Saturday, September 26, 2026
MiningNewsTerminal
Saturday, September 26, 2026 Admin

BTO.TO ·

B2Gold Corp. Announces Positive Results from the Updated Preliminary Economic Assessment for the Gramalote Project in Colombia and Assumes Role of Manager of the Gramalote Joint Venture

Economic Studies Mergers & Acquisitions Partnerships & JV

News Release

B2Gold Corp. Announces Positive Results from the

Updated Preliminary Economic Assessment for the Gramalote Project in Colombia and

Assumes Role of Manager of the Gramalote Joint Venture

Vancouver, Canada, January 21, 2020 – B2Gold Corp. (TSX: BTO, NYSE AMERICAN: BTG, NSX:

B2G) (“B2Gold” or the “Company”) is pleased to announce positive results from the Updated Preliminary

Economic Assessment (“PEA”) for the Gramalote Ridge deposit (“Gramalote Ridge”) at the Gramalote

gold project in Colombia (the “Gramalote Project ”), a joint venture between B2Gold and AngloGold

Ashanti Ltd (“AGA”). B2Gold assumed the role of manager of the Gramalote joint venture on January 1,

2020. All dollar figures are in United States dollars unless otherwise stated.

Highlights

• Assuming an effective date of January 1, 2020, and a gold price of $1,350 per ounce, Gramalote

Ridge project economic highlights from the PEA (100% basis) include:

o Open-pit gold mine with an initial life of mine (“LoM”) of 13.6 years based on current

Indicated and Inferred Mineral Resources (for Gramalote Ridge only)

o LoM gold production of 3.85 million ounces

o Average annual gold production of 416,600 ounces per year for the first five full years of

production

o Average annual gold production LoM of 283,990 ounces per year at cash operating costs of

$544 per ounce of gold

o Average LoM all-in sustaining costs (“AISC”) of $648 per ounce of gold, and average

LoM all-in costs (including pre-production capital costs) of $882 per ounce of gold

o Annual processing rate of 11.0 million tonnes per annum (“Mtpa”)

o Average LoM gold recovery of 94.3% from conventional milling, flotation and cyanide

leach of the flotation concentrate

o Estimated pre-production capital cost of $901 million (includes approximately $160

million for mining equipment)

o LoM pre-tax net cash flow of $1,827 million, and after-tax net cash flow of $1,283 million

o Assuming a discount rate of 5%, net present value (“NPV”) pre-tax of $1,027 million and

NPV after-tax of $671 million, generating an after-tax internal rate of return (“IRR”) of

18.1% at the project construction decision date (estimated to be January 1, 2021), with a

project payback (including construction capital) of 3.6 years

o Assuming a gold price of $1,500 per ounce and a discount rate of 5%, NPV pre-tax

increases to $1,394 million and NPV after-tax increases to $928 million, generating an

after-tax IRR of 21.9% at the project construction decision date (estimated to be January 1,

2021) and reducing the project payback (including construction capital) to 3.2 years

• Continue ongoing feasibility work to optimize the PEA results and a final feasibility study

expected to be completed by December 31, 2020

• Amended and restated shareholders agreement signed by B2Gold and AGA on December 23,

2019, under which B2Gold agreed to sole fund the next $13.9 million of expenditures on the

Gramalote Project, following which B2Gold and AGA will each hold a 50% ownership interest in

the joint venture (currently 48.3% B2Gold and 51.7% AGA)

• Exploration drilling is ongoing at the Trinidad deposit, with additional drilling at the Monjas zone

to commence later in 2020

The PEA is preliminary in nature and includes Inferred Mineral Resources that are considered too

speculative geologically to have the economic considerations applied to them that would enable them to be

categorized as Mineral Reserves, and there is no certainty that the PEA based on these Mineral Resources

will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated econ omic

viability.

B2Gold is currently completing approximately 42,500 metres of infill drilling at Gramalote Ridge to

convert existing Inferred Mineral Resources to an Indicated category, and 7,645 metres of geotechnical

drilling for site infrastructure.

Gramalote Project Mineral Resource Estimate

The Mineral Resource e stimate for the overall Gramalote Project (100% basis), effective December 31,

2019, within a pit shell run at a gold price of $1,500 per ounce includes:

Indicated Mineral Resource Estimate

Area Tonnes

Gold Grade

(g/t)

Contained Gold

Ounces

Gramalote Sulphide 78,200,000 0.85 2,140,000

Total Indicated Resources 78,200,000 0.85 2,140,000

Inferred Mineral Resource Estimate

Area Tonnes

Gold Grade

(g/t)

Contained Gold

Ounces

Gramalote Oxide 6,000,000 0.61 120,000

Trinidad Oxide 3,100,000 0.55 50,000

Subtotal Oxide Inferred 9,100,000 0.59 170,000

Area Tonnes

Gold Grade

(g/t)

Contained Gold

Ounces

Gramalote Sulphide 105,600,000 0.70 2,370,000

Trinidad Sulphide 14,400,000 0.62 290,000

Subtotal Sulphide Inferred 120,100,000 0.69 2,660,000

Total Inferred Resources 129,200,000 0.68 2,830,000

Notes:

1. Mineral Resources have been classified using the CIM Standards.

2. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

3. The Qualified Person for the Mineral Resource estimate is Tom Garagan, P.Geo., B2Gold’s Senior Vice President,

Exploration.

4. Mineral Resources are reported on a 100% project basis (B2Gold currently holds a 48.3% attributable interest with the

remaining 51.7% interest held by AGA).

5. Mineral Resources for Gramalote assume metallurgical re coveries of 83.9% for oxide and 95% for sulphide, and operating

cost estimates of an average mining cost of $2.13/t mined, processing cost of $3.35/t processed for oxide and $6.58/t process ed

for sulphide, general and administrative cost of $1.89/t process ed and selling cost of $50.52/oz produced.

6. Mineral Resources for Trinidad assume metallurgical recoveries of 81.7% for oxide and 90.9% for sulphide, and operating

cost estimates of an average mining cost of $1.82/t mined, processing cost of $3.35/t processed for oxide and $6.58/t process ed

for sulphide, general and administrative cost of $1.89/t processed and selling cost of $50.52/oz produced.

7. Mineral Resources for Gramalote and Trinidad are reported at cut -offs of 0.15 g/t gold for oxide and 0.20 g/t gold for

sulphide.

8. All tonnage, grade and contained metal content estimates have been rounded; rounding may result in apparent summation

differences between tonnes, grade and contained metal content.

PEA Overview

The Gramalote Project is located in central Colombia, approximately 230 kilometres (“km”) northwest of

Bogota and 120 km northeast of Medellin, in the Province of Antioquia which has expressed a positive

attitude towards the development of responsible mining projects in the region. The PEA was prepared by

B2Gold and evaluates recovery of gold from a an open-pit mining operation that will move up to 143,000

tonnes per day (“tpd”) (50.0 Mtpa), with a 30,137 tpd (11.0 Mtpa) processing plant that includes crushing,

grinding, flotation, with fine grinding of the flotation concentrate and agitated leaching of both the flotation

concentrate and the flotation tails, followed by a carbon-in-pulp recovery process to produce doré bullion.

The PEA is based solely on production from the Gramalote Ridge deposit and does not include potential

production from the nearby Trinidad deposit, which has a current Inferred Mineral Resource e stimate (see

above), and the Monjas West zone . The Mineral Resource estimate for Gramalote Ridge that forms the

basis for the PEA includes Indicated Mineral Resources of 7 0,110,000 tonnes grading 0.92 g/t gold for a

total of 2,070,000 ounces of gold and Inferred Mineral Resources of 79,030,000 tonnes grad ing 0.79 g/t

gold for a total of 2,010,000 ounces of gold.

The PEA updates and enhances the previous studies on the Gramalote Project in several areas, including:

• For Gramalote Ridge, additional drilling has been completed and a new Mineral Resource model

has been developed

• The PEA is based solely on Gramalote Ridge Mineral Resources, where previous studies included

mining and processing ore from the Trinidad deposit and the Monjas West zone

• Recent metallurgical test work has resulted in slightly lower processing costs and improved

economics

• The new Mineral Resource model for Gramalote Ridge includes new interpretations of higher

grade ore zones and has allowed more efficient mine optimization, which has resulted in higher

grade ore being fed to the plant during the first years of production, significantly improving project

economics

• Due to better defined high-grade zones in Gramalote Ridge in the block model, the overall gold

grade for the PEA is 0.85 g/t, which is significantly higher than previous studies

Accelerated mining is planned in the early years of production to provide higher grade feed to the plant

while stockpiling lower grade material. The final four years of plant feed are from low-grade stockpiles and

oxide ore. Oxide ore, which only makes up about 3% of the plant feed, will be stockpiled and processed at

the very end of the project life as blending this material with the fresh ore does not yield optimal gold

recoveries.

The PEA assumptions include revenues using a gold price of $1,350 per ounce and current prices for fuel,

reagents, labo ur, power and other consumables. The key parameters of the PEA are presented in the

following table (100% basis):

Production Profile

Contained gold ounces processed (Moz) 4.082

Gold recovery (%) 94.3

Average gold grade (g/t) 0.85

Gold ounces produced (Moz) 3.85

Average gold production for the first five years (oz) 416,600

Average annual gold production (oz) 283,990

Mine life (years) 13.6

Ore tonnes processed (Mt) 149

Waste material mined (Mt) 288

Waste to ore strip ratio 1.93

Project Economics - $1,350 /oz gold price

Construction capital ($M) 901

Sustaining capital ($M) 103

Gross gold revenue ($M) 5,198

Net cash flow (pre-tax) ($M) 1,827

Net cash flow (after tax) ($M) 1,283

NPV5.0% (pre-tax) ($M) 1,027

NPV5.0% (after tax) ($M) 671

IRR (after tax) (%) 18.1

Payback (years) 3.6

Unit Operating Costs

LoM cash operating costs (mining, processing and site G&A) ($/oz gold) 544

LoM AISC (cash operating costs + royalties, corporate G&A, selling costs and

silver credits and excluding pre-production capital costs) ($/oz gold)

648

LoM all-in costs (AISC and pre-production capital costs) ($/oz gold) 882

Average LoM mining cost ($/t mined) 2.16

Average LoM processing cost ($/t processed) 5.61

Based on the positive results from the PEA, B2Gold believes that the Gramalote Project has the potential

to become a large, low-cost open-pit gold mine, subject to completion of ongoing infill drilling and the

results of a final feasibility study expected by the end of 2020. The Gramalote Project has several key

infrastructure advantages, including:

• Reliable water supply – high rainfall region and located next to the Nus River

• Adjacent to a national highway, which connects directly to Medellin and to a major river with port

facilities, capable of bringing supplies by barge to within 70 km of the site

• Proximity to the national electricity grid with ample low-cost power and a stable record of

hydroelectric power

• Skilled labour workforce within Colombia

In addition, B2Gold expects the Gr amalote Project to benefit from several key operational advantages,

including:

• Excellent metallurgical characteristics of the ore, which results in high recovery rates at low

processing costs

• Relatively low strip ratio in the mine (1.9:1)

• Ability to mine and process higher grade ore in the initial years of the mine life resulting in

improved project economics

The PEA is subject to a number of assumptions and risks , including among others, that a Modified

Environment Impact Study and a Modified Project Implementation plan will be approved within the

required timeline, all required permits and other rights will be obtained in a timely manner, the Gramalote

Project will have the support of the local government and community, the regulatory environment will

remain consistent and no material increase will have occurred to the estimated costs.

Economic Sensitivities

Gramalote is a large, low- grade, low-cost project and sensitive to the gold price , as demonstrated in the

following table:

Gold Price

($/oz)

NPV5%

($M)

After Tax IRR

(%)

Pre-tax Post tax

$1,250 $783 $497 15.2%

$1,300 $905 $585 16.7%

$1,350 $1,027 $671 18.1%

$1,400 $1,150 $757 19.4%

$1,450 $1,272 $842 20.7%

$1,500 $1,394 $928 21.9%

$1,550 $1,516 $1,014 23.2%

$1,600 $1,638 $1,099 24.3%

$1,650 $1,761 $1,185 25.5%

Project Next Steps

B2Gold and AGA have agreed on a budget for the feasibility study on the Gramalote Project of

approximately $37 million through the end of 2020. This budget will fund 42,500 metres of infill drilling

to convert existing Inferred Mineral Resources to the Indicated category, and 7,645 metres of geotechnical

drilling for site infrastructure. The Company currently expe cts to complete all drilling by the end of May

2020. In addition, the budget will fund feasibility work including an updated Mineral Resource estimate,

detailed mine planning, ongoing environmental studies, additional metallurgical test work, engineering and

detailed economic analysis.

The Gramalote joint venture will continue to advance resettlement programs, establish coexistence

programs for small miners, work on health, safety and environmental projects and c ontinue to work with

government and local communities on social programs. B2Gold, as manager, plans to continue the

feasibility work with the goal of B2Gold completing a final feasibility study by December 31, 2020. Due

to the amount of work completed by AGA over the past several years, including extensive testing programs,

the work with local communities and small miners, and the high level of engineering performed in 2017

for an internal study, the work remaining to reach final feasibility is not extensive. The main work program

for feasibility is infill drilling to confirm and upgrade the Inferred Mineral Resources to the Indicated

category.

The Environmental Impact Study and Project Implementation Plans for the Gramalote Project have been

fully approved by the National Authority of Environmental Licenses of Colombia. Due to the desired

modifications to the processing plant and infrastructure locations, a Modified Environment Impact Study

and a Modified Project Implementation plan were submitted and are currently in the final approval process.

If the final economics of the feasibility study are positive and the joint venture makes the decision to develop

Gramalote as an open -pit gold mine, B2Gold would utilize its proven internal mine construction team to

build the mine and mill facilities and operate the mine on behalf of the joint venture.

Qualified Persons

Tom Garagan, Senior Vice President , Exploration at B2Gold, a qualified person under NI 43-101, has

approved the scientific and technical information regarding exploration matters and the Mineral Resource

estimate contained in this news release.

Bill Lytle, Senior Vice President, Operations at B2Gold, a qualified person under NI 43-101, has approved

the scientific and technical information related to operations matters contained in this news release. Mr.

Lytle has visited the Gramalote Project several times since 2009 and has reviewed the mining operations

and has reviewed the technical aspects of the PEA that form the basis for this news release.

About B2Gold Corp.

B2Gold is a low-cost senior gold producer headquartered in Vancouver, Canada. Founded in 2007, today,

B2Gold has three operating gold mines and numerous exploration and development projects in various

countries including the Philippines, Namibia, Mali and Colombia. In 2020, B2Gold forecasts consolidated

gold production of between 1,000,000 and 1,055,000 ounces.

ON BEHALF OF B2GOLD CORP.

"Clive T. Johnson"

President & Chief Executive Officer

For more information on B2Gold, please visit the Company website at www.b2gold.com or contact:

Ian MacLean Katie Bromley

Vice President, Investor Relations Manager, Investor Relations & Public Relations

+1 604-681-8371 +1 604-681-8371

[email protected] [email protected]

The Toronto Stock Exchange and NYSE American LLC neither approve nor disapprove the information contained in

this news release.

Production guidance presented in this news release reflects the total production at the mines B2Gold operates on a

100% basis. Please see our Annual Information Form, dated March 19, 2019 for a discussion of our ownership interest

in the mines B2Gold operates. In respect of La Libertad and El Limon, production guid ance is on a 34% attributed

basis (to reflect B2Gold’s approximate current ownership interest in Calibre).

This news release includes certain “forward- looking information” and “forward- looking statements” (collectively

“forward-looking statements”) within the meaning of applicable Canadian and United States securities legislation,

including: projections; outlook; guidance; forecasts; estimates; and other statements regarding future or estimated

financial and operational performance, gold production and sal es, revenues and cash flows, and capital costs

(sustaining and non-sustaining) and operating costs, including projected cash operating costs and AISC, and budgets;

statements regarding future or estimated mine life, metal price assumptions, ore grades or s ources, gold recovery

rates, stripping ratios, throughput, ore processing; statements regarding anticipated exploration, drilling,

development, construction, permitting and other activities or achievements of B2Gold; and including, without

limitation: consolidated gold production of between 1,000,000 and 1,055,000 ounces in 2020; the results of and

estimates in the Gramalote PEA, including the mine life, average annual gold production, total gold production,

processing rate, capital cost, net present value, pre-tax and after -tax net cash flow and payback; the potential to

convert existing inferred resources to the indicated category; the timing to complete a feasibility study at Gramalote;

the completion and results of a feasibility study at Gramalote; receipt of the final approval of the Modified

Environment Impact Study and the Modified Project Implementation plan from all regulatory authorities, including

the National Authority of Environmental Licenses of Colombia; the potential to develop Gramalote as an open- pit

gold mine and any decision from the joint venture in respect thereof. Estimates of mineral resources and reserves are

also forward-looking statements because they constitute projections regarding the amount of minerals that may be

encountered in the future and/or the anticipated economics of production, should a production decision be made. All

statements in this news release that address events or developments that we expect to occur in the future are forward-

looking statements. F orward-looking statements are statements that are not historical facts and are generally,

although not always, identified by words such as “expect”, “plan”, “anticipate”, “project”, “target”, “potential”,

“schedule”, “forecast”, “budget”, “estimate”, “inte nd” or “believe” and similar expressions or their negative

connotations, or that events or conditions “will”, “would”, “may”, “could”, “should” or “might” occur. All such

forward-looking statements are based on the opinions and estimates of management as of the date such statements

are made.

Forward-looking statements necessarily involve assumptions, risks and uncertainties, certain of which are beyond

B2Gold’s control, including risks and uncertainties identified in the Gramalote PEA and risks associated with or

related to: the volatility of metal prices and B2Gold’s common shares; changes in tax laws; the dangers inherent in

exploration, development and mining activities; the uncertainty of reserve and resource estimates; not achieving

production, cost or other estimates; actual production, development plans and costs differing materially from the

estimates in B2Gold’s feasibility and other studies; the ability to obtain and maintain any necessary permits, consents

or authorizations required for mining activities; environmental regulations or hazards and compliance with complex

regulations associated with mining activities; climate change and climate change regulations; the ability to replace

mineral reserves and identify acquisition opportunitie s; the unknown liabilities of companies acquired by B2Gold;

the ability to successfully integrate new acquisitions; fluctuations in exchange rates; the availability of financing;

financing and debt activities, including potential restrictions imposed on B2Gold’s operations as a result thereof and

the ability to generate sufficient cash flows; operations in foreign and developing countries and the compliance with

foreign laws, including those associated with operations in Colombia and including risks related to changes in foreign

laws and changing policies related to mining and local ownership requirements or resource nationalization generally;

remote operations and the availability of adequate infrastructure; fluctuations in price and availability of energy and

other inputs necessary for mining operations; shortages or cost increases in necessary equipment, supplies and

labour; regulatory, political and country risks, including local instability or acts of terrorism and the effects thereof;

the reliance upon contractors, third parties and joint venture partners; challenges to title or surface rights; the

dependence on key personnel and the ability to attract and retain skilled personnel; the risk of an uninsurable or

uninsured loss; adverse climate and weather conditions; litigation risk; competition with other mining companies;

community support for B2Gold’s operations, including risks related to strikes and the halting of such operations from

time to time; conflicts with small scale miners; failures of inform ation systems or information security threats; the

outcome of the ongoing tax assessment by the Colombian Tax Office (DIAN) in respect of the Gramalote property;

the ability to maintain adequate internal controls over financial reporting as required by law , including Section 404

of the Sarbanes -Oxley Act; compliance with anti -corruption laws, and sanctions or other similar measures; social

media and B2Gold’s reputation; as well as other factors identified and as described in more detail under the heading

“Risk Factors” in B2Gold’s most recent Annual Information Form, B2Gold’s current Form 40-F Annual Report and

B2Gold’s other filings with Canadian securities regulators and the U.S. Securities and Exchange Commission (the

“SEC”), which may be viewed at www.se dar.com and www.sec.gov, respectively (the “Websites”). The list is not

exhaustive of the factors that may affect B2Gold’s forward-looking statements.

B2Gold’s forward-looking statements are based on the applicable assumptions and factors management consi ders

reasonable as of the date hereof, based on the information available to management at such time. These assumptions

and factors include, but are not limited to, assumptions contained in the Gramalote PEA and assumptions and factors

related to B2Gold’s ability to carry on current and future operations, including: development and exploration

activities; the timing, extent, duration and economic viability of such operations, including any mineral resources or

reserves identified thereby; the accuracy and reliability of estimates, projections, forecasts, studies and assessments;

B2Gold’s ability to meet or achieve estimates, projections and forecasts; the availability and cost of inputs; the price

and market for outputs, including gold; the timely receipt of necessary approvals or permits; the ability to meet current

and future obligations; the ability to obtain timely financing on reasonable terms when required; the current and

future social, economic and political conditions; and other assumptions and factors generally associated with the