CORPORATE UPDATE 

JOHN DOWNS RETAINED AS ADVISOR TO CORPORATION  

Bill  McWilliam,  Cascadero  Copper  Corporation’s  President  and  CEO,  welcomes  John  Downs  to  an advisory  role  for  the  Corporation.  Mr.  Downs  brings  invaluable  experience  and  knowledge  to  the advisory position at this time in the Corporation’s development of the Taron cesium prospect. He was a key employee in Cabot Corporation’s Specialty Fluid Division from 1996 to 2014, and now has initiated a business specializing in advising clients with respect to all types of oil well formate brines, drilling, and well completion information (www.formatebrine.com).  Cascadero anticipates, in going forward, that formate brines will be a large business segment.

THE McElroy DRAFT REPORT FOR REAGENT AND UTILITY COST ESTIMATES FOR TARON  CESIUM PRODUCTION 

Cascadero has also received a draft report from Rod McElroy, Ph.D, on the consumption of chemicals and  energy  requirments  to  produce  cesium  hydroxide  (CsOH)  according  to  the  University  of  British Columbia  (UBC)  Hydrometallurgical  Study  flow  sheet  received  by  Cascadero  in  December  2015.  The McElroy report presents reagent and utility cost estimates for production of 3,000 metric tonnes per year (mtpy) of cesium hydroxide (CsOH) at a market grade of 50% solution from Taron drill core TAR‐09‐ 04.

In addition to the 3,000 mtpy cesium hydroxide production target, principal (conceptual) design criteria include:

  • a  resource grade: 0.46% cesium (Cs)
  • cesium recovery to product: 90%

These criteria also envision a process plant with a nominal capacity of 1,760 mtpd of ore at a design capacity of 2,000 mtpd and at 90% availability. The scope for estimation includes all test work, identified reagents, and utilities (water, electric power, steam) required based on the UBC process flow diagram. Excluded are operating labor, ore mining, waste disposal and product marketing as well as all capital costs related to the project and which are now in the planning stages.

Dr. McElroy’s report states, at this  time, that the  total reagent  plus utility costs are ~40% of posted industry prices of cesium hydroxide and indicate a potential for a profitable operation without further beneficial testing.  The dominant, 73% of total reagent plus utility costs are associated with sulphuric

1 | P a g e

acid (58%) and limestone, or lime, for neutralization of the waste stream (15%).  To the extent that acid and neutralization costs can be significantly reduced by process modifications indicates a clear potential for further reduction of reagent costs.

The UBC test data are also interpreted to indicate that for a sulphuric acid leach, a high‐residual acid content is necessary to achieve the high‐cesium extraction.  On this basis, one way to materially reduce acid  consumption  of  the  whole  ore  leach  conducted  at  UBC,  is  to  increase  the  grade  of  feed  to  the chemical  process;  a  process  which  was  conducted  successfully  in  2006  by  SGS  Lakefield  Research  in Peterborough, Ontario.  The SGS Lakefield report indicated an 82% cesium recovery to a concentrate containing 35% by weight of ore fed.  This test work, although it was done on a different sample from that provided to UBC, is similar to the results achieved in the UBC research.

On this basis and with a 16% higher mining rate, the acid and base costs for chemical processing can conceptually be further reduced by up to 65%, based on the units of cesium hydroxide product.  This would result in a total reagent plus utilities cost of ~21% of Dr. McElroy’s base case.  Based on these initial  test  work  results  the  Cascadero  is  planning  to  review  and  implement  the  test  work recommendations of Dr. McElroy.

Please note that these estimates are of a preliminary or scoping level but are consistent with the UBC test work database. The Company is also withholding this report from distribution at this time as the author, Dr. McElroy, has recognized and recommended several options that may be material to reducing the  cost  of  producing  cesium  hydroxide  and  it  appears  that  significant  reductions  may  be  possible, subject to positive results of additional process test work.

A core drilling program, based on ongoing geostatistical modelling scheduled for the end of July, is also planned  with  an  objective  of  defining  a  NI  43‐101  compliant  inferred  resource  of  8,000,000  to 10,000,000 metric tonnes or 11.5 to 14.5 years of production.

REGBERG LTD ― OPTION EXCERCISE 

Regberg Ltd. has exercised its option to acquire an additional 5% interest in the SESA Holdings LLC (LLC) Joint Venture for US$175,000 increasing Regberg’s interest to 30% and decreasing Cascadero’s interest to 70%. There are no other options to any party for further dilution of Cascadero’s interest in SESA.

This news release, and contained technical data, were reviewed and approved by David Trueman Ph.D, P.Geo., qualified person for the Company.

Bill McWilliam  CEO   Cascadero Copper Corporation  Email = [email protected] O = 604.924.5504  C = 604.999.0391 