BUFFALO POTASH COMPLETES INITIAL DRILL HOLE AND

SPUDS SECOND WELL AT INITIAL PRODUCTION MODULE

Highlights

• Successfully completed drilling at 15-10 Well ahead of schedule and under budget;

• Flawless coring of 15-10 Well with 100% recovery on over 108m;

• Cased the 15-10 Well for future optionality to become source well of underground brine;

• Successfully completed open hole logging program;

• Drilling rig safely and efficiently moved to the 2-14 Well location; and

• 2-14 Well spudded Monday, July 27, 2026.

SASKATOON, Saskatchewan, July 29, 2026 – Buffalo Potash Corporation (TSXV: BUFF) (OTCQB:

BLPTF) (FRA: VU5) (the “Company” or “Buffalo”) is pleased to announce the completion of the first well

(the "15-10 Well" or the " Source Well") at the Initial Production Module (" IPM") and the spudding of the

second well (the "2-14 Well" or the "Disposal Well") located at the Company's flagship Disley property in

Saskatchewan (the "Disley Project").

Completion of the Source Well (15 -10) – Further to the Company's July 22, 2026 news release ( see link),

drilling of the 15 -10 Well was completed ahead of schedule and under budget. The well was cored with

100% core recovery over more than 108m and logged through the target intervals. The well was then cased,

preserving the option to later convert it into a source well producing brackish water from the Mannville

Formation. After being pumped to surface, this brackish water is anticipated to be saturated with NaCl to

form the solvent used in Buffalo’s patented solution mining method, a key input for the IPM.

Spudding of the Disposal Well (2 -14) – Following completion of the 15 -10 Well, the drilling rig was moved

to the 2 -14 Well location, approximately 1,600m east of the 15 -10 Well. The 2 -14 Well was successfully

spudded on Monday, July 27, 2026 and, upon reaching the initial target depth, will be cored and logged

through the potash-bearing members of the Prairie Evaporite Formation. Core and log data from the vertical

drilling program will enhance the Company's geological understanding of the IPM site and support a

feasibility study for Disley West and Disley East (see Disley Project Development Plan below). Once coring

and open hole logging are complete, the 2-14 Well will be extended to the top of the Deadwood Formation

and cased to later serve as a disposal well for excess brine following surface processing under the IPM

design.

Mr. Quinton Hardage, P.Eng., PMP, President and Chief Operating Officer of the Company,

commented: "Completing our first well ahead of schedule and under budget is exactly the start we wanted

as we enter the most exciting period in Buffalo’s history . Saskatchewan is the largest producer of potash

globally, and the world depends on this province to help feed a growing population. We take that

responsibility seriously, which is why we are working tirelessly to build a more capital -efficient and lower-

impact way to produce it. Seeing our vision take shape as we bring the Initial Production Module to life is

enormously rewarding, and we look forward to carrying this momentum into the 2 -14 Well and beyond."

Disley Project Development Plan

The IPM is designed to produce 125,000 tonnes per annum (“TPA”) of soluble-grade potash and is the first

of three planned solution mining facilities at the Disley Project. The IPM has a lower initial CAPEX

requirement compared to the full Disley Project build -out and is targeted to reach first production in Q1

2027. At full build-out comprising the IPM and two 500,000 TPA mines ("Disley East" and "Disley West"),

the Disley Project would be expected to produce up to 1,125,000 TPA of potash, as contemplated in

Buffalo's recently released preliminary economic assessment titled “NI 43 -101 Preliminary Economic

Assessment Technical Report on the Disley Potash Project, Saskatchewan, Canada” dated May 21, 2026,

and effective April 15, 2026 (the “PEA”), a copy of which is available on the Company’s SEDAR+ profile at

www.sedarplus.ca. On a standalone basis, the PEA attributes a payback period of approximately 12 months

from the start of IPM production.(2) However, there is no guarantee that the Company will be able to achieve

production.

The Company's production decision for the IPM is not based on a feasibility study of mineral reserves

demonstrating economic and technical viability, and such production decisions are historically associated

with a higher risk of economic and technical fai lure (see "Note 3 – Production Decision Cautionary

Statement").

The IPM is intended to establish initial cash-flowing production at a lower upfront capital cost, while building

the operational and technical foundation for full-scale development. Development of the IPM is anticipated

to be broken down into five phases:

1. Source and disposal wells;

2. Horizontal Line-Drive ("HLD") drilling;

3. Brine circulation;

4. Site development; and

5. Surface processing.

Disley Project - General Overview

The Disley Project is located approximately 50 kilometers northwest of Regina and covers 10,610 hectares

(Crown and Freehold mineral rights). The property is situated immediately to the east of the K+S Bethune

potash solution mine and north of the Mosaic Belle Plaine potash solution mine – both of which are among

the largest producing potash solution mines in the world. In the opinion of management, the Disley Project

is in one of the most favorable areas of Saskatchewan for potash solution mining (see Figu re 1) as

evidenced by the success of these neighboring operations. (1)

On May 22, 2026, Buffalo released the results of its maiden NI 43-101 Mineral Resource Estimate and PEA

for the Disley Project, prepared by Micon International Co Limited. The PEA outlined a phased, modular

development plan contemplating full -scale product ion of up to 1,125,000 TPA of potash across three

solution mining facilities, with an estimated after-tax net present value (NPV) of US$1.1B at a discount rate

of 8% and estimated internal rate of return (IRR) of 30%. (2) Readers are encouraged to refer to Buffalo's

April 27, 2026 and May 22, 2026 news releases and the NI 43 -101 technical report filed on SEDAR+ for

complete details of the PEA and Mineral Resource Estimate.

Figure 1: The Disley Property Situated Amongst Major Potash Solution Mines (1)

About Buffalo Potash

Buffalo Potash is an emerging Saskatchewan -based potash developer pursuing a modular approach to

selective solution mining through its patented Horizontal Line-Drive (HLD) technology. Buffalo is advancing

the Disley Project – located adjacent to two of the most prominent currently producing potash solution mines

in the world – with the objective of establishing capital -efficient, lower-impact potash production in one of

the world’s leading potash jurisdictions.

Qualified Person

The technical information in this news release has been reviewed and approved by Douglas F. Hambley,

PhD, PE, P.Eng., PG, an independent consultant to the Company, who is a Qualified Person within the

meaning of National Instrument 43 -101 – Standards of Disclosure for Mineral Projects . This news release

does not contain new technical disclosure beyond information previously disclosed in the NI 43 -101

technical report for the Disley Project filed under the Company's profile on SEDAR+ at www.sedarplus.ca.

Readers are referred to that technical report, prepared by Micon International Co Limited, for complete

details of the Mineral Resour ce Estimate and Preliminary Economic Assessment, including all data

verification, methodology, assumptions, and qualifications.

All related and pertinent information has also been reviewed for this news release by Jared Galenzoski,

P.Geo, FIMMM as an independent consultant to the Company who is a Qualified Person within the meaning

of National Instrument 43-101 – Standards of Disclosure for Mineral Projects. Mr. Galenzoski is an expert

in several potash -related fields including the drilling of potash horizontal wells and solution mining

operations.

Contact

Steve Halabura | Chief Executive Officer & Director

Email: [email protected] | Phone: 1-306-220-7715

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the

policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Notes

(1) The K+S Bethune potash solution mine and the Mosaic Belle Plaine potash solution mine (together, the

“Adjacent Properties”) may each be considered an “adjacent property” (within the meaning of NI 43 -101)

to the Company’s Disley Project. The Company has no interest in either of the Adjacent Properties. The

Company believes this context is useful in illustrating the proven end owment of the district, while noting

that mineralization on adjacent or nearby properties is not indicative of mineralization on the Company’s

Disley Project. There is no guarantee that the Disley Project will yield comparable results to either of these

mines.

(2) The PEA was prepared by Micon International Co Limited in accordance with National Instrument 43 -

101 Standards of Disclosure for Mineral Projects and is preliminary in nature. The PEA includes inferred

mineral resources, which are considered too speculative geologically to have the modifying factors and

economic considerations applied to them that would enable them to be categorized as mineral rese rves.

Mineral resources that are not mineral reserves do not have demonstrated economic viability. There is no

certainty that the results of the PEA will be realized. Readers are encouraged to read the technical report

filed under the Company's profile on SEDAR+ at www.sedarplus.ca in its entirety, including all

qualifications, assumptions, and exclusions that relate to the PEA.

(3) Production Decision Cautionary Statement : The Company's decision to proceed with development of

the IPM is not based on a feasibility study of mineral reserves demonstrating economic and technical

viability. No mineral reserves have been established at the Disley Project, and the PEA is prelimin ary in

nature (see Note 2). Historically, mineral projects advanced to production without first establishing mineral

reserves supported by a feasibility study have a higher risk of economic and technical failure. Specific risks

associated with the Company' s production decision include, but are not limited to: 1) grade, continuity, or

thickness of mineralization that differs from the Mineral Resource Estimate; 2) performance of the

Company's Horizontal Line -Drive mining method, which has not been operated at commercial scale, that

is not as anticipated; 3) recoveries, production rates, or capital and operating costs that differ materially

from the PEA; and 4) production during the IPM that does not become sustainable or profitable, which

would materially and adversely affect the Company's ability to generate revenue and cash flow.

Forward-Looking Information

This news release contains “forward -looking information” and “forward -looking statements” (collectively,

“forward-looking information”) within the meaning of applicable Canadian securities legislation. Forward -

looking information is generally identifiable by the use of words such as “believes,” “may,” “plans,” “will,”

“anticipates,” “intends,” “could,” “estimates,” “expects,” “forecasts,” “projects,” or similar expressions, and

the negative of such expressions.

Forward-looking information in this news release includes, but is not limited to, statements regarding: the

timing, sequencing, and completion of the IPM development plan, including the drilling of the source,

disposal, and horizontal wells, the development of the mining plane, site development, and the installation

and commissioning of processing equipment; the anticipated role of the Source Well and Disposal Well in

IPM construction and operations; the anticipated coring and open hole logging of the Source Well and

Disposal Well and the expected use and benefits of the data obtained therefrom; the anticipated conversion

of the Source Well to produce brackish water from the Mannville Formation and the expectation that such

water will be saturated with sodium chloride and used as the solvent in the Company's solution mining

methodology; the anti cipated timing and completion of lease construction , rig mobilization, and the

commencement of drilling operations; the anticipated timing of first production from the IPM; the anticipated

timing and phasing of construction and commercial production for the IPM, Disley East, and Disley West;

the preparation, timing, and expected benefits of a concurrent feasibility study for the full build -out of the

Disley Project; the results, assumptions, and projections contained in or derived from the Mineral Resource

Estimate and PEA for the Disley Project, including projected production rates and timing of production;

expectations regarding the Disley Project’s potential for solution mining; the Company’s broader

development plans and strategy for the Disley Project; and the fact that the Company's production decision

for the IPM is not based on a feasibility study of mineral reserves demonstrating economic and technical

viability, and the associated increased risk of economic and technical failure.

Forward-looking information is based on management’s reasonable assumptions, estimates, analysis, and

opinions made in light of its experience, perception of historical trends, current conditions, and expected

future developments, as well as other factors that management believes are relevant and reasonable in the

circumstances as of the date such statements are made. These assumptions include, but are not limited

to, assumptions regarding geological continuity, potash grade and thickness, the applicability of historical

data, the performance of solution mining methods, costs of production, the availability of services and

equipment, the receipt of required permits and approvals, and the availability of financing on acceptable

terms.

Forward-looking information is subject to known and unknown risks, uncertainties, and other factors that

may cause actual results, performance, or achievements of the Company to differ materially from those

expressed or implied by such forward-looking information. Such risks and uncertainties include, but are not

limited to: the inherent uncertainty of PEA -level studies and the possibility that actual capital costs,

operating costs, and production rates differ materially from estimates; risks related to exp loration and

development activities; risks related to the timing and completion of lease construction, rig mobilization, and

drilling operations, including the availability and performance of drilling contractors, equipment, and

services; uncertainty in ge ological interpretation; risks related to the development, commissioning, and

operation of novel mining technology; risks inherent to solution mining operations and new or emerging

technologies; regulatory approvals and permitting timelines; commodity price volatility; availability of capital;

and general economic, market, and business conditions.

Although the Company has attempted to identify important factors that could cause actual results to differ

materially from those contained in forward-looking information, there may be other factors that cause results

not to be as anticipated, estimated, or intended. There can be no assurance that such information will prove

to be accurate, as actual results and future events may differ materially from those anticipated in such

forward-looking information. Accordingly, readers should not place undue reliance on forward -looking

information. The forward-looking information contained herein is made as of the date of this news release,

and the Company disclaims any obligation to update or revise such information, except as required by

applicable securities laws.