Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

CAN.V ·

Canadian Gold Resources Secures Permits for Exploration Bulk Sample at Lac Arsenault

Permits & Approvals Metallurgy & Processing

Canadian Gold Resources Secures Permits for

Exploration Bulk Sample at Lac Arsenault

Dieppe, New Brunswick--(Newsfile Corp. - July 15, 2025) - Canadian Gold Resources Ltd. (TSXV:

CAN) ("Canadian Gold" or the "Company") is pleased to announce that it has received all required

permits from the Government of Québec to proceed with a bulk sampling program with plans to test

between 5,000 to 10,000 tonnes of mineralized materials at its 100%-owned Lac Arsenault Gold

Project, located in the Gaspé region of eastern Québec. The bulk sample is intended for exploration

purposes only and is not considered a production decision.

As a condition of the permit, the Company is required to drill three (3) shallow water monitoring wells in

the vicinity of the proposed sampling area to identify potential groundwater presence. If water tables are

encountered, baseline water quality testing will be conducted both before and after the program.

Canadian Gold fully supports this requirement as part of its commitment to responsible exploration and

environmental stewardship.

Next Steps

With permits secured, Canadian Gold will now begin preparations for mobilizing personnel and

equipment to site. In the coming weeks, the Company will finalize agreements with drilling, excavation,

and haulage contractors, complete the required water wells, and install temporary infrastructure to

support safe operations near the Baker and Mersereau veins. Once site preparation is complete,

material sampling is anticipated to commence and continue for approximately three weeks. The

sampled material will be transported to a third-party facility for off-site processing and analysis. Updates

will be provided as results become available, including recoveries and implications for future exploration

planning.

Management Commentary

Ron Goguen, President & CEO of Canadian Gold, commented:

"

Receiving this permit is a major milestone in the advancement of our Lac Arsenault Project.

This program is designed to evaluate the technical and geological characteristics of the near-

surface mineralization. Historical work conducted by Imperial and Esso Minerals in the 1970s

reported a historical estimate of approximately 40,000 tonnes grading 15.43 g/t gold and 197 g/t

silver (Stevenson, L., 1975, Geological Report on the Lac Arsenault Property, Esso Minerals

Canada). A subsequent 1996 report revised the estimate to 199,580 tonnes grading 9.59 g/t gold,

or approximately 61,536 contained ounces (Côté, R., 1996, Lac Arsenault Project Resource

Evaluation, Unpublished Internal Report). While these historical estimates do not comply with

current CIM standards, they indicate strong historical interest in this high-grade system.

Additional core drilling, systematic surface sampling, and database verification will be required

to validate the data and assess whether a current resource can be defined.

"

Clarification on Economic Potential

While Canadian Gold is encouraged by the opportunity to generate technical and metallurgical data from

the bulk sample, no economic analysis has been completed, and there are no mineral reserves at Lac

Arsenault. Any references to possible revenue from sample processing are entirely speculative and do

not demonstrate economic viability. There is no production decision and no feasibility study has been

conducted. Should positive results occur, proceeds may be allocated toward working capital, additional

exploration, or future shareholder returns, but no production decision or dividend policy has been made

at this time. There is no assurance that results will support future exploration or development decisions.

Figure 1 - Aerial view of the Lac Arsenault Project showing the Baker and Mersereau vein system

areas. The upcoming bulk sample will be extracted from these zones.

To view an enhanced version of this graphic, please visit:

https://images.newsfilecorp.com/files/11663/258860_96b60e43f467fb2b_001full.jpg

Historical Resource Estimate Disclosure (NI 43-101 2.4)

The Company refers to the following historical estimates:

Stevenson, L. (1975) - Geological Report on the Lac Arsenault Property, Esso Minerals Canada:

40,000 tonnes @ 15.43 g/t Au and 197 g/t Ag

Côté, R. (1996) - Lac Arsenault Project Resource Evaluation, Unpublished Internal Report:

199,580 tonnes @ 9.59 g/t Au (approx. 61,536 contained oz Au)

These historical estimates were based on underground sampling and trenching using manual polygonal

methods. The estimates are relevant as they reflect historical interpretations, but they pre-date NI 43-101

and do not comply with current CIM Definition Standards. A Qualified Person has not completed

sufficient work to classify the estimates as current mineral resources or mineral reserves. The Company

is not treating the estimates as current, and further verification is required.

To bring these historical estimates into compliance with current CIM standards, the Company anticipates

conducting:

Systematic diamond drilling to confirm historical grade and geometry of the mineralized zones;

Verification sampling of archived and in-situ material, if available;

Construction of a validated digital geological model based on modern logging and QA/QC

procedures;

Density determinations and geostatistical analysis in accordance with current best practices;

Independent resource estimation by a Qualified Person using current CIM categories and

estimation methods.

The Company believes the planned exploration bulk sample will provide critical geological, grade

continuity, and metallurgical information to support this process.

About the Lac Arsenault Project

The Lac Arsenault Project is located in Québec's Gaspé region and hosts multiple high-grade

epithermal-style vein systems including the Baker, Mersereau, and Dunning veins. The project lies along

the Grand Pabos Fault, a regional structure within the Gaspé-Newfoundland tectonic belt that shares

characteristics with other productive gold systems, such as the Cadillac-Larder Lake Fault Zone (Abitibi)

and the Cape Ray-Valentine Lake Shear Zone (Newfoundland), which are known to host multi-million-

ounce deposits.

Surface Sample Highlights

Baker Vein

Sample ID

Au (g/t)

Ag (g/t)

Pb (%)

BVA2025-004

28.9

306

–

BVA2025-006

22.9

399

17.8

BVA2025-008

5.32

452

25.7

Historical*

32.83

–

–

Historical*

15.43

197

6.6

Mersereau Vein

Sample ID

Au (g/t)

Ag (g/t)

Pb (%)

MERS-1

25.5

447

18.4

Historical*

39.7

77.3

0.88

Historical*

13.4

109

4.69

Historical*

5.16

194

5.13

* Historical results are cited from Stevenson (1975). These assays are not compliant with NI 43-101 and are provided for reference only. Surface

samples are selective in nature and may not reflect the average grade or continuity of mineralization.

Note: The 2025 surface sample results shown above were previously disclosed in the Company's news release dated July 9, 2025, which included

complete QA/QC protocols and analytical methods in accordance with NI 43-101.

The purpose of the permitted bulk sample is to evaluate grade continuity, test metallurgical recoveries,

and gather data to inform future exploration and development decisions. The Company cautions that this

bulk sampling initiative is not based on a feasibility study of mineral reserves demonstrating economic or

technical viability. As such, the technical and economic outcomes are uncertain, and there is a higher

risk of failure. The bulk sample program is exploratory in nature.

About Canadian Gold Resources Ltd.

Canadian Gold Resources Ltd. is a Canadian junior exploration company advancing a portfolio of

precious metals projects in Québec. The Company's flagship asset is the Lac Arsenault Project, where a

fully permitted bulk sampling program of up to 10,000 tonnes is now ready to get underway. Canadian

Gold also holds interests in other highly prospective properties in the Gaspé Peninsula and remains

committed to discovery-driven growth.

Qualified Person Statement:

The scientific and technical information in this news release has been reviewed and approved by Mark

Smethurst, P.Geo., a Director of Canadian Gold and a Qualified Person as defined under NI 43-101.

For Further Information, Please Contact:

Ron Goguen

President & CEO, Canadian Gold Resources Ltd.

[email protected]

+1 (506) 383-4274

Investor Relations

[email protected]

Forward-Looking Statements

This news release contains forward-looking statements within the meaning of applicable securities laws.

These include, but are not limited to, statements regarding exploration plans, the timing and execution of

the bulk sample program, and the potential results or economic implications of the program. Forward-

looking statements are based on numerous assumptions and subject to known and unknown risks. There

is no assurance that the bulk sample will achieve its intended objectives or lead to a compliant resource

estimate or economic development. Readers are cautioned not to place undue reliance on such

statements. The Company disclaims any obligation to update or revise forward-looking statements

except as required by law.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is

defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy

or accuracy of this release.

To view the source version of this press release, please visit

https://www.newsfilecorp.com/release/258860