Canadian Critical Minerals Updates Its Permit Application to Restart the Bull River Mine and Mill
Canadian Critical Minerals Updates Its Permit
Application to Restart the Bull River Mine and
Mill
Calgary, Alberta--(Newsfile Corp. - May 23, 2025) - Canadian Critical Minerals Inc.
(TSXV: CCMI)
(OTCQB: RIINF) ("CCMI"
or the
"Company")
is pleased to provide an update on its application to
restart the Bull River Mine ("
BRM
") project near Cranbrook, BC.
Further to discussion with the Major Mines Permitting Office of the Ministry of Mining and Critical
Minerals of British Columbia ("MMCM"), the Company has decided to modify its current application to
restart the BRM project by combining project phases into one application.
If approved, this will allow the
Company to restart underground mining and milling operations at the same time.
To-date the Company
has advanced its application to restart the BRM project in a phased approach in order to reduce the
costs associated with completion of all detailed engineering studies in support of the application.
The Company is currently working with consultants to complete its application to restart the BRM mine
and mill.
Moose Mountain Technical Services has been engaged to provide a detailed underground
mine plan with estimated completion by early August 2025.
ALS Metallurgical Services has been
engaged to conduct humidity cell testing on tailings that are planned to be produced from milling
operations.
This is
follow-up work from a previous humidity cell testing program already completed.
Humidity cell testing in a laboratory environment simulates the expected metal leaching from a tailings
storage facility over time.
Previously, the Company completed a detailed design of its proposed filtered
tailings facility using Stantec Engineering.
Once all engineering reports are complete, the Company
plans to incorporate them into a Final Permit Application and make its submission to MMCM in Q1
2026.
Originally, under phase one of the restart, the Company sought permission to restart the past-producing
BRM project by processing a large 180,000 tonne surface stockpile of mineralized material through its
existing 700 tonne per day conventional mill and deposit tailings on surface in a dry stack or filtered
tailings facility.
Under phase two, the Company plans to seek permission to restart underground mining,
continue to use the 700 tonne per day mill and begin sending filtered tailings back to the underground as
cemented backfill.
In April 2024, the Company began selling preconcentrated copper, gold and silver mineralized material
that has been upgraded through an ore sorter to New Afton under an Ore Purchase Agreement ("OPA").
To-date the Company has crushed and screened the entire surface stockpile and trucked approximately
7,900 tonnes of pre-concentrated mineralized material to New Afton.
The Company expects to send an
additional 2,100 tonnes of mineralized material to New Afton by the end of August 2025.
The remaining
170,000 tonnes of mineralized fines and rejects from the crushing, screening and sorting of the surface
stockpile will remain at the BRM and will provide an initial feed to the BRM mill for approximately eight
months following restart of operations.
Revenues from the OPA have allowed the Company to significantly reduce payables, offset the costs of
care and maintenance and pay for the additional costs associated with the permit applications without
incurring additional dilution to shareholders.
With the Company's improved financial position, all
remaining engineering studies can be completed in a more sequential and expedited manner. The BRM
project has over $100 million of usable infrastructure and is already connected to grid power and all-
weather roads.
The BRM is being maintained in a dewatered condition with over 22,000 metres of
underground workings readily accessible from surface to a depth of 350 metres.
Ian Berzins, President and CEO of CCMI commented, "Revenues generated from the sale of a portion of
our stockpiled mineralized material have improved the Company's ability to advance the permitting
process in a more expedited manner.
The provincial government has stated the importance of bringing
on new projects in the critical minerals space. The past-producing BRM project is one of the most
advanced mining projects in British Columbia currently not in production.
Combining both phases under
one application should result in better use of resources by First Nations and regulators in the
consultation, engagement and review process."
About Canadian Critical Minerals Inc.
CCMI is a mining company primarily focused on copper production assets in Canada. CCMI's main
asset is the 100% owned Bull River Mine project (150 million lbs of copper) near Cranbrook, British
Columbia which has a Mineral Resource containing copper, gold and silver. CCMI also owns a 10%
interest in XXIX Metal Corp. which holds a 100% interest in the Thierry copper project near Pickle Lake,
Ontario and a 100% interest in the Opemiska copper project near Chapais-Chibougamau, Quebec.
Contact Information
Canadian Critical Minerals Inc.
Ian Berzins
President & Chief Executive Officer
M: +1-403-512-8202
E:
Website:
www.canadiancriticalmineralsinc.com
Caution Regarding Forward-Looking Information
This news release includes certain information that may constitute "forward-looking information" under
applicable Canadian securities legislation. Forward-looking information includes, but is not limited to,
statements about strategic plans, future work programs and objectives and expected results from such
work programs. Forward-looking information necessarily involve known and unknown risks, including,
without limitation, risks associated with general economic conditions; inability to access sufficient
capital from internal and external sources, and/or inability to access sufficient capital on favourable
terms; and other risks.
Forward-looking information is necessarily based upon a number of estimates and assumptions that,
while considered reasonable, are subject to known and unknown risks, uncertainties, and other factors
which may cause the actual results and future events to differ materially from those expressed or
implied by such forward-looking information and the risks identified in the Company's continuous
disclosure record. There can be no assurance that such information will prove to be accurate, as
actual results and future events could differ materially from those anticipated in such information.
Accordingly, readers should not place undue reliance on forward-looking information. All forward-
looking information contained in this news release is given as of the date hereof and is based upon
the opinions and estimates of management and information available to management as at the date
hereof. The Company disclaims any intention or obligation to update or revise any forward-looking
information, whether as a result of new information, future events or otherwise, except as required by
law.
Neither the TSX Venture Exchange nor its Regulation Service Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this new
release.