Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

BYN.V ·

Banyan Files Technical Report for AurMac Project, Yukon, Canada

Resource Estimates Technical Reports (NI 43-101)

Banyan Files Technical Report for AurMac Project, Yukon, Canada

August 20, 2025 TSX-V: BYN | OTCQB: BYAGF

VANCOUVER, August 20, 2024, Banyan Gold Corp . (the " Company" or "Banyan") ( TSX-V:

BYN) (OTCQB: BYAGF) announces the filing of the Technical Report to support the updated

Mineral Resource Estimate (“ MRE”) in accordance with the Canadian Institute of Mining,

Metallurgy and Petroleum (“ CIM”) Definition Standards incorporated by reference in National

Instrument 43-101 (“NI 43-101”) for the AurMac Pro ject (the “AurMac Property” or “AurMac”).

The Technical Report titled “Technical Report, AurMac Property, Mayo Mining District, Yukon

Territory, Canada” and dated August 20, 2025, was prepared by Marc Jutras, P.Eng., M .A.Sc.,

Principal, Ginto Consulting Inc., Tysen Hantelmann, P.Eng., of JDS Energy & Mining Inc. and

Deepak Malhotra, PhD., of Forte Dynamics. The Technical Report is available for review on

SEDAR+ at www.sedar.ca and on the Company’s website at www.banyangold.com.

As announced in the Company’s news release dated July 8, 2025, the updated MRE comprises

an Indicated Mineral Resource of 2.274 million (“M”) ounces (“oz”) of gold (“Au”) (112.5 M tonnes

at 0.63 g/t) and an Inferred Mineral Resource of 5.453 M oz of Au (280.6 M tonnes at 0.60 g/t )

(as defined in the CIM Definition Standards for Mineral Resources & Mineral Reserves

incorporated by reference into NI 43-101). The updated MRE is summarized below in Table 1

(Figure 1). The AurMac Project pit constrained MRE is contained in two near/on-surface deposits:

the Airstrip and Powerline deposits. AurMac is road accessible and is transected by an existing

transmission line of the Yukon’s power grid. The AurMac Project is located in the Mayo Mining

district, approximately 40 kilometres (“ km”) northeast from the villa ge of Mayo, Yukon and 356

km north of Whitehorse, Yukon.

The updated MRE is summarized below in Table 1.

Table 1: Pit-Constrained Indicated and Inferred Mineral Resources – AurMac Project

Indicated MRE Inferred MRE

Deposit

Au Cut-Off

Grade

(g/t)

Tonnage

(M Tonnes)

Gold

Grade

(g/t)

Gold

Content

(Oz)

Tonnage

(M Tonnes)

Gold

Grade

(g/t)

Gold

Content

(oz)

Airstrip 0.30 27.7 0.69 0.611 10.1 0.75 0.245

Powerline 0.30 84.8 0.61 1.663 270.4 0.60 5.208

Total

Combined 0.30 112.5 0.63 2.274 280.6 0.60 5.453

Notes to Table 1:

1. The effective date for the MRE is June 28, 2025 and was prepared by Marc Jutras, P.Eng., M.A.Sc., Principal,

Ginto Consulting Inc., an independent "Qualified Person" within the meaning of NI 43-101.

2. Mineral Resources which are not Mineral Reserves do not have demonstrated economic viability. The estimate

of Mineral Resources may be materially affected by environmental, permitting, legal, title, taxation,

sociopolitical, marketing, changes in global gold markets or other relevant issues.

3. The CIM Definition Standards were followed for classification of Mineral Resources. The quantity and grade

of reported Inferred Mineral Resources in this estimation are uncertain in nature and there has been insufficient

exploration to define these Inferred Mineral Resources as an Indicated Mineral Resource.

4. Mineral Resources are reported at a cut-off grade of 0.30 g/t gold for all deposits, using a US$/CAN$ exchange

rate of 0.73 and constrained within an open pit shell optimized with the Lerchs -Grossman algorithm to

constrain the Mineral Resources with the following estimated parameters: gold price of US $2,050/ounce,

US$2.50/t mining cost, US$10.00/t processing cost, US$2.00/t G+A, 90% gold recoveries, and 45° pit slopes.1

5. The number of tonnes and ounces was rounded to the nearest thousand. Any discrepancies in the totals are

due to rounding effects.

The pit outlines used to constrain the MRE are shown in Figure 1. Detailed images of the Mineral

Resource model, including an interactive 3D model and additional information can be found at:

https://www.banyangold.com/projects/aurmac/

Figure 1. Plan Map Showing the Mineral Resource Estimate and Drill Collar Locations.

1 The gold price and cost assumptions are consistent with current pricing assumptions and costs and, in particular,

with those employed for recent technical reports for similar pit-constrained Yukon gold projects.

Qualified Persons

The updated Mineral Resource Estimate for the AurMac Project was prepared by Marc Jutras,

P.Eng., M.A.Sc., Principal, Ginto Consulting Inc., an independent " Qualified Person" within the

meaning of NI 43-101, who has reviewed and approved the contents of this release and has

verified the data disclosed as it relates to the MRE. The data was verified by Mr. Jutras using

data validation and quality assurance procedures under industry standards.

Duncan Mackay, P.Geo., M.Sc., is a “ Qualified Person” as defined under NI 43 -101 and has

reviewed and approved the content of this news release in respect of all disclosure other than the

MRE. Mr. Mackay is Vice President Exploration for Banyan and has verified the data disclosed in

this news release, including the sampling, analytical and test data underlying the information

Upcoming Events

• Precious Metals Summit, Beaver Creek, September 9-12, 2025

o Corporate Presentation: September 10 at 8:15 AM MDT

• GCFF Conference, Vancouver, September 20, 2025

• 121 Hong Kong, September 24-25, 2025

• New Orleans Investment Conference, November 2-5, 2025

About Banyan

Banyan's primary asset, the AurMac Project is located in Canada’s Yukon Territory. The 215.3

square kilometres (“ sq km”) AurMac Project lies 40 kilometres (“ km”) from Mayo, Yukon. The

AurMac Project is transected by a Yukon highway and benefits from a 3-phase powerline, existing

power station and cell phone coverage. Banyan has the right to earn up to a 100% interest, in

both the Aurex and McQuesten Properties, respectively, subject to certain royalties.

In addition to the AurMac Project, the Company holds the Hyland Gold Project, located 70 km

Northeast of Watson Lake, Yukon, along the Southeast end of the Tintina Gold Belt (the “Hyland

Project”). The Hyland Project represents a sediment-hosted, structurally controlled, intrusion-

related gold deposit, within a large land package (over 125 sq km), accessible by a network of

existing gravel access roads.

Banyan also holds the Nitra Gold Project, a grassroots exploration project located in the Mayo

Mining district, approximately 10 km west of the AurMac Gold property. The Nitra Property lies in

the northern part of the Selwyn basin and is underlain by metaclastic rocks of the Late Proterozoic

Yusezyu Formation of the Hyland Group, similar to lithologies hosting portions of the AurMac

Project. Middle Cretaceous Tombstone Plutonic suite intrusions occur along the property

including the Morrison Creek and Minto Creek stocks. The property is 100% owned and operated

by Banyan and covers approximately 313.9 sq km. The property is accessible by road along the

Silver Trail Highway, South McQuesten Road and 4x4 roads.

Banyan trades on the TSX Venture Exchange under the symbol “ BYN” and is quoted on the

OTCQB Venture Market under the symbol “ BYAGF”. For more information, please visit the

corporate website or contact the Company.

ON BEHALF OF BANYAN GOLD CORPORATION

(signed) "Tara Christie"

Tara Christie

President & CEO

For more information, please contact:

Tara Christie • 778 928 0556 • [email protected]

Jasmine Sangria • 604 312 5610 • [email protected]

CAUTIONARY STATEMENT: Neither the TSX Venture Exchange, its Regulation Services Provider (as that term

is defined in policies of the TSX Venture Exchange) nor OTCQB Venture Market accepts responsibility for the

adequacy or accuracy of this release.

No stock exchange, securities commission or other regulatory authority has approved or disapproved the

information contained herein.

FORWARD LOOKING INFORMATION: This news release contains forward -looking information, which is not

comprised of historical facts and is based upon the Company’s current internal expectations, estimates, projections,

assumptions and beliefs. Such information can generally be identified by the use of forwarding -looking wording such

as “may”, “will”, “expect”, “estimate”, “anticipate”, “intend(s)”, “believe”, “potential” and “continue” or the negative thereof

or similar variations. Forward-looking information involves risks, uncertainties and other factors that could cause actual

events, results, performance, prospects and opportunities to differ materially from those expressed or implied by such

forward-looking information. Forward looking information in this n ews release includes, but is not limited to, the

Company’s plans for exploration; and statements regarding exploration expectations, prospectivity of the Company's

property interests, potential mining processes, pricing assumptions and mineral resource estimates; mineral recoveries

and anticipated mining costs. Factors that could cause actual results to differ materially from such forward -looking

information include uncertainties inherent in resource estimates, continuity and extent of m ineralization, capital and

operating costs varying significantly from estimates, the preliminary nature of metallurgical test results, delays in

obtaining or failures to obtain required governmental, environmental or other project approvals, political risk s,

uncertainties relating to the estimation of mineral resources and the availability and costs of financing needed in the

future, changes in equity markets, inflation, changes in exchange rates, fluctuations in commodity prices, and the other

risks involved in the mineral exploration and development industry, enhanced risks inherent to conducting business in

any jurisdiction, and those risks set out in Banyan’s public documents filed on SEDAR. Although Banyan believes that

the assumptions and factors used in preparing the forward -looking information in this news release are reasonable,

undue reliance should not be placed on such information, which only applies as of the date of this news release, and

no assurance can be given that such events will occur in the disclosed time frames or at all. Banyan disclaims any

intention or obligation to update or revise any forward-looking information, whether as a result of new information, future

events or otherwise, other than as required by law.