Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

CBR.V ·

Cabral Gold Announces Positive Prefeasibility Study on the Gold-in-Oxide Starter Operation at the Cuiú Cuiú Gold Project, Brazil with After-Tax IRR of 47.3%

Economic Studies

Cabral Gold Announces Positive Prefeasibility

Study on the Gold-in-Oxide Starter Operation

at the Cuiú Cuiú Gold Project, Brazil with

After-Tax IRR of 47.3%

Vancouver, British Columbia--(Newsfile Corp. - October 21, 2024) -

Cabral Gold Inc. (TSXV: CBR)

(OTC Pink: CBGZF) ("Cabral" or the

"

Company

") is pleased to announce a positive Prefeasibility

Study ("PFS") on the development of near-surface gold-in-oxide material at the Cuiú Cuiú gold district in

Brazil. The PFS, which was led by Ausenco do Brasil Engenharia Ltda. ("Ausenco") confirms the Cuiú

Cuiú gold-in-oxide starter project provides a high return and a low capital entry point to mine gold at the

prospective Cuiú Cuiú District.

Highlights

Base Case after-tax IRR of 47.3% and after-tax NPV

5

of US$25.2 million for an initial 720,000

tonne / yr starter operation using open-pit mining of oxidized gold mineralization and heap-leach

processing, and assuming a gold price of US$2,250 / oz

In the case of the current Spot Gold

1

price - US$2,710/oz, the IRR increases to 82.6% and the

after-tax NPV

5

to US$49.3 million

The PFS has a 4.5-year mine life with strong cashflows in the early years and an 18-month

payback

2

The initial in-pit resources have very favorable geometry due to the shallow and high-grade nature

of the ore. The starter pit (planned for the first seven months) is expected to mine shallow, higher

grades with a very good strip ratio, containing an estimated 418,000 tonnes of ore @ 1.38 g/t

average gold grade

3

with just 56,000 tonnes of waste

Average annual gold production in the first 2 years of operation after commissioning is 19,700

ounces per year at an all-in sustaining cost ("AISC") of US$1,003 / oz

Low development Capex of US$ 37.4 million, including 10% allowance on most quantities and

20% Contingency

Significant potential exists to add nearby resources of similar high-value oxidized mineralization

with further step-out and infill drilling at the nearby Machichie and Machichie NE targets, where

recent drilling returned 11m @ 33g/t gold

Beyond the attractive initial financial outcome, the project 1) provides future expansion options for gold-

in-oxide production, 2) provides pre-stripping exposing the underlying primary gold mineralization

reducing future strip-ratios and mining costs, 3) establishes an initial operating platform to more easily

transition into primary ore production, and 4) generates cash to fund an aggressive and sustained drilling

program aimed at expanding the oxide resources as well as the larger underlying primary ore resource

base at Cuiú Cuiú. The company plans to immediately commence detailed engineering ("DE") and

financing activities with the objective of achieving an investment decision and financial close in Q2, 2025

with initial gold production targeted for mid-2026.

During the next six months the company plans to address further potential improvements identified in the

course of the PFS and complete further shallow drilling which it expects will add new gold-in-oxide

resources. These additions have the potential to materially increase the size, scope and mine life of the

project.

Alan Carter, the President and CEO of Cabral commented,

The PFS confirms an economically attractive starter heap-leach and open-pit mining operation

targeting the weathered gold-in-oxide mineralization at Cuiú Cuiú and outlines a pathway for funding

the evaluation and drill testing of numerous targets within the Cuiú Cuiú district. With capital

expenditures of just US$37.4 million and an average operating cash cost

4

of $1,154/oz of gold, the

initial gold-in-oxide project is expected to generate strong cashflows. This cash flow will be used to

fund an aggressive program of drilling directed towards the company's principal objective of

expanding the much larger primary hard rock resource base and drill testing the numerous targets

within the Cuiú Cuiú district.

The PFS has identified several areas that should further improve the projected financial returns.

Meanwhile, further drilling could lead to significant growth of the gold-in-oxide resource base and

hence the mine life. In particular, this may lead to additional Indicated resources from Machichie into

the mine sequencing as well as the upgrading of Inferred resources at Central to the Indicated

category for inclusion in the mine plan.

The company now plans to move forward with the completion of detailed engineering work, further

resource drilling, modelling designed to grow the resource base and securing the necessary project

financing, allowing for an investment decision during Q2 2025.

Overview

Cabral Gold has a 100% interest in the Cuiú Cuiú gold project which is located in Para State in northern

Brazil, immediately adjacent to G Mining's recently commissioned Tocantinzinho gold mine. Cuiú Cuiú

was the largest producer of placer gold during the 1980's Tapajos gold rush. The project area comprises

an entire gold district.

In 2021, the company identified the economic potential of several oxide gold-in-oxide blankets directly

overlying and resulting from the weathering of the higher-grade primary gold deposits at Cuiú Cuiú. An

internal desktop study confirmed that these oxide resources could support the development of an initial

simple and low-cost starter production base that could be developed in the short term based on the

existing Trial Mining Licenses. Furthermore, this study suggested that such an operation could produce

significant cash flows, which could allow the Company to self-fund an aggressive and sustained drill

program aimed at significantly expanding the global resource inventory. Due to the strength of the

business case, the Company proceeded directly to a PFS level study with a scope to assess short-term

pathways to production that were aligned with Cabral's financial capacity.

Resources have been determined for two main gold deposits, MG and Central, and three smaller gold

deposits, JB, Central North, and the oxidized mineralization at PDM. In late 2022, SLR Consulting

(Canada) Ltd. ("SLR") calculated resources for the project which at that time comprised Indicated

resources of 21.6Mt @ 0.87 g/t gold (604,000 oz) and Inferred resources of 19.8Mt @ 0.84 g/t gold

(534,500 oz). In addition, three more significant gold discoveries (Machichie Main, Machichie NE and

PDM primary basement) as well as over 50 other early-stage exploration targets had insufficient drill

spacing to determine resources in 2022.

Economic Analysis

The gold-in-oxide project exhibits strong financial metrics across a range of gold price scenarios (Table

1). IRR's highlight the potentially attractive returns and rapid payback of the project (Figures 1 and 2).

US$M

Low Case

Base Case

High

Spot

2,750 US$/oz

Gold Price (US$/oz)

2,000

2,250

2,500

2,710

2,750

After Tax NPV

5

11.9

25.2

38.3

49.3

51.4

After Tax IRR

26.3%

47.3%

66.7%

82.6%

85.5%

Payback (years)

2.0

1.5

1.1

0.9

0.9

Average annual EBITDA (First 24 months)

19.5

23.8

28.1

31.7

32.4

LOM EBITDA

62.1

79.5

96.9

111.5

114.3

LOM After Tax Cashflow

17.0

32.8

48.3

61.3

63.8

Table 1. Key results of PFS financial analysis and sensitivities to commodity prices

Figure 1. Graph showing gold produced and production costs by year

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/3900/227247_b1181f6d545858c8_002full.jpg

Figure 2. Monthly gold production and project payback

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/3900/227247_b1181f6d545858c8_003full.jpg

PFS - Detailed Results

The following tables (Tables 2 and 3) provide both key assumptions used to complete the financial

analysis and the primary operational statistics for the project.

Operational Assumptions

UOM

Contained Gold

oz

83,762

Mill and Heap Leach Capacity

t/annum

720,000

Monthly Plant Feed

tonnes

59,685

LOM Mined Grade

g/t

0.81

Strip Ratio

Waste:Ore

0.93

LOM Ore Mined

tonnes

3,225,866

LOM Material Movement

tonnes

6,217,364

Average Gold recovery

%

87.0%

Production

UOM

Mine life

Years

5

Gold Production (First 24 months)

oz

35,826

LOM Gold Production

oz

72,478

Average Annual Production (4.5 year mine life)

oz

16,106

Project Costs

Pre-production Capital Expenditure

US$

37,370,444

Sustaining Capital Expenditure

US$

4,305,851

LOM Average Site Operating Costs

US$/tonne ore

23.2

LOM Average Site Operating Costs

US$/oz

1034.7

LOM Average AISC

US$/oz

1,228

Table 2. Economic analysis summary

Commercial Parameters

UOM

Exchange Rate

USD:BRL

5.6

Corporate Tax Rate

%

25.0%

Social Tax

%

9.0%

SUDAM Tax Reduction

%

75.0%

Gold Royalty Osisko

%

1.0%

Gold Royalty Sandstorm

%

1.5%

Selling and Refining Costs

US$/oz

30.0

Table 3. Key assumptions

Resources

Overlying the primary gold mineralization at Cuiú Cuiú is an extensive zone of highly oxidized and

weathered intrusive saprolite material ("Saprolite"). Above the Saprolite, gold is present in an erosional

blanket of colluvium and other poorly consolidated sediments ("Blanket"). The PFS focuses on the

Indicated Resources within the Saprolite and overlying Blanket, where the relatively soft or poorly

consolidated material is easily excavated, and gold is highly amenable to heap leaching.

Drilling subsequent to the 2022 SLR estimate within oxidized mineralization has been used to determine

an updated resource model for the PFS. This includes Central and MG 2023 infill and step-out drilling as

well as infill and step-out drilling to determine an inaugural Machichie oxide resource, and existing

inferred resources at PDM.

This resource estimates do not include resources in the primary zone of mineralization, which account for

approximately 80% of the total resources at the Cuiú Cuiú project. The resource estimates were

prepared based on drilling completed prior to March 2024 and do not include approximately 3,693m of

RC drilling and 1,062m of diamond drilling completed since. As such, Cabral has elected to update

resources and estimate reserves in the subsequent phase prior to construction decision.

Inferred Resources are not considered as part of the PFS study. Indicated and Inferred Resources

across four known deposits are shown in Table 4.

Cut-off

Grade

Inferred Resources

Indicated Resources

0.1 g/t

Tonnes

Grade

Ounces

Tonnes

Grade

Ounces

MG

3,142,921

0.223

22,508

8,857,901

0.477

135,855

Central

3,746,684

0.408

49,151

2,255,288

0.497

36,028

Machichie

3,732,000

0.498

57,849

-

-

-

PDM

1,600,000

0.430

22,100

Total

151,608

171,883

Table 4. Indicated and inferred resources of oxide material only

Notes:

(1)

All estimates of Mineral Resources have been prepared in accordance with National Instrument 43 - 101 - Standards of Disclosure for

Mineral Projects ("NI 43-101").

(2)

The effective date is October 9, 2024.

(3)

The independent and qualified persons ("QPs") for the mineral resource estimate, as defined by NI 43-101, are Volodomyr Myadzel (P.Geo)

Principal Geological Consultant of VMG Consultoria e Solucoes Ltda. (for MG and Central resources) and Walter Dzick (P.Geo) Principal

Geological Consultant of Dzick Geosconsultants (for Machichie)

(4)

Resources are pit constrained and presented undiluted. These mineral resources are not mineral reserves.

(5)

Mineral Resources are reported at a 0.1 g/t Au cut-off grade and constrained within a $2000 pit shell.

Mining

The PFS contemplates open-pit mining using conventional methods. Initially, ore will be sourced from

two mining areas. The Moreira Gomes (MG) pit accounts for approximately 84% of the run of mine

(ROM) ore with the balance coming from the higher-grade Central Pit, approximately 6 km by road from

the location of the ROM pad. Figure 3 shows the various material movement rates for each year.

Figure 3. Material movement schedule

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/3900/227247_b1181f6d545858c8_004full.jpg

Pit designs were completed at a gold price of $2,000/oz with a key driver being to maximize IRR and

margin and shorten payback and provide short-term cashflow to drive further development of the district.

The pit designs incorporated 5m bench heights and ramps of 10 m widths. Geotechnical test work

supported inter-ramp angles of 70 degrees with total pit angle of 45 degrees (including ramps).

Mining will be done using an excavator in the overhand position, loading a fleet of 25 to 30-tonne trucks

supported by a front-end loader. The oxidized resources occur within loose, weathered, blanket material

which can be mined using a dozer ripper without need for drilling and explosives.

Mining activities will likely be outsourced to one of the many full-service contract miners operating in the

Para State. Contract mining arrangements will include the provision of the entire mining fleet, including

operating labor and relevant maintenance services. Cabral will provide the fuel required to operate the

fleet from a mine site storage and dispensing facility.

Ore from the open pits will be delivered to a ROM pad within 200 meters from the exit of the MG pit.

Metallurgical results

Metallurgical test work was completed at Kappes Cassiday and Associates (KCA) in Reno NV on six

samples of oxide material from the MG and Central deposits

5

. KCA ran a series of tests on each

composite including coarse and fine milled bottle roll leach tests, compacted permeability tests, and

column leach tests.

Gold extractions in the bottle-roll leach tests generally exceeded 90% with a maximum recovery of 98%

achieved after 336 hours of leaching.

Column leach tests were conducted using material crushed to 100% passing 50 millimetres and

agglomerated with 15 to 20 kg/t of cement. To simulate the height of the proposed leach pads, the

material was loaded into 5-metre-tall, 8-inch (203 mm) diameter columns, which were then leached for

86 to 112 days with a cyanide solution.

In general, gold recoveries within the 5-metre columns were excellent, with the majority of ultimate leach

extractions achieved within the first 40 days of the cycle. All MG ore types reported high gold extraction

rates, all in excess of 90%, while Central Saprolite material reported lower but still robust gold

extractions in the low - mid 70% range (Table 5). Based on these test results and our understanding of

the ore types, Ausenco has determined the following heap leach recoveries for the different ore types

based on a 60-day leach cycle, using on/off operation.

Processing recovery using On/Off pads

% of Resources

6

% Recovery

MG Blanket

49

88.0

MG Saprolite

35

90.5

Central Blanket

6

91.0

Central Saprolite

10

72.5

Table 5. Processing recoveries by ore type

Processing

An average of 2,000 tpd of mineralized material will be treated by the Cuiú Cuiú processing plant. The

process plant will consist of a mineral sizer (MMD Sizer) fed from a ROM pad, producing an ore stream

at an 80% passing size of 50 mm (2"). The Crusher discharge will be agglomerated using cement and

barren leach solution and fed by portable conveyors to the on/off leach pads. There will be 4 leach pads

each with a capacity of 59,178 tonnes at 5 meters of stacked ore height. One or two pads will be

leaching at any open time at an irrigation rate of 12 L/h/m

2

. Pads not being leached will be in the

process of being prepared for leaching or being cleaned of spent ore. The leach cycles will average 60

days.

Pregnant leach solution (PLS) will be pumped to the carbon-in-column (CIC) circuit at an average

flowrate of 215 m

3

/h, targeting a loaded carbon Au grade of 2,500 g/t, which will be processed in a 1.5

tonne capacity Adsorption/Desorption and Recovery (ADR) plant. The ADR plant will consist of acid

wash column, elution column, carbon regeneration kiln, electrowinning cell, sludge filter press, sludge

drying oven and smelting furnace.

Once the leach cycle is complete, the pads will be completely rinsed during a 14-day period, and if

required, the solution will be detoxified using lime and hydrogen peroxide prior to initiating the rinsing

process. The current flowsheet for the project is shown in Figure 4.

Figure 4. Process flow sheet

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/3900/227247_b1181f6d545858c8_005full.jpg

Access and Infrastructure

The Cuiú Cuiú project is located approximately 195 km southwest of Itaituba, a town on the Tapajós

River. The Cuiú Cuiú village lies 60km North of the regional road BR-163, which is the main supply route

for the world-scale Tocantinzinho Gold Mine. The Cuiú Cuiú access road will require an upgrade to an

all-weather gravel road to accommodate year-round servicing of the mine using 20-25 tonne loads.

The Cuiú Cuiú township is serviced by a 1,000-meter-long unpaved airstrip maintained by the company.

It provides air access to Itaituba, the project's regional supply/service town.

Cabral's main camp is located in the village of Cuiú Cuiú, adjacent to the project site. The village

consists of 80 houses and, in 2022, had a population of up to 200 families. The PFS assumes the

addition of additional lodging and other support facilities to accommodate an additional 60 workers

during both the construction and production phases.

Power for the village and the project will be provided by a diesel generator bank.

One of the benefits of a

heap leach operation is the relatively low energy intensity and a lack of need to build grid connection

infrastructure at this early stage.

Mining Permits

The Project is predicated on the current Trial Mining Licenses, which include a limit in ore processing of

300,000t/year project area. In late 2023, a request was made to increase the processing rate under the

Trial Mining License to 500,000t/year. This request received a positive technical review

7

and now awaits

final approval through a vote from the Federal Directors of the ANM later in 2024 or early in 2025. Once

granted, this Trial Mining License will be valid until November 2027.

Applications for the environmental license on the full mining license were made in December 2020, and

SEMAS/PA is expected to finalise this application in early 2025. This will support the issue of the

Preliminary Licence (LP) in late 2025 and, subsequently, the Installation Licence (LI) in late 2026 on the

full mining license. This will allow for an increase in production volumes as proposed in the PFS

production plan from 500,000t/year in 2026 to 720,000t/year in 2027.

Operating Costs

Operating costs were derived using key operating design parameters, unit cost assumptions and

estimates for manning and indirect costs. Pricing for reagents and consumables was solicited from

qualified local suppliers and reflects the expected pricing for the project.

Mining costs were based on offers received from suitably qualified Civil Engineering companies offering

contract mining services. The proposals included a complete service, including equipment hire,

operating staff, and mobilization and demobilization. Cabral will supply fuel to the mining fleet. The

unitized cost of the complete service is estimated at US$4.15/tonne of material moved. Following a

more detailed negotiation with preferred contract miners, a firm figure will be available in the next phase.

A detailed breakdown of the Mine's operating costs is shown in Table 6.

Item

LOM

US$ M

LOM

US$/oz

Mining

25.8

356

Processing

47.1

650

Site G & A

2.0

28

Selling Costs

2.2

30

Royalties

6.4

89

Operating Cash Costs

83.6

1,154

Sustaining Capital Expenditure

5.4

75

AISC

89.0

1,228

Table 6. Operating costs breakdown

Capital Costs

The capital cost estimate was compiled based on the proposed plant design by Ausenco.

Approximately 70% of the direct costs within the PFS capital cost estimate are based on supplier

quotations.

A priority for the detailed engineering phase is finalizing these costs through detailed engagement and

negotiation with preferred suppliers.

The total Initial capital cost estimate is US$37.4 million including a 10% allowance on all materials and a

20% Contingency on all direct and indirect Costs. A detailed breakdown of the initial capital costs is

shown in Table 7.

Area

Detail

US$

Process Plant

Heap Leach Pads

7,918,623

Process Equipment

8,596,291

Infrastructure

Onsite

2,778,340

Offsite

1,492,930

Earthworks

4,826,716

Indirect Costs

4,954,958

Owners Costs

574,179

Project Contingency

6,228,407

Total Initial Capital Expenditure

37,370,440