Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

BTO.TO ·

B2Gold Corp. Reports Strong Third Quarter 2017 Results; New

Financials

B2Gold Corp. Reports Strong Third Quarter 2017 Results; New

Fekola Mine Achieves First Gold Pour on October 7, 2017, and

Gold Production of 40,286 Ounces to October 31 during Ramp-up

Phase; Commercial Production at Fekola Anticipated by End of

November

Vancouver, British Columbia--(Newsfile Corp. - November 7, 2017) - B2Gold Corp. (TSX: BTO) (NYSE

AMERICAN: BTG) (NSX: B2G) ("B2Gold" or the "Company") is pleased to announce its operational and

financial results for the three and nine months ended September 30, 2017. The Company previously

released its gold production and gold revenue results for the third quarter of 2017 (see news release

dated 10/13/17). All dollar figures are in United States dollars unless otherwise indicated. In addition, the

Company is pleased to announce that the ramp up to full scale production at the Fekola Mine is ahead of

schedule with gold production well above budget in September and October. The Company now expects

the Fekola Mine to achieve commercial production by the end of November.

2017 Third Quarter Highlights

 Consolidated gold production of 135,628 ounces, in cluding 6,340 ounces of pre-commercial gold

in-circuit production from Fekola, exceeding (original) budget by 2% (or 2,254 ounces) and

reforecast production by 15% (or 17,372 ounces)

 Consolidated gold revenue of $154.1 million on sales of 121,597 ounces at an average price of

$1,267 per ounce

 Otjikoto Mine achieved record quarterly production of 55,151 ounces

 Fekola Mine construction completed, and processing of ore commenced more than three months

ahead of schedule, in September 2017

 First gold pour at the Fekola Mine achieved on October 7, 2017

 In October 2017, subsequent to the third quarter, the Fekola Mine produced 33,946 ounces of

gold in the month (significantly surpassing budget of 15,100 ounces) and is now expected to

achieve commercial production (four months ahead of original schedule) by the end of November

 Consolidated cash operating costs (see "Non-IFRS Measures") of $563 per ounce, $28 per

ounce (or 5%) below budget

 Consolidated all-in sustaining costs ("AISC") (see "Non-IFRS Measures") of $921 per ounce, $66

per ounce (or 8%) above budget, due to the timing of capital expenditures, but year-to-date AISC

of $927 per ounce remained well below budget

 Cash flow from operating activities (after non- cash working capital changes) of $41.8 million

($0.04 per share)

 Strong cash position of $89.7 million at quarter-end combined with additional liquidity of $175

million available for draw down on the Company's upsized corporate revolving credit facility

 In July 2017, the Masbate operations were presented with the Philippine Department of

Environment and Natural Resources' ("DENR") prestigious Saringaya Award for its contribution to

environmental protection, conservation and management in the regions surrounding the Masbate

Mine

 In July 2017, the Company secured a $500 milli on upsized corporate revolving credit facility,

representing a $75 million increase from the existing facility

 For full-year 2017, the Company is on track to meet the high end of its revised annual

consolidated production guidance range of between 530,000 and 570,000 ounces of gold and be

at the lower end of its guidance ranges for cash operating costs (of between $610 to $650 per

ounce) and AISC (of between $940 to $970 per ounce)

 2018 outlook provides for dramatic production gr owth of approximately 70%, with the planned first

full year of production from the Fekola Mine, consolidated annual gold production is expected to

increase significantly to between 925,000 and 975,000 ounces with cash operating costs and

AISC expected to decrease and be approximately $525 per ounce and $800 per ounce,

respectively

2017 Third Quarter and First Nine Months Operational Results

Consolidated gold production in the third quarter of 2017 was 135,628 ounces, including 6,340 ounces of

pre-commercial production from the newly constructed Fekola Mine in Mali (attributable to the increase in

its gold in-circuit inventory in September), exceeding (original) budget by 2% (or 2,254 ounces) and

reforecast production by 15% (or 17,372 ounces). The better than budgeted and reforecast consolidated

gold production reflects the continued very strong operational performances of both the Masbate Mine in

the Philippines and the Otjikoto Mine in Namibia as well as the successful early start-up of the Fekola

Mine in September (see "Operations" section below).

On September 25, 2017, the Company announced that it had completed construction of the Fekola mill

on budget and commenced ore processing at the Fekola Mine, more than three months ahead of

schedule. Commissioning of the mill is ongoing and is expected to ramp up quickly to achieve commercial

production by the end of November 2017, four months ahead of the original schedule. The Fekola mill

started processing ore on September 24, 2017, and treated 57,695 tonnes of ore at a grade of 3.54 g/t

over the remainder of the month of September with a gold recovery of 96.6%, producing 6,340 ounces of

in-circuit gold inventory (nil ounces budgeted). The first pour at the Fekola Mine was achieved on October

7, 2017.

In October 2017, the first full month of ramp up and pre-commercial production, the Fekola mill treated

324,525 tonnes of ore (budgeted – 225,804 tonnes) at an average grade of 3.40 g/t (budgeted – 2.33 g/t)

with a gold recovery of 95.4% (budgeted – 90.0%), producing a total of 33,946 ounces of gold in the

month (surpassing budget of 15,100 ounces). Mill availability was 75% (budgeted – 50%) and the mill

was operating at design throughput (of 607 tonnes per hour) during the latter half of the month. For 2017,

the Company is projecting gold production from Fekola to exceed its reforecast production guidance

range of between 50,000 and 55,000 ounces (at an expected cash operating cost of $580 to $620 per

ounce). 2018 is scheduled to be the first full year of gold production at Fekola, yielding 400,000 to

410,000 ounces for the year at a cash operating cost of approximately $354 per ounce of gold and AISC

of $609 per ounce of gold.

In the third quarter of 2017, consolidated cash operating costs were $563 per ounce (Q3 2016 – $491 per

ounce), $28 per ounce (or 5%) below budget. The favourable variance against budget reflects higher than

budgeted gold production at the Masbate and Otjikoto mines combined with slightly lower production

costs at the Masbate and Otjikoto mines. Consolidated AISC in the quarter were $921 per ounce (Q3

2016 – $702 per ounce), $66 per ounce (or 8%) above budget. The increase was mainly a result of higher

than budgeted capital expenditures at the Otjikoto Mine due to the timing of the purchase of mobile

equipment during the third quarter, which was originally planned for earlier in 2017. However, year-to-

date, consolidated AISC remained well below budget.

Consolidated gold production in the first nine months of 2017 was 389,812 ounces (YTD 2016 – 409,772

ounces), 3% (or 11,820 ounces) better than (original) budget and 5% (or 17,372 ounces) better than

reforecast production.

Year-to-date, consolidated cash operating costs were $585 per ounce (YTD 2016 – $495 per ounce), $62

per ounce (or 10%) below budget, and consolidated AISC were $927 per ounce (YTD 2016 – $765 per

ounce), $122 per ounce (or 12%) below budget.

For full-year 2017, B2Gold is projecting another year of solid growth with forecast production for the year

expected to be at the upper end of the Company's revised guidance range of 530,000 to 570,000 ounces

and to be at the lower end of its guidance ranges for cash operating costs (of between $610 to $650 per

ounce) and AISC (of between $940 and $970 per ounce). The Company expects continued strong

performances from Masbate and Otjikoto, combined with Fekola's early September 24, 2017, pre-

commercial production start, to offset any lower production from La Libertad and El Limon.

Looking forward to 2018, with the planned first full year of production from the Fekola Mine (based on

current assumptions and updates to the Company's long-term mine plans), the Company is projecting its

consolidated gold production to increase by over 70% and to be between 925,000 and 975,000 ounces.

The Fekola Mine is projected to be a large low-cost producer that will result in a significant reduction in

the Company's forecast cash operating costs per ounce and AISC per ounce. The Company's forecast

consolidated cash operating costs per ounce and AISC per ounce are expected to decrease in 2018

(compared to 2017) and be approximately $525 per ounce and $800 per ounce, respectively.

These increased production levels and low costs are expected to dramatically increase B2Gold's

production revenues, cash from operations and cash flow for many years, based on current assumptions

(including a gold price assumption of $1,275 per ounce). On average over the next three years, beginning

in 2018, the Company is projecting per annum gold sales revenues of approximately $1.2 billion, cash

flow from operations of approximately $0.5 billion and a significant increase in free cash flow (operating

cash flows less investing cash flows).

2017 Third Quarter and First Nine Months Financial Results

Consolidated gold revenue in the third quarter of 2017 was $154.1 million on sales of 121,597 ounces at

an average price of $1,267 per ounce compared to $193.0 million on sales of 145,029 ounces at an

average price of $1,331 per ounce in the third quarter of 2016. The 20% (or $38.9 million) decrease in

revenue was mainly attributable to a 16% decrease in gold sales volume, due to lower production and the

timing of gold shipments, and a 5% decrease in the average realized gold price. The decrease in sales

volumes reflects a 12% decrease in gold production (excluding in-circuit Fekola pre-commercial

production ounces). In addition, the timing of gold shipments at several sites impacted the available gold

for sale in the third quarter of 2017. These ounces will be sold in the fourth quarter of 2017.

Consolidated gold revenue in the three and nine months ended September 30, 2017, included $15 million

and $45 million, respectively, relating to the delivery of gold into the Company's Prepaid Sales contracts

(deferred revenue) associated with the Company's Prepaid Sales transactions entered into in March

2016. Proceeds from the Prepaid Sales transactions, used to fund the Fekola Mine construction, were

originally received in March 2016 and are being recognized in revenue as the underlying Prepaid Sales

ounces are delivered into. During the three and nine months ended September 30, 2017, 12,908 ounces

and 38,724 ounces, respectively, were delivered under these contracts.

Cash flow provided by operating activities (after non-cash working capital changes) was $41.8 million

($0.04 per share) in the third quarter of 2017 compared to $90.3 million ($0.10 per share) in the third

quarter of 2016. The decrease reflected the delivery of 12,908 ounces of gold into the Company's Prepaid

Sales contracts in the quarter (representing $15 million of gold sales revenue for which no cash proceeds

were received in the current quarter), lower gold sales revenue (as previously described above) and

higher operating costs. In 2018, the Company's cash flow from operations is expected to increase

significantly (relative to 2017) driven by new gold production from the Fekola Mine.

The Company generated net income of $12.4 million ($0.01 per share) in the quarter compared to net

income of $35.7 million ($0.04 per share) in the same quarter last year. Adjusted net income (refer to

"Non-IFRS Measures") was $13.9 million ($0.01 per share) in the third quarter of 2017 compared to $48.6

million ($0.05 per share) in the prior-year quarter. The decrease in adjusted net income was mainly

attributable to lower gold sales revenue (as previously described above) and higher operating costs.

Consolidated gold revenue for the first nine months of 2017 was $464.7 million on sales of 373,271

ounces at an average price of $1,245 per ounce compared to $502.1 million on sales of 396,757 ounces

at an average price of $1,266 per ounce in the first nine months of 2016.

Year-to-date, cash flow from operating activities (after non-cash working capital changes) was $129.4

million ($0.13 per share) compared with $329.5 million ($0.35 per share) in the first nine months of 2016.

Included in the prior-year period was $120 million of proceeds received from the Company's Prepaid

Sales transactions in March 2016.

For the nine months ended September 30, 2017, the Company generated net income of $27.1 million

($0.03 per share) compared to net income of $30.5 million ($0.04 per share) in the comparable period of

2016. Adjusted net income for the nine months ended September 30, 2017, was $46.1 million ($0.05 per

share) compared to $96.5 million ($0.10 per share) for the nine months ended September 30, 2016. The

decrease in adjusted net income was mainly attributable to lower gold sales revenue (as previously

described above) and higher operating costs.

Liquidity and Capital Resources

At September 30, 2017, the Company remained in a solid financial position with working capital of $35.2

million including unrestricted cash and cash equivalents of $89.7 million. In addition, the Company had

drawn $325 million under its $500 million amended revolving credit facility, leaving an undrawn and

available balance at September 30, 2017, of $175 million. At September 30, 2017, the Company also had

Euro 36.4 million of undrawn capacity on its Fekola equipment loan facility and $9.1 million of undrawn

capacity on its Masbate equipment loan facility.

Operations

Mine-by-mine gold production in the third quarter and first nine months of 2017 was as follows:

Mine

Q3 2017

Gold

Production

(ounces)

YTD 2017

Gold

Production

(ounces)

2017

Revised

Annual Production

Guidance

(ounces)

2017

Original

Annual Production

Guidance

(ounces)

Masbate 46,557 149,049 180,000 - 185,000 175,000 - 185,000

Otjikoto 55,151 139,08 8 170,000 - 180,000 165,000 - 175,000

La Libertad 16,487 67,641 90,000 - 100,000 110,000 - 120,000

El Limon 11,093 27,694 40,000 - 50,000 50,000 - 60,000

Subtotal 129,288 383,472 480,000 - 515,000 500,000 - 540,000

Fekola (pre-commercial) 6,340 6,340 50,000 - 55,000 45,000 - 55,000

B2Gold Consolidated 135,628 389,812 530,000 - 570,000 545,000 - 595,000

Masbate Gold Mine – Philippines

The Masbate Mine in the Philippines continued to exceed expectations, producing 46,557 ounces of gold

in the third quarter of 2017, 20% (or 7,799 ounces) above both (original) budget and reforecast

production, and comparable with the prior-year quarter. Gold production exceeded budget and reforecast

production due to better than expected throughput and recoveries mainly driven by significantly higher

than budgeted oxide ore from the Colorado Pit. As mining advances in the Colorado Pit, the trend of more

oxide ore than modelled has continued. The Masbate Mine has continued its outstanding safety

performance, achieving two years without a "Lost-Time-Injury" on October 12, 2017.

Mill throughput in the quarter was 1,704,723 tonnes compared to budget of 1,619,060 tonnes and

1,604,176 tonnes in the third quarter of 2016. Mill recoveries averaged 77.4% which was better than

budget of 68.9% and 77.2% in the third quarter of 2016. The average grade processed was 1.10 g/t

compared to budget of 1.08 g/t and 1.20 g/t in the third quarter of 2016. As expected, grades were higher

in the prior-year quarter attributable to the high-grade ore from the Main Vein Stage 1 Pit which is no

longer active.

Masbate's third quarter cash operating costs were $541 per ounce (Q3 2016 – $466 per ounce),

significantly below budget by $203 per ounce (or 27%). This favourable variance was mainly the result of

higher than expected production and lower than expected production costs (due to cost savings in most

areas) and stockpile adjustments. Masbate's AISC in the third quarter were $717 per ounce (Q3 2016 –

$650 per ounce), significantly below budget by $339 per ounce (or 32%). AISC were below budget as a

result of lower cash operating costs and sustaining capital expenditures due to the timing of mobile

equipment purchases which were expected in the third quarter of 2017 but are now expected to occur in

the fourth quarter of 2017.

Year-to-date, gold production at Masbate was 149,049 ounces (YTD 2016 – 157,591 ounces),

significantly above (original) budget by 12% (or 16,043 ounces) and 6% (or 7,799 ounces) more than

reforecast production.

Masbate's cash costs remained significantly below budget in the first nine months of the year with cash

operating costs of $527 per ounce (YTD 2016 – $437 per ounce), $161 per ounce (or 23%) below budget,

and AISC of $800 per ounce (YTD 2016 – $612 per ounce), $256 per ounce (or 24%) below budget.

Compared to the prior-year period, Masbate's AISC increased, reflecting higher fuel costs as well as its

2017 planned mine fleet replacement and expansion program. However, in 2018, Masbate's mine

equipment purchases are planned to significantly decrease (relative to 2017).

Capital expenditures in the third quarter of 2017 totaled $6.1 million including pre-stripping costs of $1.6

million, mobile equipment costs of $1.2 million and powerhouse upgrade costs of $1.0 million. Year-to-

date capital expenditures totaled $36.5 million, consisting mainly of mobile equipment costs of $17.2

million, pre-stripping costs of $6.1 million, powerhouse upgrade costs of $3.4 million and processing plant

upgrades of $3.1 million.

For full-year 2017, the Masbate Mine is well on track to meet or exceed the high end of its previously

increased production guidance range of between 180,000 to 185,000 ounces of gold (original guidance

was 175,000 to 185,000 ounces) while meeting the low end of its guidance range for cash operating costs

of between $595 to $635 per ounce and AISC of between $935 and $975 per ounce.

The Masbate operations were recently presented with the DENR's Saringaya Award for its contribution to

environmental protection, conservation, and management in the regions surrounding the Masbate Mine.

The Saringaya Award is considered the DENR's most prestigious regional environmental award.

The Philippine Mining Industry Coordinating Council ("MICC") (the MICC is the oversight committee for

the DENR) has voted to rescind the existing Department Administrative Order which bans new open-pit

mines (does not apply to current Masbate operations). They have indicated that the order may be lifted

provided that mining laws, rules and regulations are strictly enforced.

Otjikoto Gold Mine – Namibia

The Otjikoto Mine in Namibia produced a quarterly record 55,151 ounces of gold in the third quarter of

2017, 14% (or 6,793 ounces) above both (original) budget and reforecast production, and 16% (or 7,587

ounces) higher than the third quarter of 2016. As mining advances into the consolidated rock in the

Wolfshag Phase 1 Pit, the amount of high-grade ore tonnage mined from Wolfshag continues to be

significantly higher than modelled. Analysis of the Wolfshag model is ongoing to determine whether this

positive variance in the amount of high-grade ore tonnage continues throughout the entire Wolfshag

orebody.

The average gold grade processed in the quarter was 1.99 g/t compared to budget of 1.85 g/t and 1.66

g/t in the third quarter of 2016. Grade exceeded budget due to the higher amount of high-grade ore being

sourced from Wolfshag which increased the overall average mill feed grade at Otjikoto. Mill throughput for

the quarter was 873,516 tonnes compared to budget of 832,784 tonnes and 910,036 tonnes in the third

quarter of 2016. Mill recoveries remained high and averaged 98.5%, slightly above both budget and the

prior-year quarter.

Otjikoto's third quarter cash operating costs were $447 per ounce, slightly better than budget. Compared

to the prior-year quarter, cash operating costs were $103 per ounce higher as the prior-year quarter had

benefited from a weaker Namibian dollar and lower fuel prices. Otjikoto's AISC in the third quarter were

$809 per ounce (Q3 2016 – $474 per ounce), above budget by $160 per ounce. The increase over

budget was mainly attributable to the timing of the purchase of mobile equipment during the third quarter

which was originally planned for earlier in 2017. However, year-to-date, Otjikoto's AISC remained

significantly below budget.

During the first nine months of 2017, the Otjikoto Mine produced a year-to-date record 139,088 ounces of

gold, 16% (or 19,148 ounces) above (original) budget and 5% (or 6,793 ounces) more than reforecast

production, and 16% (or 19,649 ounces) higher compared to the same period last year.

Otjikoto's cash costs were significantly below budget in the first nine months of 2017 with cash operating

costs of $459 per ounce (YTD 2016 – $368 per ounce), $101 per ounce (or 18%) below budget, and

AISC of $756 per ounce (YTD 2016 – $611 per ounce), $235 per ounce (or 24%) below budget.

Capital expenditures in the third quarter of 2017 totaled $20.9 million consisting of $9.0 million for mining

equipment, $4.8 million for installation of a solar power plant, $3.1 million for capitalized equipment

rebuilds and $3.0 million for pre-stripping. For the nine months ended September 30, 2017, capital

expenditures totaled $36.1 million consisting of $11.9 million for mobile equipment purchases, $9.5 million

for pre-stripping, $6.4 million for capital repairs and $4.8 million for installation of the solar power plant.

Total capital expenditures for the year are expected to be under budget due to a combination of lower

pre-stripping costs and a slight delay in the solar plant construction.

For full-year 2017, the Otjikoto Mine remains well on track to meet or exceed the high end of its

previously increased production guidance range of between 170,000 to 180,000 ounces of gold (original

guidance was 165,000 to 175,000 ounces) while meeting the low end of its guidance range for cash

operating costs of between $480 to $520 per ounce and AISC of between $725 and $765 per ounce.

Geotechnical, hydrogeological and design studies for Wolfshag have been completed. These studies,

coupled with an updated resource model, indicate that a larger open pit, which is the Company's

preferred option, have similar positive economics to the underground option. In addition, the Wolfshag

resource remains open down-plunge which may be exploitable in the future by underground mining.

La Libertad Gold Mine – Nicaragua

La Libertad Mine in Nicaragua produced 16,487 ounces of gold in the third quarter of 2017 (Q3 2016 –

37,261 ounces), approximately in-line with revised guidance (but lower than originally budgeted as gold

production at La Libertad was negatively impacted by permitting delays for new mining areas). Year-to-

date, gold production at La Libertad was 67,641 ounces (YTD 2016 – 97,266 ounces), approximately in-

line with reforecast but 18,679 ounces lower than (original) budget.

As previously released, the Company has changed its planned sequencing for bringing the Jabali

Antenna Pit into the mine plan (originally forecast to enter production in the third quarter of 2017). With

strong support from the Nicaraguan government, the Company is now focused on bringing the San Juan

and San Diego open pits into production in the second half of 2017 ahead of the Jabali Antenna Pit. In

September 2017, the San Juan mining permit was received, and it is anticipated that the San Diego

mining permit will also be received by early December (following public consultation). Mining has already

commenced in the San Juan Pit and is expected to commence in the San Diego Pit upon receipt of its

permit. The Company has also made significant progress in resettlement and permitting activities at the

high-grade Jabali Antenna Pit and is expecting to receive its permit in time to start production from the pit

in the third quarter of 2018.

La Libertad's third quarter cash costs, on a per ounce basis, were impacted by the lower than planned

production with cash operating costs of $788 per ounce (Q3 2016 – $637 per ounce) and AISC of $1,187

per ounce (Q3 2016 – $788 per ounce), both well above the original budget. Year-to-date, La Libertad's

cash operating costs were $780 per ounce (YTD 2016 – $658 per ounce) and AISC were $1,019 per

ounce (YTD 2016 – $913 per ounce).

Total capital expenditures in the third quarter of 2017 were $5.9 million, consisting primarily of $2.7 million

in project development costs related to the new San Juan and San Diego open pits and underground

development costs of $2.5 million. For the nine months ended September 30, 2017, capital expenditures

totaled $18.1 million, consisting primarily of underground development costs of $4.9 million, La

Esperanza Tailings Dam expansion of $4.7 million, project development costs of $4.5 million and land

acquisitions of $3.1 million.

For full-year 2017, La Libertad's production is expected to be at the low end of its revised production

guidance range of between 90,000 to 100,000 ounces of gold (original guidance was 110,000 to 120,000

ounces) and to be at the upper end of its cash operating costs (of between $795 to $835 per ounce) and

AISC (of between $1,075 and $1,115 per ounce) guidance ranges. Inclusion of the newly permitted open

pits is expected to increase gold production in the fourth quarter of 2017, resulting in total 2017

production near the lower end of revised guidance. With the permitting of Jabali Antenna (currently

scheduled for Q2 2018) gold production for 2018 is expected to reach original 2017 guidance, up to

120,000 ounces. The Company has a successful track record of converting its mineral resources to

reserves. Permitting and development of San Juan, San Diego and Jabali Antenna Permits, combined

with successful conversion of underground resources to reserves at Mojon and Jabali, have the potential

to extend the LoM at La Libertad for an additional two years (past 2018). Mineral resources that are not

mineral reserves do not have demonstrated economic viability. In addition, exploration continues at La

Libertad for additional open pit or underground mineral targets.

El Limon Gold Mine – Nicaragua

El Limon Mine in Nicaragua produced 11,093 ounces of gold in the third quarter of 2017 (Q3 2016 –

14,185 ounces), in-line with revised guidance and a significant improvement compared to 7,740 ounces

produced in the second quarter of 2017. Throughout the year, El Limon's production had been negatively

affected by water pumping issues which had reduced high-grade ore flow from Santa Pancha

Underground. However, with the successful rehabilitation of the Santa Pancha 1 dewatering well at the

beginning of the third quarter, mine output and production grade are now improving. Year-to-date, gold

production at El Limon was 27,694 ounces (YTD 2016 – 35,476 ounces).

During the quarter, four Environmental Impact Assessments ("EIA") were presented to the Nicaraguan

government for approval relating to both open pit and underground mining projects: Mercedes - Aparejo,

Veta Nueva, Santa Emilia South and Mercedes South. The EIA for the Mercedes South Pit has been

approved and the permit process is now advancing to the public consultation phase. Development of this

pit is anticipated to commence in the fourth quarter of 2017 and is expected to provide an open-pit source

to complement underground operations for the duration of 2018.

El Limon's third quarter cash costs, on a per ounce basis, were impacted by the lower than planned

production with cash operating costs of $901 per ounce (Q3 2016 – $682 per ounce) and AISC of $1,409

per ounce (Q3 2016 – $1,067 per ounce), both well above budget. Year-to-date, El Limon's cash

operating costs were $1,050 per ounce (YTD 2016 – $725 per ounce) and AISC were $1,599 per ounce

(YTD 2016 – $1,101 per ounce).

Capital expenditures in the third quarter of 2017 totaled $4.5 million which consisted mainly of

underground development costs for Santa Pancha of $2.3 million, mining development/project costs of

$0.7 million and mobile equipment costs of $0.7 million. For the nine months ended September 30, 2017,

capital expenditures totaled $11.0 million which consisted mainly of underground development costs for

Santa Pancha of $5.9 million, mobile equipment costs of $2.2 million and mining development/project

costs of $1.5 million.

The Company anticipates gold production from Santa Pancha 1 to continue to increase and El Limon's

cash operating costs to decrease in the fourth quarter of 2017. For full-year 2017, El Limon's production is

expected to be at the low end of its revised production guidance range of between 40,000 to 50,000

ounces of gold (original guidance was 50,000 to 60,000 ounces) with cash operating costs and AISC

expected to be at the high end of guidance (of between $815 to $855 per ounce and between $1,415 and

$1,455 per ounce, respectively). In 2018, El Limon's gold production is expected to return to more normal

levels and be between 50,000 and 60,000 ounces.

Ongoing El Limon Exploration and Development

In 2017, El Limon's exploration budget was increased to $7 million to include 28,600 metres of drilling

(over 157 holes) with a focus on El Limon Vein system. The system comprises of the Pozo Bono, Limon

Sur, Limon Central, Limon North and Tigra-Chaparral zones, most of which were previously partially

mined by both open pit and underground methods. Drilling to date has identified a new large good grade

near-surface zone that the Company believes could be exploitable by open-pit mining. This has the

potential to significantly extend the current mine life at El Limon and may support an expansion of El

Limon's milling and production capacity. In November 2017, the Company expects to announce the

results of its 2017 drill campaign.

In 2017, an initial study was completed regarding the potential re-processing of the old tailings at El

Limon. Based on historic mill and drilling records, the tailings contain an estimated 9 million to 11 million

tonnes with a potential gold grade of 0.80 g/t to 1.0 g/t. An ongoing drilling program is underway as part of

a Feasibility Study which will confirm resources and grades, the optimum grind size, capital costs and

final project economics. Based on the initial study completed in 2017, the Company believes that the

project has the potential to produce an average of approximately 20,000 to 25,000 ounces of gold and

70,000 to 80,000 ounces of silver per year for approximately 9 to 11 years. The concept is to regrind the

old tailings to a much finer grind size, process them through a new CIP plant and place the tailings in a

new lined tailings storage facility. The potential quantity and grade included in the initial study is

conceptual in nature and there has been insufficient exploration to date to define a mineral resource and

it is uncertain if further exploration will result in the target being delineated as a mineral resource.

Fekola Gold Mine – Mali