Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

CAD.V ·

Colonial Coal Annou Nces Results of up-Dated Preliminary Economic Assessment FOR Its Huguenot Project

Economic Studies

LEGAL_29421486.2

COLONIAL COAL INTERNATIONAL CORP.

Suite 200 -595 Howe Street, Vancouver, British Columbia, Canada, V6C 2T5

Telephone: (604) 568-4962

PRESS RELEASE

COLONIAL COAL ANNOU NCES RESULTS OF UP-DATED PRELIMINARY

ECONOMIC ASSESSMENT FOR ITS HUGUENOT PROJECT

Vancouver, B.C., Canada – July 10, 2018 – Colonial Coal International Corp. (TSX-V: CAD) (the

“Company” or “ Colonial Coal ”). David Austin, Colonial Coal’s President and CEO, is pleased to

announce the results of a recently up-dated Preliminary Economic Assessment (the “ PEA”) for the

Company’s 100% owned Huguenot hard coking coal project (the “ Huguenot Project”) located

approximately 85 kilometres southeast of Tumbler Ridge in northeast British Columbia.

The original PEA report was prepared in 2013 by Norwest Corporation (“ Norwest”) and the results were

the subject of a news release dated September 24, 20 13. The up-dated PEA report, prepared by Norwest

now Stantec Consulting Services Inc. (“ Stantec”) in accordance with CSA National Instrument 43-101

(“NI 43-101”) standards, will be completed and filed on SEDAR (the System for Electronic Document

Analysis and Retrieval) within 45 days. The results of the up-dated PEA show that the Huguenot Project

continues to demonstrate positive economics, and th at it is worthy of continued exploration and

development.

In summary, Stantec used previously reported (2013), in situ, and potentially mineable resources plus the

2013 conceptual mine plan to exploit the coal resources through a combination of open pit and

underground mining, and up-dated sco ping-level cost estimates and economic analyses for the Huguenot

Project.

Highlights of the up-dated PEA report respecting th e Huguenot Project are summarized as below. All

costs are in US dollars but, where Canadian dollar equivalents are provided, they have been converted

using an exchange rate of US$1.00 equals CAD$1.30.

 The Huguenot Project has an indicative after-tax (and royalty) net present value (“NPV”)

of US$1,166 million (CAD$1,516 million), using a 7.5% discount rate, and an IRR of

33%, based on a coal price of US$172.00 per tonne.

 The financial analysis suggests that the “br eak-even” price is less than US$116, US$120,

and US$125 per tonne for discount rates of 5%, 7.5% and 10%, respectively. It also

indicates that for a 15% IRR, a minimum coal price of US$135 would be required.

 The Huguenot Project has a total projected mine life of 31 years, with the open pit (Years

1 - 14) and underground (Years 3 - 31) operating simultaneously during Years 3 - 14.

- 2 -

LEGAL_29421486.2

 Measured and indicated in-situ coal res ources total 277.7 million tonnes (132.0 million

tonnes surface mineable plus 145.7 milli on tonnes underground mineable). Inferred

resources total an additional 119.2 million tonn es (0.5 million tonnes of surface mineable

plus 118.7 million tonnes underground mineable).

 The Huguenot Project’s potential coal production is identified as hard coking coal similar

to coking coal currently exported from northeast British Columbia.

 The base coal price, of US$172.00 per tonne, used for the study represents a discount of

US$13.00 per tonne from a projected long-te rm benchmark price of US$185 per tonne

for premium low volatile hard coking coal.

 The PEA economic analysis is based on a con ceptual open pit mine plan targeting 56

million run-of-mine (“ ROM”) tonnes of resource at an average stripping ratio of 8.6 :1

(bank cubic metres (bcm) :ROM tonnes) plus a conceptual underground mine plan that

targets an additional 66 million ROM tonnes of resource.

 The Huguenot Project has total projected clean coal production of 89 million tonnes over

a mine life of 31 years.

 Projected clean coal production from combined surface and underground mining

operations ranges from 1.4 million tonnes per annum (“ Mt/a”) to 5.9 Mt/a, averaging

approximately 3.0 Mt/a.

 Projected clean coal production from the open pit averages approximately 3.2 Mt/a in

Years 1 through 12 and 1.8 Mt/a from underground from Years 5 through 31.

 The Huguenot Project’s proposed payback of initial capital is estimated within 5 years

from start-up of operations.

 The Huguenot Project’s cash operating costs are estimated at US$67.20 per tonne clean

coal at the mine loadout.

 The Huguenot Project’s estimated direct plus offsite costs (ie, FOB cost), total US$95.50

per clean tonne (excluding production taxes and royalties).

Included in the up-dated PEA are previously disclosed NI 43-101 compliant resource estimates originally

reported by Norwest in September, 2013. These resource estimates are tabulated below:

Deposit type Measured (Mt) Indicated (Mt) Inferred (Mt)

Surface 96.2 35.75 0.53

Underground 18.85 126.88 118.66

TOTAL 115.05 162.63 119.19

Conceptual mine plans developed in the study utili ze surface mining for the steeper dipping sections of

the North, Middle and South resource blocks, while the shallower dipping portions of the North Block

below the economic limits of the open pit were c onceived as being mineable by underground longwall

mining techniques. Coal resources accounted for in both the open pit and underground mine plans were

estimated as:

- 3 -

LEGAL_29421486.2

Mining Method ROM (Mt) Clean (Mt)

Open Pit 56 39

Underground 66 50

TOTAL 122 89

It was assumed that the Huguenot Project would be connected by rail to the existing rail line south of

Tumbler Ridge, and that a third party would construc t this rail link, with costs being charged to the

Huguenot Project on an annual basis. It was furthe r assumed that other potential projects along that

extended rail corridor would come on stream during th e same general time frame as the Huguenot Project

and that the rail costs would be shar ed among several users, such that th e Huguenot Project’s share of the

annual costs would be no more than 50% of the total (equivalent to US$4.59/clean tonne over the first 15

years, or US$2.91/clean tonne over life-of-mine (“LOM”).

The initial capital costs of the Huguenot Project have been significantly reduced by assuming that major

equipment items for surface mining would be leased, and are therefore included as cash operating costs.

Pre-production capital cost for the proposed mine is estimated at US$661 million, with additional

sustaining capital of US$178 million over the LOM.

A summary of the financial analyses is shown in the following tables:

Coal Price NPV (US$M) at Varying Discount Rates with

5% 7.5% 10% IRR (%)

US$172/t $1 ,669 $1 ,166 $831 33%

US$156/t $1,203 $811 $551 25%

US$188/t $2,134 $1,521 $1,109 40%

Coal Price NPV (CAD$M) at Varying Discount Rates

5% 7.5% 10% IRR (%)

CAD$224/t $2 ,170 $1 ,516 $1 ,080 33%

CAD$203/t $1,564 $1,054 $717 25%

CAD$244/t $2,775 $1,977 $1,442 40%

This PEA is preliminary in nature and includes in ferred mineral resources that are considered to

be too geologically speculative to be subject to economic considerations that would enable them to

be categorized as mineral reserves. There is no cert ainty that the forecast results stated in the PEA

will be realized.

This press release has been reviewed by Warren Ev enson of Stantec, a Professional Geologist and a

Qualified Person, as defined in NI 43-101.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts res ponsibility for the adequacy or accuracy of this

release.

- 4 -

LEGAL_29421486.2

About Colonial Coal International Corp.

Colonial is a publicly traded pure-play hard coki ng coal company in British Columbia. The northeast

Coal Block of British Columbia, within which our Company's projects are located, hosts a number of

proven deposits and has been the subject of M&A activities by Xstrata, Walter Energy, Anglo-American,

Conuma and others.

Additional information can be found on the Company's website www.ccoal.ca or by viewing the

Company's filings at www.sedar.com.

Forward-Looking Information

Information set forth in this news release may in volve forward-looking statements. Forward-looking

statements are statements that relate to future, not past, events. In this context, forward-looking statements

often address a company's expected future business and financial performance, and often contain words

such as "anticipate", "believe", "plan", "estimate", "e xpect", and "intend", statements that an action or

event "may", "might", "could", "should", or "will" be taken or occur, or other similar expressions. By

their nature, forward-looking statements involv e known and unknown risks, uncertainties and other

factors which may cause our actual results, performance or achievements, or other future events, to be

materially different from any future results, performance or achievements expressed or implied by such

forward-looking statements. Such factors include, among others, the following risks: risks associated with

marketing and sale of securities; the need for additional financing; reliance on key personnel; the potential

for conflicts of interest among certain officers or dire ctors with certain other projects; and the volatility of

common share price and volume. Forward-looking stat ements are made based on management's beliefs,

estimates and opinions on the date that statements ar e made and except as required by law, the Company

undertakes no obligation to update forward-looking stat ements if these beliefs, estimates and opinions or

other circumstances should change. Investors are cautioned against attributing undue certainty to forward-

looking statements.

THE FORWARD-LOOKING INFORMATION CONTAINED IN THIS NEWS RELEASE

REPRESENTS THE EXPECTATIONS OF THE COMPANY AS OF THE DATE OF THIS NEWS

RELEASE AND, ACCORDINGLY, IS SUBJECT TO CHANGE AFTER SUCH DATE. READERS

SHOULD NOT PLACE UNDUE IMPORTANCE ON FORWARD-LOOKING INFORMATION AND

SHOULD NOT RELY UPON THIS INFORMATION AS OF ANY OTHER DATE. WHILE THE

COMPANY MAY ELECT TO, IT DOES NOT UNDERTAKE TO UPDATE THIS INFORMATION

AT ANY PARTICULAR TIME EXCEPT AS REQU IRED IN ACCORDANCE WITH APPLICABLE

SECURITIES LEGISLATION.

For further information please contact:

Colonial Coal International Corp.

Shane Austin

604.568.4962

[email protected]

www.ccoal.ca