAL ARRANGEMENT
PITS, STOCKPILES, T.M.F, WATER MANAGEMENT, ETC.
PLAN VIEW
ALACRAN P.E.A.
CORDOBA MINERALS
18220-01
NOT FOR CONSTRUCTION
PRELIMINARY
BWS / AK / HL
TAILINGS MANAGEMENT FACILITY
(ELEV. 173 m) 98.1M cu. m
ALACRAN WASTE DUMP
26.4M cu. m
SAPROLITE STOCKPILE
5M TONNES
MONTIEL EAST PIT
MONTIEL WASTE DUMP
1.2M cu. m
COSTA AZUL PIT
COSTA AZUL WASTE DUMP
0.7M cu. m
WATER COLLECTION
AND TREATMENT
MONTIEL WEST PIT
STOCKPILE
100,000 TONNES
ALACRAN PIT
WATER COLLECTION
AND PUMPING
LEGEND
MAIN RIVERS
RECLAIMED WATER LINE TO MILL
TRANSFER WATER LINE TO TREATMENT FACILITY
SEEPAGE WATER LINE TO TREATMENT
700m BLASTING SET-BACK FROM ALACRAN PIT
OPEN PIT MINING AREA
ORE STOCKPILE
TOPSOIL STOCKPILE
OPEN PIT WASTE ROCK STORAGE
TAILINGS MANAGEMENT FACILITY
858,000
422,000
857,000856,000855,000854,000853,000
421,000420,000419,000418,000417,000416,000
422,000421,000420,000419,000418,000417,000416,000
858,000857,000856,000855,000854,000853,000
1
WATER TREATMENT
WATER COLLECTION
AND PUMPING
EMERGENCY SPILLWAY
SECONDARY STREAMS
EXISTING ROADS
PLANNED SITE ROADS
TAILINGS LINE FROM MILL
WATER COLLECTION
AND PUMPING
PAG WASTE
17.6M cu. m
2019-07-22
A
B
C
D
E
F
1 2 3 4 5 6 7 8
A
B
C
D
E
F
2 50 100 Millimeters
REF. DWG. NO. REFERENCE DRAWING TITLE REV. DESCRIPTION DATE BY CHECK APPR.
DATE
THIS DRAWING MIGHT BE REDUCED FROM ITS ORIGINAL SIZE. DO NOT SCALE
CLIENT:
PROJECT / LOCATION:
TITLE:
SCALE: PROJ. NO. DWG. NO.
134 Inches
DESIGNED BY:
DRAWN BY:
CHECKED BY:
APPROVED BY:
R E V I S I O N SR E F E R E N C E D R A W I N G S
REV. NO.
NOT TO SCALE
1 UPDATED PIT SHAPES, WASTE TONNAGES, TAILINGS SITE DESIGN 2019-07-24 AK
MILL / LABRATORY
CRUSHER
WATER COLLECTION
AND TREATMENT
6
Figure 2: Progressive PEA pit outlines at the Alacran mine
Mineral Processing, Metallurgy and Infrastructure
The process plant has been designed as a conventional milling operation with an initial nameplate
capacity of 8,000 tpd, increasing to 16,000 tpd following a planned processing plant expansion
completed at the beginning of Year 6. The conceptual plant design includes a gravity separation
circuit for initial precious metals recovery prior to a conventional froth flotation circuit. The PEA
assumes that the plant will produce gold-silver doré bars on site and a copper concentrate
containing the remaining precious metals by-products. The copper concentrate is expected to
contain very low levels of deleterious elements, such as arsenic and lead.
The Project process flowsheet includes:
• Primary crushing with stockpile;
• A Semi Autogenous Ball Mill Comminution (“SABC”) circuit, utilizing one Semi Autogenous
Grinding (“SAG”) Mill and one Ball Mill for initial plant throughput, adding a second Ball
Mill during the planned expansion to achieve the higher processing rate;
• Potential for gravity separation of precious metals with Intensive Leach Reactor (“ILR”)
chemical separation to produce doré;
7
• Froth flotation with rougher, scavenger and cleaning stages;
• Thickening and dewatering of final concentrate prior to transport for refining.
Based on preliminary metallurgical test work completed on fresh rock and recent test work to
predict recovery performance of upper (oxidized) zones, the overall copper recovery is expected
to average 78.6%. Gold and silver recoveries for the overall process are expected to average
74.4% and 65.5% respectively. Further metallurgical test work is recommended to optimize
recoveries and confirm the validity of a doré producing circuit from the Ball Mill cyclone underflow.
Copper concentrate output is expected to be approximately 280 to 300 tpd for the first five years
of operation, increasing to approximately 560 to 600 tpd thereafter.
Power to the Project is expected to be supplied via a 15-kilometre, 230 KV powerline connecting
to the Sator SAS 300 MW thermal power plant. The Sator SAS plant is part of a permitted regional
electric grid expansion that includes the currently operating ISA and Gecelca 300 MW thermal
power plants. The Sator SAS plant is expected to be operational within the next three to five years.
The PEA envisions that the road access to the San Matias site will be improved to the town of
Puerto Libertador to allow for increased movement of equipment and materials to and from site.
Any doré produced is expected to be flown out through the Puerto Libertador airport located
approximately 20 kilometres away, and copper concentrate is planned to be loaded on-site and
transported by 60-tonne trucks to port facilities at Tolu (approximately 250 kilometres away) or
Cartagena (approximately 400 kilometres away) for export to international smelters. Both ports
currently support the export of ferronickel from South 32’s Cerro Matoso nickel mine.
Tailings Management Facility (“TMF”)
The PEA envisions that the TMF will be located in Concepción Creek valley, approximately 1.5
kilometres west of the Alacran open pit and will be designed to contain a maximum of 156 million
tonnes of tailings and waste rock material. The initial TMF is designed to contain 43 million tonnes
of tailings material and waste rock. Dam raises are planned for Years 9, 14 and 18 of operations.
The foundation materials in the valley generally consist of low permeability saprolite lying over
low permeability bedrock. The Final Dam is planned to be constructed using non-potentially acid
generating waste rock from open pit mining operations to develop the expanded valley type
impoundment.
The PEA calls for the upstream face of the Final Dam to be lined with a geosynthetic lining system
to minimize seepage from the TMF. The PEA envisions that a foundation drain will be installed in
the base of the Final Dam to collect any potential seepage. The Final Dam in the conceptual TMF
will be raised in several stages using the downstream construction method and c onventional
tailings slurry will be conveyed from the plant via a pipeline. Waste rock will be hauled and placed
in the TMF basin by the mine haul trucks and a dozer. In the conceptual TMF, the tailings slurry
will be su b-aqueously discharged from multiple locations along the dam crests and around the
perimeter of the TMF basin to evenly fill the impoundment. The potentially acid generating (“PAG”)
waste rock is expected to be strategically placed within the TMF basin such that the tailings and
supernatant pond will cover and maintain the PAG waste rock in a saturated state within 6 months
of the waste rock being placed in the TMF.
The PEA envisions that t he TMF will have a permanent water cover over the tailings and waste
rock to keep the waste submerged. A floating pump barge is to be installed at start-up to reclaim
process water from the TMF to the plant for reuse in the process. The TMF concept includes
8
freeboard to temporarily store runoff resulting from the Environmental Design Storm (“EDS”) and
a spillway to safely pass the peak flows resulting from the Inflow Design Flood (“IDF”).
It is expected that the TMF will operate in a water surplus during the wet season and that
supernatant water will need to be treated, as required, and discharged over a portion of the year.
Operating Costs
Copper C1 cash costs are expected to average $2.51/lb including royalties but before precious
metals credits and $1.32/lb net of credits. Total onsite operating costs including royalties are
expected to average $15.78 per tonne processed. Mining costs are expected to average $1.85
per tonne of material mined at the Alacran and satellite pits based on a total of 215.3 million
tonnes of total material moved. Cost contingencies of up to 25% have been applied as additional
buffer in the cost estimates. A breakdown of the unit costs is shown in Table 2 below.
Table 2: San Matias operating cost breakdown.
Operating Cost $/t mined $/t
processed
$/lb copper
payable LOM $M
Mining $1.85 $3.34 $0.45 $398.1
Processing $8.89 $1.20 $1,058.4
G&A $1.47 $0.20 $175.5
Royalties $0.56 $0.08 $66.3
Government royalties $1.52 $0.21 $180.7
Total onsite $15.78 $2.14 $1,879.0
TC/RC & other offsite $2.77 $0.38 $330.5
Total before by-product credits $18.55 $2.51 $2,209.5
By-product credits ($8.80) ($1.19) ($1,048.2)
Total net of by-product credits $9.75 $1.32 $1,161.2
Capital Expenditures
The initial capital expenditures for the Project total $161.4 million, which include site preparation,
construction of the processing plant and TMF, road upgrades and other infrastructure. It is
expected that site construction will occur over a 3-year pre-production period. The PEA assumes
that mobile mining equipment will be supplied by the mining contractor and operated for the first
5 years of operations, after which the equipment will be bought out and converted to an owner-
operated mining fleet beginning in Year 6.
An expansion of the mine, mill and processing facilities is planned to be completed in Year 6 and
is expected to cost $120.6 million, including $46.6 million for the purchase of the owner-operated
mine fleet (including contingency). The Year 6 expansion is expected to increase the nameplate
capacity of the San Matias plant from 8,000 tpd to 16,000 tpd. A breakdown of the PEA life of
mine capital expenditures is shown in Table 3 below.