Cantex Extends Main Zone to Drill Confirmed 2,300 Metres ON Its 100% Owned North Rackla Project, Yukon

Drill Results

CANTEX EXTENDS MAIN ZONE TO DRILL

CONFIRMED 2,300 METRES ON ITS 100%

OWNED NORTH RACKLA PROJECT, YUKON

KELOWNA, BC

,

Sept. 26, 2022

/CNW/ -

Cantex Mine Development Corp.

(TSXV: CD) (OTCQB:

CTXDF) (the "Company") is pleased to provide an update on drilling of the Main Zone at its 100-

percent-owned 14,077 hectare North Rackla claim block in the

Yukon

.

Figure 1.

Map of Main Zone Drilling (CNW Group/Cantex Mine Development Corp.)

Dr.

Charles Fipke

reports

Drilling confirms strike extension of mineralization to northeast along Main

Zone

Cantex is pleased to report the first results from its 2022 drill program at the Main Zone of the North

Rackla project. To date results from three holes have been received. These results confirm that the

Main Zone mineralization continues to the northeast in the Discovery Sector. The results from these

three holes are presented in Table 1.

Holes YKDD22-243 and YKDD22-244 are drilled from pad MZ52A while YKDD22-245 was drilled

from pad MZ52. All these holes intersected mineralization 50 metres beyond drilling completed in

2021, bringing the strike length to 2,150 metres. Additional drilling is now underway further to the

northeast, from which results are awaited, that has extended the mineralization a further 150 metres,

bringing the drill confirmed strike length to 2,300 metres.

The drill collar location of these holes is shown on Figure 1. A cross section through these holes is

presented in Figure 2.

Table 1. Significant results from Discovery Sector

Pad

Dip

Hole

From

(m)

To

(m)

Length

(m)

Silver

(g/t)

Lead

+ Zinc

(%)

Lead

(%)

Zinc

(%)

Copper

(%)

Man-

ganese

(%)

-55

YKDD22-243

159.0

167.0

8.0

19.63

3.97

0.93

3.04

0.05

1.68

185.0

187.1

2.1

71.94

27.57

11.78

15.79

0.05

1.46

MZ52A

-65

YKDD22-244

197.0

206.0

9.0

24.71

9.69

3.13

6.56

0.09

1.76

220.0

221.05

1.05

64.60

24.10

13.45

10.65

0.06

1.55

MZ52

-55

YKDD22-245

48.5

50.5

2.0

40.30

11.49

6.29

5.20

0.02

3.59

58.5

65.5

7.0

37.53

12.13

5.11

7.02

0.14

3.52

78.5

79

0.5

10.65

4.92

1.56

3.36

0.01

0.60

106.5

107.5

1.0

4.31

2.54

0.78

1.76

0.01

0.62

134.0

135.0

1.0

4.55

1.25

0.13

1.12

0.01

0.75

Results have also been received from 8 holes drilled at the GZ Zone. These holes were drilled in

covered areas to help define controlling structures and did not intersect significant mineralization.

Cantex has completed 54 holes on the North Rackla project so far during the 2022 season. Results

from 36 of these holes are still awaited and will be reported when received.

The drill team will shortly go on a two week break as mandated by the Yukon Workers' Safety and

Compensation Board and will be back drilling on

October 7

th

.

Sample Preparation

The drill holes reported in this press release were drilled using HQ (63.5mm) diamond drill bits. The

core was logged, marked up for sampling and then divided into equal halves using a diamond saw on

site. One half of the core was left in the original core box. The other half was sampled and placed

into sealed bags which were in turn placed into larger bags closed with security seals prior to being

transported to CF Mineral Research Ltd. in

Kelowna, BC

.

At CF Minerals the drill core was dried prior to crushing to -10 mesh. The samples, which averaged

over 3kg, were then mixed prior to splitting off 800g. The 800g splits were pulverized to -200 mesh

and a 250g split was sent for assay. Quality control procedures included running a barren sand

sample through both the crusher and pulveriser between each sample to ensure no inter-sample

contamination occurred. Silica blanks were inserted along with certified reference samples. These

quality control samples were each inserted approximately every 20 samples.

ALS Chemex in

Vancouver

assayed the samples using a four-acid digestion with an ICP-MS finish.

The 48 element ME-MS61 technique was used to provide a geochemical signature of the

mineralization. Where lead or zinc values exceeded one percent the Pb-OG62 or Zn-OG62

techniques were used. These have upper limits of 20% lead and 30% zinc respectively. Samples

with lead and zinc values over these limits were then analyzed by titration methods Pb-VOL70 and

Zn-VOL50. Where silver samples exceeded 100 g/t the Ag-OG62 technique was used which has an

upper limit of 1,500 g/t. The over limit analyses contributed to delays in receiving final assay

results.

The technical information and results reported here have been reviewed by Mr.

Chad Ulansky

P.Geol

., a Qualified Person under National Instrument 43-101, who is responsible for the technical

content of this release.

Signed,

Charles Fipke

Charles Fipke

Chairman

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this

release. Information set forth in this news release includes forward-looking statements under

applicable securities laws. Forward-looking statements are statements that relate to future, not

past, events. In this context, forward-looking statements often address expected future business

and financial performance, and often contain words such as "anticipate", "believe", "plan",

"estimate", "expect", and "intend", statements that an action or event "may", "might", "could",

"should", or "will" be taken or occur, or other similar expressions. All statements, other than

statements of historical fact, included herein are forward-looking statements. By their nature,

forward-looking statements involve known and unknown risks, uncertainties and other factors

which may cause the actual results, performance or achievements, or other future events, to be

materially different from any future results, performance or achievements expressed or implied by

such forward-looking statements. Such factors include, among others, risks identified in the

management discussion and analysis section of the Company's interim and most recent annual

financial statements or other reports and filings with Canadian securities regulators. Forward

looking statements are made based on management's beliefs, estimates and opinions on the date

that statements are made and the respective companies undertake no obligation to update forward-

looking statements if these beliefs, estimates and opinions or other circumstances should change,

except as required by applicable securities laws. Investors are cautioned against attributing undue

certainty to forward-looking statements.

Figure 2.

Cross Section Through Drill Pads MZ52 and MZ52A. (CNW Group/Cantex Mine

Development Corp.)

SOURCE

Cantex Mine Development Corp.

View original content to download multimedia:

http://www.newswire.ca/en/releases/archive/September2022/26/c1979.html

%SEDAR: 00010333E

For further information:

Cantex Mine Development Corp, Tel: +1-250-860-8582; Email:

[email protected]

CO: Cantex Mine Development Corp.

CNW 09:00e 26-SEP-22