Mont Sorcier Optimization Studies Delay Bankable Feasibility Study, Key ESIA filings Remains on Schedule

Economic Studies Permits & Approvals

Press Release

July 15, 2026

61,755,191 shares issued and outstanding

Mont Sorcier Optimization Studies Delay Bankable Feasibility Study,

Key ESIA filings Remains on Schedule

ROUYN-NORANDA, QUÉBEC- Chibougamau Independent Mines Inc. (CBG-TSX-V in Canada, CLL1-Frankfurt, Stuttgart,

Berlin and Lang & Schwarz Stock Exchanges in Germany, CMAUF-OTC in the US), herein called Chibougamau, is pleased

to report that Cerrado Gold Inc. (CERT -TSXV, CRDOF-OTCQX) (Cerrado) have elected to extend the completion date on

the Bankable Feasibility Study at its Mont Sorcier high grade iron ore deposit in the Chibougamau region of Quebec

where Chibougamau owns a 2% GMR royalty. Cerrado intends to review numerous optimization and trade off

opportunities that have been identified during the BFS process as having the potential to materially enhance the overall

value of the project.

Highlights of the Optimization and Trade Off opportunities discussed in the Cerrado Gold press release.

• Optimization opportunities to be incorporated into the Mont Sorcier Feasibility Study, this work will extend the

date of completion of the BFS.

• Optimization will focus on:

o Enhanced Mine plan to reduce the overall strip ratio.

o Tailings Dam construction.

o Capital cost and operating cost review in light of ongoing regional inflation.

o Study of the trade – offs in concentrate quality vs premium price.

• Complete a modest drill program in Q3/2026 to enhance the mine plan by upgrading additional resources.

Mont Sorcier Feasibility Updated Timeline

• Cerrado has continued to advance the feasibility study for the Mont Sorcier iron ore project over the past number

of quarters and in doing so have identified opportunities to optimize project economics and reduce both capital

and operating costs despite the industry wide inflation.

• The most significant opportunity to enhance the project has been identified in the overall mine plan by covering

a modest amount of currently inferred resources to measured resources within an area to the east of the current

planned pit. This material should be shallower and therefore reduce stripping and tailings management costs

over the life of the mine. This drill program is scheduled to occur in Q3/26.

• Cerrado reports that capital and operating cost estimates are currently seeing a material impact from rising

inflationary pressures and therefore the optimization studies will focus on the life of mine tailings dam

construction and other project infrastructure needs to reduce the overall size and construction material required

for the project.

2

• Cerrado will conduct trade off studies to commence the operation producing a 65% grade iron concentrate

versus the currently planned 67% grade iron concentrate. Cerrado reported that the current price premium for

the 67% iron ore concentrate over the 65% iron ore concentrate may not sufficiently justify the additional capital

and operating costs to deliver the premium product.

• The 65% product remains highly desirable in the market receiving a 20% premium to the 61-62% ion concentrate

index and the 67% concentrate garner an approximately US$20/tonne premium to the 65% Index as published

by leading industry forecasters, subject to specific concentrate characteristics. The lower price could be offset

by a higher weight recovery in the concentrator plant to deliver high levels of production with a simplified flow

sheet, thereby reducing capital and operating costs.

• Cerrado has not provided an exact date for the final completion of the Bankable feasibility study pending the

completing of the drill program.

• Cerrado does not expect the optimization studies and trade off studies to materially impact the timing of the

Environmental and Social Impact Assessment (ESIA), which is expected to be filed in Q2/2027. This is a key

milestone for the project as the submission initiates the permitting process, and Cerrado believes permits

could be granted around year end 2028, suggesting construction could commence in Q1/2029.

Please see Cerrado’s press release dated July 15, 2026 available here for more details.

David Christie, P.Geo., consultant to Chibougamau, in his capacity as a Qualified Person (Q.P.) under Ni 43-101, prepared

the information that forms the basis of this written disclosure utilizing the information in Cerrado Gold Inc.’s press

release dated July 15, 2026.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the

TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.

We Seek Safe Harbour.

CUSIP Number 167101 203

LEI 529900GYUP9EBEF7U709

For further information, contact:

Jack Stoch, P.Geo., Acc.Dir.

President & CEO

Chibougamau Independent Mines Inc.

86, 14th Street

Rouyn-Noranda, Quebec Canada J9X 2J1

Tel.: 819.797.5242

Fax: 819.797.1470

[email protected]

www.chibougamaumines.com

Caution Regarding Forward-Looking Statements

Certain statements included in this press release may constitute “forward -looking statements” within the meaning of

applicable Canadian securities laws. Except as may be required by such laws, Chibougamau Independent Mines Inc.

(“Chibougamau”) does not undertake any obligation to update or revise any forward-looking statements, whether as a

result of new information, future events or otherwise. Forward-looking statements, by their very nature, are subject to

numerous risks and uncertainties. As a result, ac tual results could differ materially from Chibougamau’s expectations

expressed in or implied by such forward-looking statements. No assurance can be given that any events anticipated by

the forward-looking statements will materialize, or if any of them do, what benefits Chibougamau will derive therefrom.

Numerous risk factors which may cause actual results to differ materially from expectations expressed in or implied by

the forward-looking statements are discussed in Chibougamau’s annual information form f or the 2025 fiscal year filed

with the Canadian securities regulatory authorities, available on SEDAR+ at www.sedarplus.ca and on Chibougamau’s

website at www.chibougamaumines.com. Chibougamau cautions readers that such risks are not the only ones that could

impact it. Additional risks and uncertainties not currently known to Chibougamau or that Chibougamau currently deems

3

to be immaterial may have a material adverse eff ect on Chibougamau’s business, financial condition, and results of

operations. Given these risks and uncertainties, Chibougamau cautions investors and others against placing undue

reliance on such forward-looking statements as a prediction of future results or for any other purpose. This press release

does not constitute or form a part of any offer or solicitation to purchase or subscribe for securities in the United States.

The securities referred to herein have not been and will not be registered under the Securities Act of 1933, as amended

(the “1933 Act”), or with any securities regulatory authority of any state or other jurisdiction in the United States, and

may not be offered or sold, directly or indirectly, within the United States or to, or for the a ccount or benefit of, U.S.

persons (as such term is defined in Regulation S under the 1933 Act), except pursuant to an exemption from or in a

transaction not subject to the registration requirements of the 1933 Act.