Bunker Hill Provides October 2022 Project Restart Update

Corporate Updates

BUNKER HILL PROVIDES OCTOBER 2022 PROJECT RESTART UPDATE

Live 6ix Summit Today, Thursday November 3 @ 11:00am ET / 8:00am PT

HIGHLIGHTS

• Demolition activities at Pend Oreille site completed ahead of schedule and under budget

• Procurement of new Bunker Hill mill building initiated , concurrent with abatement and demolition of

existing mill building. Geotechnical drilling for mill foundations completed

• Winter weather plan finalized with all mill equipment secured; other site preparation activities ongoing

• Underground decline continues to advance with excavation of primary vent fan drift

• CEO Sam Ash and CFO David Wiens to host interactive 6ix investor event today, Thursday November 3 at

11:00am ET / 8:00am PT. Investors are invited to register at: [LINK]

TORONTO, November 3, 2022 – Bunker Hill Mining Corp. (the “Company”) (CSE: BNKR, OTCQB: BHLL) is pleased

to provide an update on restart project activities during the month of October 2022.

Sam Ash, CEO stated: “Project advancement continued at pace in October, most notably the early and successful

completion of demolition activities at the Pend Oreille site. With the mill now fully demobilized and ready to

construct, site preparation has begun in earnest to ensure the project remains on track. Geotechnical drilling for

the mill foundations is already complete, building designs are being finalized together with Strike, our PCM

partner, and required abatement and demolition activit ies have begun. In the underground mine , the

development drift is progressing well , excavation of the primary vent fan location is underway , and we are on

course to break through to the 6-Level over the coming weeks.”

PEND OREILLE MILL DEMOBILIZATION AND DEMOLITION COMPLETE

Demolition activities at the Pend Oreille site safely concluded on Oct 2 8, 2022, ahead of planned completion in

November and marking the completion of the project which began in May 2022 with the dismantling and removal

of critical equipment. The former crusher and mill buildings have been reduced to their foundations, the conveyor

that fed fine ore from the surface crushers to the concrete silos has been removed, and all material that has not

yet been transported off site has been segregated into stockpiles of metal, concrete and debris. This milestone

ensures that the Bunker H ill site is furnished with fit-for-purpose crushing, grinding, flotation and thickening

equipment and instrumentation, representing the vast majority of equipment needs for the mine restart. Project

activities are now exclusively focused on site preparation and construction. The project benefitted from strong

support from the onsite Pend Oreille team and was completed safely, ahead of schedule and under budget.

Final state of the Pend Oreille Crusher Building (L) and Mill Building (R)

BUNKER HILL MILL SITE PREPARATION ACTIVITIES INITIATED

After an extensive evaluation process the Company has appointed Rivers Edge Environmental Services as its

partner for critical site demolition activities at Bunker Hill. Rivers Edge is a fully licensed remediation, excavation

and demolition company headquartered in Washington State, USA. Permits have been secured and Rivers Edge

teams have mobilized to site , undergone site specific safety training and initiated demolition activities

encompassing abatement, building removal, foundation extraction and related earthworks. These activities are

expected to conclude by the end of 2022, ensuring readiness for the new mill building that is being procured. The

new mill building will utilize the existing building footprint and is expected to arrive in 2023.

In parallel with the mobilization of Rivers Edge, geotechnical drilling was performed at the end of October to

inform detailed foundational planning for the new mill building.

Drilling in the main Bunker Hill yard in late October to inform the foundational design for the new Mill Building

UNDERGROUND DEVELOPMENT ADVANCING - VENT DRIFT EXCAVATION INITIATED

As part of the restart plan, a decline continues to be driven from ‘5 Level’ (the highest accessible level of the mine)

to ‘6 Level’. The decline advanced steadily through the month of October, progressing 286 feet, with a current

focus on excavation of a primary fan drift that will house a 7-foot fan integral to the overall mine ventilation plan

when breakthrough to 6 Level is achieved before the end of the year.

Engineering design of primary fan drift that is currently being excavated between the 5 & 6 Levels

QUALIFIED PERSON

Mr. Scott E. Wilson, CPG, President of RDA and a consultant to the Company, is an independent “qualified person”

as defined by NI 43-101 and is acting as the qualified person for the Company. He has reviewed and approved the

technical information summarized in this news release.

ABOUT BUNKER HILL MINING CORP.

Under new Idaho -based leadership the Bunker Hill Mining Corp, intends to sustainably restart and develop the

Bunker Hill Mine as the first step in consolidating a portfolio of North American mining assets with a focus on

silver. Information about the Compa ny is available on its website, www.bunkerhillmining.com, or within the

SEDAR and EDGAR databases.

For additional information contact:

David Wiens, CFA

CFO & Corporate Secretary

+1 208 370 3665

[email protected]

Cautionary Statements

Certain statements in this news release are forward-looking and involve a number of risks and uncertainties. Such

forward-looking statements are within the meaning of that term in Section 27A of the Securities Act of 1933, as

amended, and Section 21E of the Securities Exchange Act of 1934, as amended, as well as within the meaning of

the phrase ‘forward-looking information’ in the Canadian Securities Administrators’ National Instrument 51-102 –

Continuous Disclosure Obligations. Forward -looking statements are not comprised of historical facts. Forward -

looking statements include estimates and statements that describe the Company’s future plans, objectives or

goals, including words to the effect that the Company or management expects a stated condition or result to occur.

Forward-looking statements may be identified by such terms as “believes”, “anticipates”, “expects”, “estimates”,

“may”, “could”, “would”, “will”, or “plan”. Since forward -looking statements are based on assumptions and

address future events and conditions, by their very nature they involve inherent risks and uncertainties. A lthough

these statements are based on information currently available to the Company, the Company provides no

assurance that actual results will meet management’s expectations. Risks, uncertainties and other factors involved

with forward-looking information could cause actual events, results, performance, prospects and opportunities to

differ materially from those expressed or implied by such forward-looking information.

Forward looking information in this news release includes, but is not limited to, the Company’s intentions regarding

its objectives, goals or future plans and statements, the envisaged outcomes from the PFS, the capabilities of the

ball mill, estimated completion time for the demolition of the Pend Oreille site, the timing of the planned r estart

of the Bunker Hill Mine, Strike’s ability to refine the master schedule for the project and drive engineering and

other studies, the decline of the ramp at the Bunker Hill Mine’s facilitation of access to existing internal ramp

systems and the accretive opportunities identified in the PFS . Factors that could cause actual results to differ

materially from such forward -looking information include, but are not limited to: the ability to predict and

counteract the effects of COVID -19 on the busi ness of the Company, including but not limited to the effects of

COVID-19 on the price of commodities, capital market conditions, restriction on labor and international travel and

supply chains; failure to identify mineral resources; failure to convert estimated mineral resources to reserves; the

preliminary nature of metallurgical test results; the Company’s ability to restart and develop the Bunker Hill Mine

and the risks of not basing a production decision on a feasibility study of mineral reserves demonstrating economic

and technical viability, resulting in increased uncertainty due to multiple technical and economic risks of failure

which are associated with this production decision including, among others, areas that are analyzed in more detail

in a feasibility study, such as applying economic analysis to resources and reserves, more detailed metallurgy and

a number of specialized studies in areas such as mining and recovery methods, market analysis, and environmental

and community impacts and, as a re sult, there may be an increased uncertainty of achieving any particular level

of recovery of minerals or the cost of such recovery, including increased risks associated with developing a

commercially mineable deposit with no guarantee that production will begin as anticipated or at all or that

anticipated production costs will be achieved; failure to commence production would have a material adverse

impact on the Company's ability to generate revenue and cash flow to fund operations; failure to achieve the

anticipated production costs would have a material adverse impact on the Company's cash flow and future

profitability; delays in obtaining or failures to obtain required governmental, environmental or other project

approvals; political risks; changes in equity markets; uncertainties relating to the availability and costs of financing

needed in the future; the inability of the Company to budget and manage its liquidity in light of the failure to obtain

additional financing, including the ability of the Company to complete the payments pursuant to the terms of the

agreement to acquire the Bunker Hill Mine Complex; inflation; changes in exchange rates; fluctuations in

commodity prices; delays in the development of projects; capital, operating and reclamation co sts varying

significantly from estimates and the other risks involved in the mineral exploration and development industry; and

those risks set out in the Company’s public documents filed on SEDAR. Although the Company believes that the

assumptions and factors used in preparing the forward -looking information in this news release are reasonable,

undue reliance should not be placed on such information, which only applies as of the date of this news release,

and no assurance can be given that such events will occur in the disclosed time frames or at all. The Company

disclaims any intention or obligation to update or revise any forward -looking information, whether as a result of

new information, future events or otherwise, other than as required by law. No stoc k exchange, securities

commission or other regulatory authority has approved or disapproved the information contained herein.