Bunker Hill Provides November 2022 Project Restart Update

Corporate Updates

BUNKER HILL PROVIDES NOVEMBER 2022 PROJECT RESTART UPDATE

Live 6ix Summit Tuesday December 6 @ 2:00pm ET / 11:00am PT

HIGHLIGHTS

• Abatement of maintenance shop complete, demolition to prepare for new mill building underway

• Commitment made to new Bunker Hill pre-engineered mill building design and vendor

• Underground decline advances to within 300 feet of breakthrough to 6-Level

• Preparation for Wardner Power upgrade advanced with pole locations surveyed, cable corridor cleared,

transformers set and air switch and electrical ancillaries received on site

• CEO Sam Ash and CFO David Wiens to host interactive 6ix investor event, Tuesday December 6 at

2:00pm ET / 11:00am PT. Investors are invited to register at: [LINK]

TORONTO, December 1, 2022 – Bunker Hill Mining Corp. (the “Company”) (CSE: BNKR, OTCQB: BHLL) is pleased

to provide an update on restart project activities during the month of November 2022.

Sam Ash, CEO stated: “With the Pend Oreille demobilization complete, our full focus in November was at Bunker

Hill, with excellent progress made above and below ground. We are excited about declaring three major

milestones in the near future: full demolition of the maintenance shop in preparation for mill construction, the

safe and successful breakthrough to the 6 -Level, and the purchase of the ball mill that is capable of i ncreasing

production throughput levels to 2,100 tons per day, subject to future detailed mine planning and engineering.”

DEMOLITION ACTIVITIES IN PREPARATION FOR MILL CONSTRUCTION

After successful demolition activities at Pend Oreille, the team’s focus switched to preparation for the demolition

of the maintenance shop on site at Bunker Hill. As reported in the Company’s news release of November 3, 2022,

the Company selected Rivers Edge Environmental Services, a fully licensed remediation, excavation and

demolition company headquartered in Washington State, USA for this work. Activity in November began with the

abatement phase that included removal, after necessary permits were first procured, of the roofing and side

shingles of the structure, in accordance with hazardous assessment protocols. After successful completion of this

work the windows were removed from the structure, allowing general demolition to commence at the end of

November. Full building demolition is expected by the end of 2022. Thereaf ter, focus will switch to removal of

the historic concrete base in preparation for more substantial foundations to support mill construction. The full

demolition scope also includes removal of a pre-existing retaining wall and some earthworks.

Demolition of the maintenance shop in preparation for mill construction is now fully underway

COMMITMENT TO NEW BUNKER HILL MILL BUILDING AND FINALIZATION OF DESIGN

After evaluating multiple options, the Bunker Hill team has committed to a final design for a Pre-Engineered Metal

Building (the “PEMB”) to house the mill, once constructed. The design is bespoke for the finalized equipment

arrangement, is fully compliant with all building and environmental codes and regulations, and will house a full -

length o verhead crane that is compatible with planned equipment mezzanine levels. The timing of the

commitment aligns fully with the planned project restart timeline and represents a key long-lead item.

Concurrent with the PEMB focus, the project team has significantly advanced engineering on a concentrate load-

out building, has selected a vendor for the ore silo structure, and has progressed conveyor and crusher designs.

Bunker Hill has committed to its PEMB of choice

UNDERGROUND DEVELOPMENT NEARING BREAKTHROUGH TO 6 LEVEL

As part of the restart plan the 1,800-foot decline from the 5-Level (the highest accessible level of the mine) to the

6-Level is nearing completion, wi th less than 300 feet remaining. Breakthrough is anticipated at approximately

the end of 2022, at which point the focus of underground activities will switch to rehabilitation of the pre-existing

decline from the 6-Level to the 8-Level. During November, the ventilation drift adjoining this decline was advanced

to support the long-term ventilation plan and adjustments were made to the existing ventilation plan to ensure

optimal conditions are maintained through to breakthrough.

The decline from 5 Level to 6 Level has less than 300 feet remaining

WARDNER POWER UPGRADE

At the Wardner area, which serves as the above -ground base for mining operations, ongoing activities include

preparation for a significant power upgrade which will reduce dependence on diesel generators and enable access

to lower-cost, reliable green power. During the course of November, activities included clearing a corridor across

the Bunker Hill property for cables, setting a transformer, surveying pole locations and inspecting and audit ing

equipment that arrived on site including the air switch and pole ancillaries. The power upgrade will include

support from Avista to upgrade the external supply capacity and is planned for completion in early 2023.

QUALIFIED PERSON

Mr. Scott E. Wilson, CPG, President of RDA and a consultant to the Company, is an independent “qualified person”

as defined by Canadian National Instrument 43 -101 Standards of Disclosure for Mineral Projects and is acting as

the qualified person for the Company. He has reviewed and approved the technical information summarized in

this news release.

ABOUT BUNKER HILL MINING CORP.

Under new Idaho -based leadership the Bunker Hill Mining Corp, intends to sustain ably restart and develop the

Bunker Hill Mine as the first step in consolidating a portfolio of North American mining assets with a focus on

silver. Information about the Company is available on its website, www.bunkerhillmining.com, or within the

SEDAR and EDGAR databases.

For additional information contact:

David Wiens, CFA

CFO & Corporate Secretary

+1 208 370 3665

[email protected]

Cautionary Statements

Certain statements in this news release are forward-looking and involve a number of risks and uncertainties. Such

forward-looking statements are within the meaning of that term in Section 27A of the Securities Act of 1933, as

amended, and Section 21E of the Securities Exchange Act of 1934, as amended, as well as within the meaning of

the phrase ‘forward-looking information’ in the Canadian Securities Administrators’ National Instrument 51-102 –

Continuous Disclosure Obligations. Forward -looking statements are not comprised of historical facts. Forward -

looking statements include estimates and statements that describe the Company’s future plans, objectives or

goals, including words to the effect that the Company or management expects a stated condition or result to occur.

Forward-looking statements may be identified by such terms as “believes”, “anticipates”, “expects”, “estimates”,

“may”, “could”, “would”, “will”, or “plan”. Since forward -looking statements are based on assumptions and

address future events and conditions, by their very nature they involve inherent risks and uncertainties. A lthough

these statements are based on information currently available to the Company, the Company provides no

assurance that actual results will meet management’s expectations. Risks, uncertainties and other factors involved

with forward-looking information could cause actual events, results, performance, prospects and opportunities to

differ materially from those expressed or implied by such forward-looking information.

Forward looking information in this news release includes, but is not limited to, the Company’s intentions regarding

its objectives, goals or future plans and statements, the envisaged outcomes from the PFS, the capabilities of the

ball mill, estimated completion time for the demolition of the Pend Oreille site, the timing of the planned r estart

of the Bunker Hill Mine, Strike’s ability to refine the master schedule for the project and drive engineering and

other studies, the decline of the ramp at the Bunker Hill Mine’s facilitation of access to existing internal ramp

systems and the accre tive opportunities identified in the PFS. Factors that could cause actual results to differ

materially from such forward-looking information include, but are not limited to: the Company’s inability to raise

capital, including completion of the proposed public offering as publicly disclosed on November 22, 2022; the ability

to predict and counteract the effects of COVID-19 on the business of the Company, including but not limited to the

effects of COVID-19 on the price of commodities, capital market conditions, restriction on labor and international

travel and supply chains; failure to identify mineral resources; failure to convert estimated mineral resources to

reserves; the preliminary nature of metallurgical test results; the Company’s ability to restart and develop the

Bunker Hill Mine and the risks of not basing a production decision on a feasibility study of mineral reserves

demonstrating economic and technical viability, resulting in increased uncertainty due to multiple technical and

economic risks of failure which are associated with this production decision including, among others, areas that

are analyzed in more detail in a feasibility study, such as applying economic analysis to resources and reserves,

more detailed metallurgy and a number of speci alized studies in areas such as mining and recovery methods,

market analysis, and environmental and community impacts and, as a result, there may be an increased

uncertainty of achieving any particular level of recovery of minerals or the cost of such reco very, including

increased risks associated with developing a commercially mineable deposit with no guarantee that production

will begin as anticipated or at all or that anticipated production costs will be achieved; failure to commence

production would have a material adverse impact on the Company's ability to generate revenue and cash flow to

fund operations; failure to achieve the anticipated production costs would have a material adverse impact on the

Company's cash flow and future profitability; delays in obtaining or failures to obtain required governmental,

environmental or other project approvals; political risks; changes in equity markets; uncertainties relating to the

availability and costs of financing needed in the future; the inability of the Com pany to budget and manage its

liquidity in light of the failure to obtain additional financing, including the ability of the Company to complete the

payments pursuant to the terms of the agreement to acquire the Bunker Hill Mine Complex; inflation; changes in

exchange rates; fluctuations in commodity prices; delays in the development of projects; capital, operating and

reclamation costs varying significantly from estimates and the other risks involved in the mineral exploration and

development industry; and those risks set out in the Company’s public documents filed on SEDAR , including the

Company’s preliminary prospectus dated November 21, 2022, and in the Company’s filings with the Securities and

Exchange Commission. Although the Company believes that the assumptions and factors used in preparing the

forward-looking information in this news release are reasonable, undue reliance should not be placed on such

information, which only applies as of the date of this news release, and no assurance can be given that such events

will occur in the disclosed time frames or at all. The Company disclaims any intention or obligation to update or

revise any forward-looking information, whether as a result of new information, future events or otherwise, other

than as required by law. No stock exchange, securities commission or other regulatory authority has approved or

disapproved the information contained herein.